March 12, 1973
Mr. Harry G. Lacay, Area Director
U. S. Department of Labor Occupational Safety and Health Administration Jonnet Building, Room 802 4099 William Penn Highway Monroeville, Pennsylvania 15146
Reference:
GAP Corporation
143 East 16th Street Erie, Pennsylvania
CSHO No. S-1482
Dear Mr. Lacey:
As directed in Citation Humber 1, issued to GAP on February 14,
1973, we are hereby submitting a plan for long term abatement of the alleged violation.
Engineering controls are to be used to reduce employees1 exposure to asbestos fibers st the mixing operation in the Hatsehelc Beater Room. The controls will consist of local exhaust systems at each source of airborne fiber, with the exhausted air to be cleaned by means of a eyeIona and bag collector before it la discharged to
atmosphere. The aystens shall be designed, constructed, installed,' end maintained in accordance with the American national Standard
Fundamentals Governing the Design and Operation of Local Exhaust Systems, ANSI 29.2*1971.
The estimated schedule for completion of the project is sa follows:
Design engineering
Completed
Securing state permit to construct, and placement of purchase orders
April 30, 1973
MICH08133
Mr. Barry G. Lacey, Area Director
U. 5. Departaent of Labor Occupational Safety and Bealth Admlolatration
March 12, 1973 Page 2
Delivery of equipment
July 31, 1973
Installation
September 30, 1973
Start-up adjustments, balancing, completion of abart--nt
October 31, 1973
During the tine period necessary to install the engineering con trols, approved air purifying respirators mill be used in the Beater
Please let us know if any fiorther information is needed. Very truly yours. CAF Corporation
V. *. Holt Plant Manager
UBH/dg
cc: Mr. B. Suroviec Director of Occupational Health Erie County Community Information Center 606 Beet Second Street Erie, Pennsylvania 16302
be: Messrs. Darrell, Dent, Faaauliotla, Bylan, Vainer