Mr. Eric Holder Environmental Health & Safety Manager Independence Power & Light City of Independence P.O. Box 1019 Independence, MO 64051-0519
Dear Mr. Holder:
Information Request
The U.S. Environmental Protection Agency is seeking information about the management of Coal Combustion Residuals ("CCR") managed in the Bottom Ash Pond, North Fly Ash Pond and South Fly Ash Pond at the Blue Valley Generating Station owned/operated by the City of Independence located at 21500 E Truman Road, Independence, Missouri (hereinafter referred to as the "referenced facility"). CCR are regulated under a comprehensive set of regulatory requirements for the management of CCR in landfills and surface impoundments. 40 C.F.R. Part 257. These regulations were promulgated pursuant to Subtitle D of the Resource Conservation and Recovery Act ("RCRA"), as amended in 2016 by the Water Infrastructure Improvements for the Nation ("WIIN") Act. Together, these authorities establish a framework for the handling and management of CCR and grant the Administrator the authority to use Section 3007 of RCRA to obtain requested information to evaluate compliance and Section 3008 of RCRA to enforce the prohibition on open dumping under Section 4005(a), 42 U.S.C. 6945(a), with respect to CCR units (42 U.S.C. 6945(d)(4)(A)(i).
Enclosed with this letter are instructions, requested information, and a certification that should be signed by someone authorized to sign on behalf of the City of Independence. Please carefully read and follow the instructions. The referenced facility's response to this request, in accordance with the instructions, is required, and substantial penalties may result for not complying. Please note that the EPA retains its authority to pursue appropriate enforcement actions, including penalties, for violations discovered as a result of EPA's review of the referenced facility's response to this letter, regardless of whether the violations were subsequently corrected.
The EPA strongly encourages submittal of electronic responses. Response files larger than 25 megabytes may be broken into smaller files for transmission in separate e-mails to the following email address:
Cynthia Sans (ECAD-WB) Case Review Officer U.S. Environmental Protection Agency, Region 7 sans.cynthia@epa.gov 913-551-7492
If you prefer to utilize a cloud-based system to share larger documents or if you are unable to provide your response electronically, notify the EPA contact to receive further instruction.
Any documents claimed as confidential business information should not be sent electronically. Such document should be marked and mailed to:
Cynthia Sans (ECAD-WB) Case Review Officer U.S. Environmental Protection Agency, Region 7 sans.cynthia@epa.gov 913-551-7492
Questions regarding submission of documents claimed as confidential business information should be directed to Ms. Sans before transmitting the documents. Additional information regarding confidential business information can be found in the 3007 Response Instructions enclosed with this letter.
Please submit your response to this information request within 30 calendar days of receiving this letter. We appreciate your prompt response to this letter.
Sincerely,
JODI BRUNO
Digitally signed by JODI BRUNO Date: 2023.10.23 15:34:58 -05'00'
David Cozad Director Enforcement and Compliance Assurance Division
Enclosures: 1. 3007 Response Instructions 2. Statement of Certification 3. Requested Information
cc: Greg Snellen, MoDNR
2
RCRA 3007 RESPONSE INSTRUCTIONS
Identify the person(s) responding to this request.
Address each numbered item separately and precede each answer with the number of the item to which it responds.
For each numbered item, identify all documents consulted, examined, or referred to in the preparation of the answer, or that contain information responsive to the requested item. Provide true, accurate, and legible copies of all such documents. (If information responsive to an item is available but there are no relevant source documents, you must still provide the information.)
For each document provided, indicate on the document (or in some similar manner) the number of the item to which it responds.
For each numbered item, identify all persons consulted in the preparation of the answer.
For purposes of this request, the term "you" or "the referenced facility" refers to the city, municipality, and any public official, officer, principal, agent employee, or any other person(s) associated in any capacity.
If information responsive to a requested item is not in your possession, identify the person(s) from whom the information may be obtained.
If information that is not known or available at the time you make your response later becomes known or available to you, you must supplement your response.
If, at any time after you submit your response, you find that any part of the information you submitted is incomplete, false, or misrepresents the truth, you must notify the EPA immediately.
You must provide the requested information even though you consider it confidential information or trade secrets. If you want to make a confidentiality claim covering part or all the information submitted, identify the material with words such as "trade secret," "proprietary," or "company confidential."
The EPA will disclose this information only to the extent and by the means described in 40 C.F.R. Part 2, Subpart B., if it qualifies as confidential business information.
The Code of Federal Regulations may be accessed at https://www.epa.gov/lawsregulations/regulations.
This request for information is not subject to the approval requirements of the Paperwork Reduction Act of 1980.
The EPA encourages you to conserve resources. Suggested methods include use of recycled paper, printing on both sides (duplex printing), and when possible, submitting documents electronically (i.e., email or compact discs). If hard copy submittals are necessary, please do not submit documents in binders.
Not responding to this information request within the stated time limit and in accordance with these instructions may subject your municipality to an enforcement action which could include the imposition of significant penalties per violation, per day of continued noncompliance. Providing false, fictitious, or fraudulent statements or representations could lead to criminal penalties.
2
STATEMENT OF CERTIFICATION I certify that I am authorized to respond to this information request on behalf of Blue Valley Generating Station, City of Independence. I certify under penalty of law that I have examined and am familiar with the information submitted in this document and all attachments and that, based on my inquiry of those individuals immediately responsible for obtaining the information, I believe that the information is true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fines and imprisonment. Executed on (date)
(Signature)
(Printed Name)
(Title)
(Entity)
NOTE: For the purposes of this form, your typed name, title and date as an electronic signature is equivalent to your valid signature on a paper copy of the form. As such, this electronically completed form bears the same rights and responsibilities as a hand-signed form.
