CHAPTER 43
1949 Guide
2. Determination of outside air require ments.
3. Determination of cooling load. a. Room sensible heat gain. b. Room latent heat gain. c. Room total heat gain, d: Grand total heat gain.
4. Determination of heating load. a. Room sensible heat loss. b. Room moisture loss. c. Humidification requirement. d. Total heating requirement.
5. Determination of. apparatus . dew point and dehumidified or humidi fied air quantity.
' a. Summer (full load and part load), b: Winter.
6. Supply air temperature difference and quantity.
a. Summer. b. Winter.
7. Equipment selection.
8. Equipment layout.
The foregoing steps are merely typical. Many applications will require
at least a preliminary investigation of some of the latter steps before pro
ceeding with the earlier steps. A permanent record of all design assump
tions and computations should'be made and preserved-for comparison with
the performance of the installation.
`
CHAPTER 44
OWNING AND OPERATING COSTS
Fixed Charges: Amortization, Interest, Taxes, Insurance, Rent; Maintenance Costs, Service Costs: Operating Refrigeration Equipment, Condenser Water, Heating
THE purpose of this chapter is to discuss the owning and operating costs of heating, ventilating, air conditioning and refrigeration systems for buildings from an economic standpoint so that owners or prospective purchasers may compare the operating economics of one system with another and evaluate properly the over-all costs of the systems instead of considering only the first cost.
There are cases in which it may be desirable to study the possibilities of installing a system for the purpose of obtaining a substantial increase in income or a better return on the investment due to: increased patronage in theaters, stores; or hospitals; increased occupancy in office buildings; improved efficiency of employees in offices or factories; or improvement in a manufactured product or a decrease in its cost of production.'
Ovming and Operating Costs may be grouped under three headings: (1) Fixed Charges, (2) Maintenance Costs, and (3) Service Costs.
-
FIXED CHARGES
Fixed Charges, which are the costs of owning the system, include: (1) Amortization, (2) Interest, (3) Taxes, (4) Insurance, and (5) Rent.
Amortization
Amortization cost will depend on: (1) the total first cost, and (2) the amortization period.
The total first cost of an installation is the actual dollar outlay or capital expenditure required to buy and install the air conditioning, or heating and ventilating system ready for operation. It can be divided into two parts: (a) The -first cost of the air conditioning or heating and ventilating system itself, and (6), other first costs incurred because of the installation of the air conditioning or heating and ventilating system.
The first cost of air conditioning or heating and ventilating systems in cludes the following:
1. Heat producing equipment including boilers, burners, etc. 2. Heat distributing equipment including direct radiation, piping, etc. . 3. Air handling equipment including fans, air heaters, air conditioners, filters, controls, etc. 4. Air distributing equipment including ducts, outlets, grilles; etc. 5. Refrigerating equipment including piping, pumps, etc. .6. Water conservation devices including towers, evaporative condensers, etc.
The best procedure for establishing the first cost of any system - is to ` select the various parts after, thorough engineering study, and then to esti
mate the installed costs of same. When such detailed work is not war-