Document 7Mq5j7b603XJZ7xa82V2vY1ZE
/
Report of Results: MVA0154 Manchester, Hew Hampshire
Prepared for: Farad, Guadagnino, Lange & Johns Suite 300, Times Square Building
45 Exchange Street Rochester, Hew York 14614
(
Prepared by: Millette, Vender Hood a Associates, Inc,
5500 Oakbrook Parkway, Suite 200 Horcrosa, Georgia 30093
29 October 1991
Report of Results: KVA Project mo. 0154 Manchester, KH
MEASUREMENT 0? AIRBORNE ASBESTOS CONCENTRATIONS DURING THE REMOVAL OF VALVE PACKING
INTRODUCTION
Most piping systems use valves to regulate the flow of fluids or gases within them. The valves, especially in industrial facilities, may contain asbestos packing material which acts as a seal to prevent fluid or gas leakage as the valve is turned. At various time intervals the valves must be repaired or maintained by removing the packing and replacing it with new packing. In some large steam plants it is common practice to collect a number of valves together and perform the removal and repacking of these valves at one time, and this effort may involve several workers and take several days to complete. The purpose of this study was to document the airborne levels of asbestos, if any, during valve packing removal activity.
ASBESTOS PACKING MATERIAL
According to the U.S. Environmental Protection Agency (EPA), asbestos packing means an asbestos-containing product Intended for use as a mechanical seal in circumstances involving rotary, reciprocating, and helical motions, and which are intended to
restrict fluid or gas leakage between moving and stationary surfaces (1).
'
The graphite impregnated packing material which has the -
appearance of shiny stiff rope is the type most commonly used in
valves. Compression packings are manufactured from various-forms
of fibers, such as vegetable, animal, mineral (asbestos), or
'
synthetic combined with binders and lubricants. The types of
construction include twisted or braided (2). Packings are not
considered friable asbestos-containing materials (ACM) because
they are not easily crumbled into fine or dusty material by hand
pressure. However, EPA states that products such as packing may
release asbestos dust if cut or torn (3).
STUDY TEAM
- '.
The on-site research team consisted of Jame6 R. Millette, Ph.D., of Millette, Vender Wood & Associates, Inc. (MVA), Michael D. Mount, OHST, of Azimuth, Inc., and Robert Yantz, a retired steam plant maintenance worker.
Page -- 2 --
STUDY SITE
>
The study was conducted in an unused steam power plant in .*
Manchester, New Hampshire, The study team conducted the valve
packing removal tests after an asbestos abatement contractor had
prepared a double containment area around two valves attached to
the main power plant turbine. Prior to the studies, the
abatement contractor prepared the valves by removing all pipe
insulation from the valve area and thoroughly cleaning each
.
valve. In a separate area of the plant the abatement contractor
also prepared a third valve which had been disconnected from the
steam plant piping system by similarly removing all the pipe
insulation and cleaning the valve thoroughly. This valve was
later moved into the containment for packing removal. The>
containment barriers in the area consisted of layers of 6-mil
polyethylene plastic sheets on a wooden frame and two layers of
6-mil polyethylene plastic on the floor. A containment area (5
ft by 7 ft) around the valves was completely contained within a
larger containment area (7 1/2 ft by 11 ft). The study area had
two High Efficiency Particle Absolute (KEPA) air filtration
devices (AFD) used to clean the air of particulates including
asbestos. The inner area AFD was turned off during each phase of
testing. The outer area AFD operated throughout the tests. A
diagram of the area is shown in Appendix A.
PERSONAL PROTECTION
All personnel inside the study area were protected by air purifying respirators and complete head and body coverings.. The decontamination system consisted of a hallway outside the testing area, a shower room, and a clean room. The decontamination system was used each time a person exited the study area and the overall containment area.
