mmmcAH VP OIL BOILER
INSTRUCTION MANUAL
PACKAGED OIL HEATING UNITS
FORM NO. 32425-j^_04
NOTICE TO INSTALLER AND OPERATOR THIS BOOKLET MUST BE AFFIXED ON OR ADJACENT TO THE HEATING EQUIPMENT.
06955
To the homeowner:
The American-Standard boiler which has been installed for you is the heart of your hydronic heating system. Since the performance of your syBtem depends upon the boiler, it has been designed to operate at maximum efficiency. Advanced design, precision engineering, and modern manufacturing techniques are combined in this product to provide you with comfort at a low operating cost and with a minimum of maintenance.
The boiler sections are cast in iron--a metal resistant to corrosion, especially in a closed system. If this boiler is part of a new installation, it is Joined in a closed system--i.., normally water is neither lost nor addsd-and should not be drained. The replacement of water adds oxygen to the system; corrosive action continues until that oxygen is consumed; but, certainly, the boiler should not be fired without an adequate supply of water. On the other hand, if the boiler is not used during the winter months, it must be drained to prevent damage caused by freezing.
By following the suggestions contained in this manual, you can assume your boiler will function properly for many years. Should any problem arise, contact your nearest American-Standard contractor, whose name can be found in the "yellow pages" of your telephone directory.
AMERICAN-STANDARD
w
The V? Pa.cks.ged responsiiiiity will
Boiler comes to you pre-assembled; the installers major be m locating , connecting accessory parts and performing
the actual hookup.
i
06957
5.5 . : e U t e S t e n d tld improved b V i =
5 5 5:5 O: . - t: C' .
D me-a with three. four or five sections. I=3=r(. rr-.;:n: `.ie I.
v; aliai'icn
-> .u , i:i a level 1. ,jir as 5ir tne cnimnay da o-CosiUi...
' *" .'.In ' ` .1 .
~ - *. . . S niiO Wf G it Zl5c front (at least a 2tV clearance,- t.- t..,.-.
'*3.: " . .i
-r
Cleir..
= pace vapproxirnate ly 24") .sIj.a. -A-.;
<- tlo"'rn l. .r.c : a*r.k -.,.c c; ;.ne oo;ler.
- :r. he easement, or it has been necessary tc wate r ' ..io v should be mounted on a concrete or hollow tut
bin AOILFR
-cat.-:
~ :. c r - i r
final installation site before removing its crate. I
- ulr be acccm.p. ^ v* r. as follows: (See Figs. 1 and 2)
1. r.ifa-:er. an crating wire at tne corner of the crate.
2. 'uvtv.v 5.5:..- fastening crate sides to top and bottom of crate.
ate top and unwrap crate side from crate base.
i.-'u,. of the plastic bag, remove and discard the snort nipple it* tapping at top of boiler.
a training draft stabilizer, relief valve, ana misceiiar.eo-u-
ai- r. .r.r.atir.g the expansion tame. It should not be set m a c-'-i t.-.r c.ne in or from the tar.x were to freeze, serious cam si'-
,, /. rate rabie to usn a minimum of horizontal, run pip: ns-; a 5.-: to facilitate free connmur.ication from the boiler to uie tanh.
06958
RATINGS & DATA
X X X
o f w a te r h e a te d fro m 40F to 140F w it h 200F h o i l e -i w a te r
Ci, i s1 --
--: x
2t .1
< z
1 >
22 -- u; 1
zz >-- w p
z--
n
x z^
p- -- s
'jC < -- Z
z <
"
<
Z W
-
X X _a_ m X
' CO
jC < = zXz < 3Z
_
r- r3 X <^ z pp
s ^ wl < z
cX Xzz o, r- X . il 22 z s -- Zo--
* -. x lO x -- r-
XXX *XX coxao
uO x pp pp Xx 2z Xx Xx
x""x
N CM N XXX pp pp pH
111 CO CO X
o* o* XX X CO 11 rr rr
3 33 .-I 3 -p p- --
pp Xx --1 --p
-O CO ^ O nM pp p-i p^
XN
> n rr z ^ pH
c. o c.
irtoo -- co o' - r-t
oo 33 X 05 pp pH
CZ X z
a
s s o z
>*
22 **
r*
pp
PP.
Z CJ z 22 < a
H-
CZ
0.