3
LIST OF REQUESTED INFORMATION
Blue Valley Generating Station Independence, Missouri
The EPA has reviewed the documentation placed on Blue Valley Generating Station's publicly available webpage as it relates to the Coal Combustion Residuals Rule and it appears the Facility initially intended to close the North Fly Ash Pond, South Fly Ash Pond, and Bottom Ash Pond in accordance with the early closure provisions under 257.100(b). Those provisions were subsequently vacated by the United States Court of Appeals for the District of Columbia Circuit1 on June 14, 2016. Following vacatur, these units became subject to all the requirements for existing CCR surface impoundments and the EPA extended the compliance deadlines for the affected units. These new requirements were established in a direct final rule on August 5, 20162. On May 7, 2019, the EPA sent correspondence to all facilities regulated under the CCR rule reminding them of the obligation to post required documents on their CCR webpage (letter attached). It appears the Blue Valley Generating Station's website has not been updated to include the required documents. Accordingly, the EPA is seeking the following information:
1. Identify the person(s) answering these questions on behalf of the referenced facility. Additionally, please provide the name, title, mailing address, email, and phone number for each identified person.
2. Provide a separate response for each unit identified above (i.e. the Bottom Ash Pond, North Fly Ash Pond, South Fly Ash Pond, and any additional units not identified above that are subject to the CCR Rule).
3. The table below lists the required documents and the dates they were due. For each required document, please:
a. Provide a copy of the required document which is required to be maintained in the facility's operating record.
b. Note on the table below when it was placed in the operating record. c. Explain the City of Independence's progress in preparing the required document if it
does not have the document and provide a date when it will be provided to the EPA. d. Describe the basis of any conclusion by the City of Independence that preparation of
any of the required documents are not required.
1 See Per Curiam Order, Utility Solid Waste Activities Grp. v. EPA, No. 15-1219 (D.C. Cir. June 14, 2016). 2 https://www.federalregister.gov/documents/2016/08/05/2016-18353/hazardous-and-solid-waste-management-systemdisposal-of-coal-combustion-residuals-from-electric
Federal CCR Citation 257.64(d)(1) 257.80(b)(5) 257.80(c) 257.81(c)(3) 257.84(b)(3)
257.90(e)
257.91(f) and
Requirement Unstable areas demonstration
Deadline to PREPARE Oct 17, 2018
Deadline to POST Nov 16, 2018
Initial fugitive dust control plan
Initial annual CCR fugitive dust control report 2nd annual CCR fugitive dust control report 3rd annual and subsequent CCR fugitive dust control reports Initial run-on and run-off control system plan Report by PE following initial annual inspection Report by PE following 2nd annual inspection Report by PE following 3rd annual and subsequent inspections Initial annual groundwater monitoring and corrective action report 2nd annual groundwater monitoring and corrective action report 3rd annual and subsequent groundwater monitoring and corrective action report
Groundwater monitoring system
Oct 19, 2015 Dec 19, 2016 Dec 19, 2017 Dec 19, 20XX Oct 17, 2016 Jan 19, 2016 Jan 19, 2017 Jan 19, 20XX
Jan 31, 2018
Jan 31, 2019
Jan 31, 20XX Oct 17, 2017
Nov 19. 2015 Jan 18, 2017 Jan 18, 2018 Within 30 days of
Dec 19 Nov 16, 2016 Feb 18, 2016 Feb 20, 2017 Within 30 days of
Jan 19
Mar 2, 2018
Mar 4, 2019
Within 30 days of Jan 31
Nov 16, 2017
Date POSTED
Federal CCR Citation 257.90(b)(1)(i)
Requirement certification
Deadline to PREPARE Deadline to POST
257.93(f)(6) and 257.90(b)(1)(i) 257.94(e)(3)
257.95(g) 257.95(g)(2) 257.95(g)(5) 257.96(d) 257.102(b)(2) 257.102(b)(3)(iii)
257.102(g)
257.102(k) 257.102(k)(5)
Statistical method certification Notification that an assessment monitoring program has been established Notification that Appendix IV constituents have been detected at SSI above GWPS Notification to land owners Notification of initiation of corrective measures Assessment of corrective measures Initial closure plan
Amended closure plan
Notification of intent to close CCR unit
Initial retrofit plan
Notification of intent to retrofit
Oct 17, 2017
If triggered
If triggered
If triggered
If triggered
If triggered Oct 17, 2016 At least 60 days prior to change in operation of facility
or unit No later than the date the owner or operator initiates
closure 60 days prior to initiating retrofit Site-specific, if
3
Nov 16, 2017
Within 30 days
Within 30 days
Within 30 days Within 30 days Within 30 days Nov 16, 2016 Within 30 days of
amending
Within 30 days
Within 30 days of completing the
plan Within 30 days
Date POSTED
Federal CCR Citation 257.104(d)(2) 257.104(d)(3)(iii)
Requirement CCR unit Initial post-closure care plan
Amended post-closure care plan
Deadline to PREPARE applicable
Oct 17, 2016 At least 60 days prior
to change in operation of facility
or unit
Deadline to POST
Nov 16, 2016 Within 30 days of
amending
Date POSTED