EXPERIMENTAL PROCEDURES
The study was conducted on August 27, 1991, and consisted of collection of air samples before and during a valve packing removal activity to compare the airborne asbestos fiber levels. The activity was replicated three times. Prior to starting each part of the study, four area air samples were collected to ' determine the background level of asbestos in the air of' the study area. The sampling cassettes were located on the walls at the breathing zone, five feet from the floor. A total volume of 720 to 640 liters of air passed through each cassette at a flow rate of 15 liters per minute. Two area air samples were collected during the valve packing removal in the same locations as the background air samples. The person doing the packing
Page - 3 -
removal (Mr* Yantz) was fitted with two personal air sampling
devices* These personal air samples were collected at a rate of
about 2-3*5 liters per minute. The person observing and taking
photographs (Dr. Millette) also wore two personal air sampling
cassettes. These air samples were collected at a rate of 2 - 3.5
liters per minute. Following packing removal from a valve
attached to the power turbine/ the area was cleaned and another
valve found disconnected from the piping system was moved to the
containment* The air filtration unit was turned on for a period
of approximately 2 hours to reduce the number of airborne fibers
in the study area. Prior to the second test a new set of
background samples was collected. After the second test the area
was cleaned and the air filtration unit again allowed to cleanse
the air.
;:
;
The first two valve packing removal activities consisted of
opening a valve and reaching in with a variety of tools to pull
out the old packing. The third test Utilized the same valve that
had been opened in the second test. More packing was removed.
Mr* Yantz brought his own tools and performed the removal-of
packing in the same way that he had in his previous years of work
with industrial valves. Pieces of the removed packing were
placed in plastia bags and stored for analysis. Each packing
removal activity occurred for approximately 30 minutes.
.
Three sampling locations were established outside the study area to monitor the airborne fiber levels during the packing removal. Two samplers were positioned in the outer containment area and one was placed outside the entrance the decontamination system. These samples were analyzed to make sure that fibers were not escaping the contained study area.
ANALYTICAL METHODS
All samples were analyzed by phase contrast microscopy (PCM) following the method currently required under Occupational Safety and Health Administration (OSKA) regulations. This method/ developed by the national Institute of Occupational Safety and Health (NIOSH) is called the NIOSH 7400 method. The analyst followed the "A11 counting rules which are currently specified by OSHA for asbestos monitoring. The phase contrast microscope enhances the analyst's ability to see fibers over other types of light microscopes but the technique does not involve an ' identification step which specifically determines that*the fibers counted are all asbestos. Therefore/ in addition/ some of the . samples were analyzed by transmission eleatron microscopy (TEM) following the NIOSH 7402 preparation method. The TEM analysis procedure identifies asbestos fibers on the basis of morphology, crystal structure/ and x-ray elemental analysis. Only asbestos fibers longer than 5 um were counted.
Page - 4 -
Samples of the packing material removed from the valves ware analysed for asbestos type by polarized light microscopy (PLM) techniques. Samples of the packing material were also examined by scanning electron microscopy (SEM) to determine whether or not the chrysotlle fibers were encapsulated.
The friability test to determine whether or not an asbestoscontaining material potentially will release asbestos is a field test in which an attempt is made to crumble the ACM by hand. If the material can be crumbled by hand, it is considered friable. The U, S. Environmental Protection Agency (EPA) distinguishes friable from non-friable ACM in their regulations on handling asbestos products. Friable ACM is considered more of a potential hazard than non-friable material.
RESULTS
-
The results of the PCM analyses of the air samples collected in the study area are shown in Table I* Prior to the first-teat, the background air samples showed that the air contained less than 0.006 fibers/cc. During the aatual removal activity, one personal sample collected on Mr. Yantz, the person doing the packing'removal, showed that his exposure was about 0.2 fibers/cc. The personal samples on Dr. Mlllette, who was observing the removal operation ranged from 0.1 to 0.2 fibers/cc.
Prior to the second test, three of the four background air samples were less than 0.006 fiber/cc. One background sample was 0.009 fibers/cc. The personal samples on Mr. Yantz during the packing removal showed levels of over 1 fiber/cc in the air. The personal samples on Dr. Mlllette ranged from about 0.6 to 0.9 fibers/cc.
Prior to the third test, all background air samples showed the
airborne fiber concentration to be less than 0.007 fiber/cc. The
personal samples on Mr. Yantz during the packing removal ranged
from about 0.4 to 0.7 fibers/cc. The personal samples on Dr.
