MEMORANDUM
SUBJECT:
CLEAN AIR ACT INSPECTION REPORT Amsted Rail Company, Inc., Groveport, Ohio
FROM:
David Sutlin, Environmental Engineer AECAB (MN/OH)
THRU:
Brian Dickens, Section Supervisor AECAB (MN/OH)
TO:
File
BASIC INFORMATION
Facility Name: Amsted Rail Company, Inc.
Facility Location: 3900 Bixby Road, Groveport, Ohio 43125
Date of Inspection: November 6-8, 2023
EPA Inspector(s): 1. David Sutlin, Environmental Engineer 2. Sasha Letuchy, Environmental Engineer
Other Attendees: 1. Lila Jones, Attorney, Department of Justice 2. Susan Tennenbaum, Attorney, EPA Region 5 Office of Regional Counsel 3. Sophie Grueterich, Attorney, EPA Region 5 Office of Regional Counsel 4. Bobby Randhawa, Vice President, GCT 5. Tyler Govett, Sr. Mechanical Engineer, GCT 6. Samuel Boxerman, Attorney, Sidley Austin LLP 7. Robert Ribbing, Environmental Director, Amsted Rail 8. Paul Sheppard, Environmental Manager, Amsted Rail 9. Amy Kosbab, Environmental Manager, Amsted Rail 10. Additional attendees for Amsted Rail
Facility Name: Amsted Rail Company, Inc. Facility Location: 3900 Bixby Road, Groveport, Ohio 43125
Date of Inspection: November 6-8, 2023
Purpose of Inspection: The main purpose of this inspection was to assess uncaptured emissions from the facility's two electric arc furnaces (EAFs) by collecting parametric data, taking field measurements, and recording videos of the EAFs in operation. This work was carried out primarily by Gas Cleaning Technologies, with assistance from EPA. In addition, EPA took opacity readings of emissions from the EAFs building's roof monitor and took differential pressure (DP) readings for various baghouses at the facility.
Facility Type: Steel Foundry
Regulations Central to Inspection: National Emission Standards for Hazardous Air Pollutants from Steel Foundry Area Sources; Title V Permit No. P0103976; Title V Renewal Permit No. P0119336.
The Title V permit states that the EAFs building's roof monitor has an opacity limit of 20% as a 6-minute average, that baghouses #7 and #10 each have an allowable DP range of 3 - 10 inches WC, baghouse #17 has an allowable DP range of 3 - 11 inches WC, and baghouse #5 has an allowable DP range of 4 - 10 inches WC.
November 6 Arrival Time: 9:00 AM Departure Time: 4:30 PM
November 7 Arrival Time: 9:00 AM Departure Time: 4:30 PM
November 6 Arrival Time: 9:00 AM Departure Time: 1:15 PM
Inspection Type: Unannounced Inspection Announced Inspection
PROCESS DESCRIPTION
The facility casts wheels for rail cars. A charge bucket loads cold scrap and carbon additive into one of two EAFs. Occasionally there is a second charge several minutes after the first charge. Typically there is no heal of molten steel at the time of the initial charge. After a charge is completed, a cover moves into place and the electrodes are lowered into the EAF for the melt phase. During melting emissions are vented through a side draft hood to a single shaker, 12-compartment baghouse. During melting, slag is removed through a side door in the furnace. There is an emission capture hood over the slag door. Lime and oxygen are also injected into the EAF during melting. Once the melt phase is complete, the furnaces is tilted and the molten steel is tapped into a ladle. In order for tapping to occur, the EAF's tap hole is cleared either with a prybar or, if necessary, using an oxygen lance. There is a push/pull capture system installed on EAF2 to capture a portion of the tapping emissions. After tapping, the molten steel is poured into graphite molds, cooled, and then the wheel castings and molds are
Page 2 of 5
Facility Name: Amsted Rail Company, Inc. Facility Location: 3900 Bixby Road, Groveport, Ohio 43125
Date of Inspection: November 6-8, 2023
processed through various downstream operations. These include cope and drag cleaners, hot wheel grinders, wheel cleaner, and peener & chamfer. These units are controlled by baghouses that are monitored for differential pressure.
TOUR INFORMATION EPA Tour of the Facility: Yes
Data Collected and Observations: EPA observed all phases of the EAF cycle for both EAF1 and EAF2, from various locations in the melt shop and from the control room. The majority of uncaptured emissions were observed during charging and tapping, with some uncaptured emissions observed during melting.
Since EPA's last inspection, the facility has modified its slag handling operation to allow slag to cool inside rather than outside the EAFs building, and then to load the slag onto trucks that pull into a building extension next to the slag pit. EPA toured the new slag handling building extension to better understand where and how slag is loaded onto the trucks. Because slag removal now occurs only on weekends, the actual loading operation could not be observed.
EPA recorded the following baghouse DP readings:
Emission Unit Cope Cleaner (P002) Drag Cleaner, (P003) Grinders (P004, P005, P006) WCPC (P017, P018, P022)
Baghouse #7 #10 #17 #5
DP Readings (In WC) 5.5 - 10.5 4 - 8 5.2 7.5 - 8.5
DP Limits (In WC) 3 - 10 3 - 10 3 - 11 4 - 10
Photos and/or Videos: were taken during the inspection.
Field Measurements: were taken during this inspection. EPA took digital opacity video recordings of emissions exiting the EAFs building's roof monitor during operation of EAF1 and EAF2.
DIGITAL SIGNATURES DAVID
Digitally signed by DAVID SUTLIN
Report Author: ____S_U__T_L_I_N_______15_:2_2:_38_-0_6'_00_' _________ Date: 2024.01.04
Section Supervisor:
BRIAN
Digitally signed by BRIAN DICKENS
__D_I_C_K__E_N_S_____1_5_:40_:4_3_-0_6'0_0_' ____________ Date: 2024.01.04
Page 3 of 5
Facility Name: Amsted Rail Company, Inc. Facility Location: 3900 Bixby Road, Groveport, Ohio 43125
Date of Inspection: November 6-8, 2023 APPENDICES AND ATTACHMENTS
1. Appendix A: Digital Image Log
Page 4 of 5
Facility Name: Amsted Rail Company, Inc. Facility Location: 3900 Bixby Road, Groveport, Ohio 43125
Date of Inspection: November 6-8, 2023
APPENDIX A: DIGITAL IMAGE LOG
1. Inspector Names: Sasha Letuchy (12) and David Sutlin (3-9)
2. Archival Record Location: EPA Region 5 Electronic Records Center
Image Number
1 2 3 4 5 6 7 8 9
File Name
PXL_20231108_142725363.jpg PXL_20231108_142735254.jpg
PB080324.JPG PB080325.MOV PB080326.JPG PB080327.JPG PB080328.MOV PB080329.MOV PB080330.JPG
Date and Time
2023:11:08 09:27:25 2023:11:08 09:27:35 2023:11:08 10:05:48 2023:11:08 10:11:00 2023:11:08 10:11:36 2023:11:08 10:21:08 2023:11:08 10:22:00 2023:11:08 10:27:00 2023:11:08 10:27:49
Description of Image
Overhead door to side opening of slag loading building extension
Inside of slag loading building extension Grinders DP Gauge
Cope Cleaner DP Gauge Cope Cleaner DP Gauge Drag Cleaner DP Gauge Drag Cleaner DP Gauge
WCPC DP Gauge WCPC DP Gauge
Page 5 of 5