<o
' to
22
ZZ zu XX zz X
X pS X XX
Xz O3 sz
u. SzOI
2!
o 51
z z| VA
XXX X Ui a
ooo XXX XXX c c in C ^ <N pp pH pH
X ax
oo XX XX ox n
pH pP
x x in 1- n
^ pH ^
oo X> pp pH
pp pH
^ U. Hp
T? th rr
ptp "t* ^1
555
NN Hp
XX p1p p1p
aE
Xoo pH CO TT pH pp Pp
11l a. a. a. >>>
3O 3
i-l rH 11 3 0. >>
CO
- uO X i" pp
X X
: CJ X r-i
XX
x"x
XX
NN XX pp pp
O hT
o o HH N IN
3O
oo X 13 N IN
XX
oo fp
XX ox oN
MN
Xx O IN
NN
nn
pp
Xt
X i
XX
Ea
oo
nm NN
I1 a. s.
>?
in
i,. i
c>
I
xa
H
CO
<** 30
xa tfi
>
CcbOfl o 4J
rt
u
CO
u CJ
0w
pj
a 2.
X
0s) 5
o
j)
Cfi o
15 pH
c<
X
crt co
H -GH
4-)
X<5
Jp
0)
G
0) fH
o
H
0
X
X Cm o z
06959
1. Side Fasteners 2. Nails
FIG.
06960
Remove ;o-- -'--s
mj ooii^r to -
colts on .e:: i...e. So It a u.i rig at s:o.
./.'.ere they .v;li stay. This is irroor:; n: "o proven: damaging jacket
removing boiler frorr. base.
above or tceaure is quite simple and can be very easily accomplished by two Ir. an _m.erger.cy, it can be accomplished by one man with comparative ease).
Alter tne coiner is removed from the crate base, it can be easily walked to its ;;r.al .0ca..or..
06961
:heck-off parts list for v? packaged boiler
Although the VP Packaged Boiler comes to you assembled, it is necessary :o check certain accessory items prior to final hook up.
Accessory Box
Draft Stabilizer Relief Valve 3/4" x 7-1/4" Pipe 3/4" Tee 3/4" Dram Valve Oil Burner Nozzles Circulator Flange Gasket and 3olts Thermostat 3/4" Street Elbow Draft Tube Sleeve Sleeve Insulation Instruction Sheet
Nipple
Oil Burner Sox DH-F Oil 3urr.er
ZLIMINAIRE FEATURE
This VP Boiler makes use of a special front section with a 1-1/2" supply tapping incorporating the "Eliminaire" feature (See Figs. 3 and 4).
The "Eliminaire" is a unique, built-m air separator which prevents air from being transmitted to the system and directs the air to the com pression tank or vent. This eliminates the need for external air sepa rators such as dip-tubes or unlined accessories. The "Eliminaire" also assures positive air separation, thereby insuring proper system per formance .
5
06962
i^5 FLOW
(WATE.t hEATc.R HEAD)
5 --
(Bi_iND FLANGE)
control TAP!NGS
SIZE OF --T-'-`4 ->r=iNGS
CONTROL USED
VALVE
Ml* CONTROL
OR
P
^4
COMBINATION _.MfT AND REVERSE ACT.NG control
FOR .NSTAi_*_A"CCNS WiTHOUT
~ank_ess nater iEater)
iMVERSION CONTROL
COLELE "RORftCW SWITCH
iMMERSiCN CONTROL RELAT COMBINATION _
0
CCMSINA~ICN ALTITUDE, GAUGt ANC *HERMOMTER
E
^4
AUXiuARY uMI" CONTROL (WHEN REQUIRED]
a
VA
FIGURE 3
FRONT VIEW-SHOWING CONTROL TAPPINGS
FUMt PIPE-------
TO CONVENTIONAL EXPANSION TANK OR AIR VENT IF DIAPHRAGM TANK IS USED
_ RELIEF VALVE
_-t L *
iMS OF
NIPPLE
\ a:o
ELIMNAIRC *JiO PIPING FOR FLOW PIPE
ANO RELiEF VAi^E
FIGURE 4
t . r, <
06963
cling t:-iz v? boiler
r moving the VP Packaged 3oiLer to the desired Location, final installation - _ .-cores sr.ouid oe accomplished as outlined below.
!. Hook up piping. I: jacket extension is to be used, make sure that piping connected with the hot water heater and the boiler return piping to t.ic circulator is arranged to pass through the opening in either the top or sices of the jacket extension (follow assembly instructions accompanying same'/. (See Fig. 5).
2. Screw cram valve into tee at iower right front of boiler.
3. Insr.au relief valve and fittings m top of front section (See Fig. 4), marling sure the direction of the discharge is away from controls.
4. The upper flange of the circulator should be installed on the return piping, men ooitcd to the circulator flange. 3e sure that flange gasket :s not damaged, and that the flange bolts are drawn up equally tight.
