Armco Project "600" - Middletown Works Expansion Program
DAILY PROGRESS REPORT NO. 326
Assigned Program Personnel, June 22, 1965:
Technical Construction Administrative Clerical Subcontract Personnel on Loan
Total
9k 36 20 60
1
k
KE Crafts Subcontractor Forces McGraw Work Order Forces
25? 15k
80
Progress:
1. 6U71-00 Temporary Construction: D.H.S. Corporation has returned to the job site to begin work on temporary- railraods.
Painting is underway in the First Aid Building. Occupancy is expected by June 28.
Ironworkers have begun installing insulating panels on outside walls of the Field Office. Foundations for the 20' extension are ready for structural steel.
Siding on the Pipe Shop is complete, ready for sheet metal roof.
Structural steel for the Electrical and Miscellaneous Craft Building is complete.
Sheetmetaiworkers have begun erection of the Timekeeper's Shack.