Interoffice Alcmoraudam
TO (Nm and locillM)
Mr. C. J. Schaefer
F ROM (N*m and location)
Mr. J. j. Fritsch
c
OATE
_ 7/1/85__________ _
REFERENCE NO.
JJF-119-85
SUBJECT: Second Quarter 1985 Safety Audit Update gelanese Chemical Company 1985 Audit
There are two items incomplete at this time from the subject audit.
Findings No. 3-84
The contractor safety audits are currently being scheduled. This item will be completed by the end of August.
Finding No. 14-84
The contractor safety booklet is currently being printed. The slide programs are complete. The QAT to implement Contractor Safety Orientation will be commissioned in July. This item is scheduled for completion by September 30, 1985.
JJF:EAT/bjw