5. Install the flue pipe and draft staoilizer using instructions provided with stabilizer. The flue pipe should not extend beyond the inside wail of tne chimney flue. Horizontal runs of flue pipe should be kept at a minimum with approximately 1/4" pitch per foot maintained.
6. Run electric service line from switch (not furnished by A-S) to the cor.troi mounted on built-in water heater, or for boilers without water heater, on water heater opening cover plate.
7. The Cad Ceil leac should be taped to the conduit assembly extending from control to burner to prevent snagging or damage. (See ?g. 13.
3. Install room thermostat.
9. Make ail eiectric connections according to wiring diagram. (See Fig. 6).
10.
The ooiler is now readv to be filled. THE FILLING PROCEDURE IS AN IMPROVED METHOD, AND SHOULD BE FOLLOWED AS INDICATED ON FIG. 7.
M. 3oiier :s now ready for service.
06964
<5
2
FIGURE 5 5pac Heauirer.ents For 3oiler PiDine
'I W * f, (
06965
TEMPERED
PARTIAL VIEW SHOWING PIPING FROM WATER HEATER TO MIXING VALVE
o_j ss
?8
9
06966
-ini_ , hOT-' dotted lines /
: i
'i I' ;:
kjOTFURNISHED
_!!i---------------------- L
,06 '. z
oT
oi r.
HONEYWEi RRie20
combination control
Z c
-F ;o0
z a
,
[
B, c, c, 1 0 c o;
1
WIRE COLORS ajLACK W - WH!"E
MlGr ulMiT CONTROL SETTING APPROX. 210) vL0W LIMIT CONTROL SETTING APPROX. I90a)
3 w-
N'UTC DR.'.lSHFi
A TE PET' Z7C
CULATCR
| LOW VOLTAGE-,
1________________________ 1
____________________ L
OiL BURNER
GENERAL SCHEMATIC SHOWING WIRING TO COMPONENTS
(1)
1L <\_r*f{ '*tT *
IyR V
NTf^NAL "mpm'Tic
r-'MKrTiONS fC*
C0NT**OL
PACKAGED OU, BOILER WITH WATER HEATER WIRING DIAGRAMS FOR CONSTANT IGNITION
1 I . I , t[ 1
06967
o < :J o o5T <2 UHi
U"> _J LU
U U. Q
2; o
5$ 1 co j $
OO
t- c.
5<
5E
^= UtoJ
a
5
iJ
I
!-0h* hot-
JOr
m JO,
afO-
II -- -*-Ocg ----- 1-0 -
SO'' is
igl
00 UJ uj r
zco JZ a
o9z
-) ig <Mp _J|- Oz UjZ o ^<r 2
uZn2h
IScs
o
^r
O'
i I
o < o>
'S
q
2 4 VOLT
THERMOSTAT
PACKAGED OIL BOILER LESS WATER HEATER WIRING DIAC-RAUr WITH REVERSE ACTING CIRCULATOR CONTROL AND CONSTANT IGl'.T
06968
-Q-24'C'.at^aSTAT
INTERNAL SCHEMATIC and CONNECTIONS FOR R8I82E CONTROL
''5 V, 60 CT
INTERNAL SCHEMATIC ANO CONNECTIONS FOR R8I82F CONTROL
PACKAGED OIL BOILER LESS WATER HEATER WIRING DIAGRAMS WITH REVERSE ACTING CIRCULATOR CONTROL AND CONSTANT IGNITION r :g\ire o r
06969
c7 N0.5-Z 'iOO ON* ZONE CONTROL SET FOR USE WITH HONEYWELu R-8182 0 CONTROL
*7r
* . f,'
06970
7he following procedure should be used Co fill a ser.es loop Heatrirr. System (See Jig.
Close all zone valves except the one for the zone to be filled with water ar.c purged of air. Open the drain valve on the boiler. . Open the fill valve. Close the purge valve, i. Open the relief valve. 0. Open the valve to the second zone to be purged; then close the first. Reoeat this step until all zones have been purged of air and filled with water; but always have one zone open. (Zones are purged and filled when water can be felt in the pine at the end of the zone). 7. Close the drain valve. 1. When water appears, release the lever on the relief valve, allowing it to close. '. Continue filling the system until the pressure gauge reads 12 psi without heat or 25 psi at 200 F. ; close the fill valve. '>. Open the purge valve.
following the completion of the installation, a thorough check should be made of the -ntire hydronic system to locate possible leaks.
HOTE: For a single loop heatrim system no additional vents, cocks, valves or other accessories are required except: When tankless heater is used and heatrirr. .s above the boiler outlet, install a flow-check valve to prevent gravity circulation.
wA'JTION: If a valve of any type is installed in the piDing leading to or from the expansion tank, BE ETTRE THAT TT !E ALWAYS QPEH WH'T ,E THE ROUE? TE IN' nPfRATmy.
