ASBESTOS GASKET PLAN FOR TEXAS CITY
//'
PURPOSE:
Eliminate the use of asbestos gaskets.
SCOPE:
Applies to gaskets for replacement, repair or new installation but does not require wholesale change out of all asbestos gaskets presently within Texas City.
TIMING:
Implementation 3rd Q 1985
PLAN:
I. Determine materials to be used as replacement.
B. J. Sanders 1/15/85
II. Develop engineering standards for replacement materials by class of service.
III.
Jon Bullock 2/1/85
Complete initial Loss Prevention Review with Safety on test program.
B. J. Sanders 2/15/85
IV. Develop field test program with SM, AN, PA, Oxo-Esters, Acetic, Methanol, HCN Complex, Power II, Lactic Acid as required.
Gatewood/Bailey Samples installed 3/1/85 Gatewood/Bailey Testing Complete 6/1/85
V. VI.
VII. VIII.
Prepare replacement lists by MCC number for Stores ordering.
PETS, Purchasing, Stores 6/3/85
Review results of field tests and determine exceptions. Modify MCC number lists as required.
B. J. Sanders 7/1/85
Complete Loss Prevention Review for project.
B. J. Sanders 7/19/85
Present data to manufacturing superintendent for approval.
B. J. Sanders 7/26/85
6113 19163
LAM021820
r2- -
IX. Stores orders gaskets.
Stores, Purchasing 8/1/85
X. Conduct training sessions for craftsmen.
PETS 9/2/85
XI. Replace material in Stores bins and begin use of non-asbestos material.
Stores 10/1/85