Document 93NxyV2Q41oyEG76v30roV6pD
(conoco)
/
Interoffice Communication
to J. F. Pinkman - Houston From J. w. Ware
ate June 24, 1980
subject
"Mundogas Brasilia" * March, 1980 Lifting Lake Charles VCM Plant
This letter is in response to your IOC to H. D. Garrison dated June 3, 1980. I have attached documentation relevant to this lifting which is fairly comprehensive.
One comment I would like to add is that "freeze-up" of the process side of the plant vent refrigeration unit has been linked on several occasions to wet heel samples from the ship (see attached IOC to R. Parker from J. W. Ware dated June 6, 1980). Experience gained from the "Brasilia" and other recent liftings which have caused these "freeze-ups" will lead to a more timely and appropriate response by plant personnel in the future. The fact remains, however, that the underlying cause of these "freeze-ups" (and the resulting loading delays) is moisture from the ship.
J. W. Ware
is Enc
VVC 000019294
i -v>
(conoco)
Interoffice Communication
To
Prom Data
H. Garrison John F. Pinkman
October 31, 1973
Subject VCM SHIP VENT RECOVERY MODIFICATIONS
Since receiving your letter of September 19, I have been- in contact with Unigas concerning the problem raised in your memo.
I understand instructions were issued to the captain of the "DeltagasM in order that this problem might be overcome. My understanding is that the potential solution did not work.
1 have just received a letter and piping diagram from Herman Bouwmeester, Unigas1 operation manager in which he points out the problem on the "Deltagas" and what
they plan to do on' the "E.ps i 1 ongasJ1. I understand the "EpsHongas" has just been loaded.
Would you look at these piping diagrams and Herman's letter, then let me have your comment.
/Pj cc: REL, RDG, JAD, JWW, JD
VVC 000019295