06971
^arE OF 3CILER WHILE IX OPERATION 3X A CLOSED HOT WATER SYSTEM, THE PRESSURE MUST NOT EXCEED 30LBS. r ;t DOES, IT MUST 3E RELIEVED IMMEDIATELY AND THE CAUSE OF THE FA'L Vr the THE REUSE VALVE INVESTIGATED AND CORRECTED: OTHERWISE, PRESSURE MAY 3UILD UP AND CAUSE DAMAGE TO THE HEATING SYSTEM.
i
FIG. 8 The homeowner should periodically check the readings on the gauge, located on the front of the boiler (See Fig. S). The lower scale indicates the water temperature. That temperature should never be allowed to exceed 250 F. The boiier is designed to operate with a normal maximum water temperature of 230 F; but during mild weather, the system operates with water temperatures considerably below the maximum. The upper scale indicates the pressure within the system and should not exceed 30 lbs. In a closed system, the boiler and piping are entirely filled with water except for a cushion of air in the upper portion of the expansion tank. When the water is heated, it expands, compressing the air in the expansion tank. If, for any reason, this air were completely displaced from the tank, there would no longer be a cushion; an increase in water temperature would cause a corresponding increase in volume; pressure would force the relief valve open to discharge the excess volume. To correct such a condition, the expansion tank must be drained enough to permit the tank to fill with air. Clean boiler surfaces at regular intervals. Do not draw water from boiler while in use. When adding water while boiler is in operation, DO NOT OPEN SUPPLY VALVE FULLY, BUT ADD WATER SLOWLY.
06972
CARE OF BOILER At end of heating season, ciean boiler thoroughly and spray flue surfaces with light lubricating or crankcase oil using gun with extended stem so as to reach all corners. When replacing cleanout door, boiler putty is necessary for sealing. Lubricate circulator in accordance with lubrication instructions on decal. Clean and remove flue pipe where feasible. Keep system filled with water: in other words, DO NOT DRAIN 30ILER. IF 30ILER IS NOT USED DURING WINTER, IT MUST BE FULLY DRAINED TO PREVENT DAMAGE CAUSED BY FREEZING,
t i i, 06973
S - 1S O 1/ . . i rC. c; > O . ~
1 s unoiv .ao~:.;.. ar.a rA;m:ra:re
*
:*o t-.t? - - c.r
o
p car.opv
made of steel nrn heat.
:.- provided. Smciteoioe Srr.oiceoiDe
6"
th 1
hernias. An ac;c;iLiOnai 1 ' of inouiau'^,
t < f 06974
iA R
n
-2 S INFLOW
i i
-D-
3
,~3
SECTION THRU BOILER
Mi ir^-.rpoF
3tMN3!OfjiS :
:CTiOMS A,____ H___ ______ i?_.
4___22| life 6^ 4| 5 2&1~ '4fe 7%'
j
FIGURE 9
L fi '
06975
PACKAGED BOILER
FIGURE 10
Although the basic boiler remains the same, the differences ex:.;: in the wiring procedure with or without water heater (fee
06976
COMBUST.ON' C.:.... . . The Vp Boiler has a or.e-piece precast Re;ractory Combustion target wa specially designed tor maximum performance and efficiency. OIL 3URNER .he Model DH-F oil burner is used with the VP boiler. This burner is espec-allv resigned with a conventional flame-retention head to give maximum Derfomance'' and efficiency m the VP boiler. CONTROLS Controls for the VP Packaged Boiler are conventional. JACKET Jacket design for the V? fdckaged Boiler is conventional as with other A-S boilers.
20
L 06977
CAUTION TO INSTALLER AND HOMEOWNER
This hydronic heating boiler incorporates the best in engineering and manufacturing :echniques and will give years of good service and trouble-free operation if properly treated.
The heat transfer surface has been carefully designed to give optimum performance and reliability. However, the presence of contaminants such as scale, sediment, and boiler sealing compounds in the section waterways may serve to insulate the heat transfer surface and cause premature failure of the sections.
5cale build-up can be prevented by good installation practices which eliminate addition of makeup water to the system.
Sediment which may accumulate in the boiler should be flushed out on a regular basis in accordance with recommended maintenance practices.
Occasionally, leaks will be detected in the system. These leaks are usually of such a nature that they may be prevented or corrected by good workmanship. Every effort should be made to correct them without the use of boiler sealing compounds. If sealing compounds are used, they should be used as sparingly as possible and never in excess of the manufacturers' recommendations. Following their use, the boiler must be thoroughly flushed out. Otherwise, serious damage may result.