Document BypqgXOOQRv6N2KznXgOqzwkw

Interoffice Communication To From Da,e Sub|Bct R. D. Gamblin -Houston J. A. DeBernardi April 16, 1982 Maintenance AFE to Retube H-110A The following criteria have been met for the subject AFE. 1) The project cost of $26,000 is based on a definitive estimate and includes an escalation allowance. 2) Funds will be committed for this project immediately after approval. 3) The entire project will be expensed. 4) Project completion is estimated to be two months after AFE approval. 5) This project will not change plant operating costs. cc: JRH-JHB-RB-JWW CCR 000067294 (conoco) Conoco Inc. Conoco Chemicals Authority for Expenditure Project Title Retube H-110A Budget Proj. No. AFE No. 08- Check if partial AFE Location Aberdeen Baltimore Hammond DUCCP Newark DOKC Xfe VCM .__________________________ Project Category Plant Expansion & Modernization Cost Savings -- Energy Cost Savings -- Ocher Safety & Health P Mainf-pnanro Requested Capital _____________________ Expense . --$26,000.00 Product Improvement Pollution Abatement: Water Air Land Noise Miscellaneous Budgeted Capital _______________________ Expense $33r 1 Rfl. HO Source of Capital Budget Unallocated Transfer Over Commitment Project Description The tubes in H-11QA, EDC Product Cooler, have corroded to the point that the exchanger is no longer suitable for service. It must be retubed and installed in place of H-110B to maintain efficient operation. ... Summary of Estimated Cost Contract Cash and Wa i louse Outlay $26,000 0C ' * 'Ri Distribution RDG-RFW-BRJ-JAB-WHH-JAD-JHB-OWW-JRH-RB-FILE Total Approved By Supt./Mech. Supt ~P' .... 4Mb*-, y//^/e2_ Grand Total Approved By Manager of Manufacturing Vice President $26,000 $26,000 18-103 PA.11-79 AFE No. 08- CCR 000067295