Mlllette ranged from 0.2 to 0.3. The area samples collected in
the vicinity of the packing removal activity were elevated over
the background levels in all three tests. The air samples
collected outside the double containment at the door to the
decontamination unit were less than detection limits.
*
The TEM analyses results are shown in Table II. Chrysotlle asbestos fibers were identified as the primary fiber in the air samples collected during the packing removal. Chrysotlle asbestos was the type of asbestos found by polarized light microscopy in the packing material removed. All asbestos fibers longer than 5 um were counted and recorded during the TEM
Page - 5 -
analysis* However, fibers thinner than about 0.2S ym would not be* resolved by the PCM method which uses a light microscope. Therefore, two asbestos concentrations are listed. One of all asbestos fibers greater than 5 pm and one including only those over 5 Jim in length and also over 0.25 ym in width. The second value is considered a PCM equivalent count because the fibers counted in the TEM would be equivalent to what would be seen by the PCM. Because of the greater resolving power of the electron microscope the fibers longer than 5 ym but thinner than 0.25 ym can be counted in the TEM analysis.
The used packing, removed from the valve, was friable. When examined under the scanning electron microscope, the sample of used packing was found to contain chrysotile fibers which were uncoated with any binder material.
CONCLUSIONS
**
The data show that airborne levels of asbestos fibers can be over
the OSHA excursion limit (30 minute sample) of 1 fiber per cc
during the removal of asbestos-containing packing material from
valves using methods routinely employed by maintenance workers.
Airborne levels of asbestos are significantly increased over
background levels in the vicinity of the packing removal during
the removal activity.
*
*
REFERENCES
1. Federal Register, July 12, 1989, 54(132):295Q9.
2. Nelson, C. A., Millwrights and Mechanics Guide, McMillian
Pub. Co., London, (1986), p. 236.
3. U.'S. EPA, Asbestos Waste Management Guidance, EPA/530-SW-85
-007, p. 146.
.
KVA PROJECT MO. 0154 - MANCHESTER STEAM PLANT
TABLE I PHASE CONTRAST ANALYSIS (PCM)
FIRST TEST
SAMPLE
TIKE
DATE
SAMPLE TYPE SAMPLE DESCRIPTION
RATS (LPK) FIBERS CONC IN VOLUME (L) FIELDS FIBERS/CC
10 807-901 Southwest Comer of Containment, 27 Aug 91 Background Inside Building; Inside Work Area
15.00 810
8.0 < 0.006 100
11 27 Aug 91
12 27 Aug 91
805-901 Center of Containment, Background inside Building; Inside Work Area
805-901 East Wall of Containment, Background Inside Building; Inside Work Area
15.00 840
15.00 840
8.5 100
11.0 100
< 0.006 < 0.006
13 27 Aug 91
O'?27Vau9 91
805-901 Northeast Comer of Containment, Background inside Building; Inside Work Area
1050-1115 Bob Yantz, Right Side, Personal Inside Building; Inside Work Area
15.00 840
` 2.00 50
11.5 100
22.0 100
< 0.006 0.184
15 27 Aug 91
0-0 Personal
Bob Yantz, Left Side,
'
Inside Building; Inside Vork Area
VOID - PUMP FAILED
0.00 0
0.0 100
16 27 Aug 91
f")
27 'Auy 91
1050-1115 Jia Hillette, Left Side Personal Inside Building; Inside Vork Area
1050-1115 Jim Hillette, Right Side
-
Personal Inside Building; Inside Vork Area
3.50 87.5 \
2.00 SO
23.5 100
26.0 100
0.114 0.223
18 27 Aug 91
0-0 Area
Southwest Comer of Containment,
Inside Building; inside Vork Area VOID - FILTER DAMAGED
0.00 . 0
0.0 100
19 27 Aug 91
1050-1116 Northeast Comer of Containment,
Area
Inside Building; inside Vork Area
15.00 390
54.00 100
0.064
MVA PROJECT NO. 0154 - MANCHESTER STEAM PLANT TABLE I
PEASE CONTRAST ANALYSIS (POO SECOND TEST
SAMPLE #
TINS
DATE
SAMPLE TYPE SAMPLE DESCRIPTION
RATE (LPM) FIBERS CONC ZM VOLUME (L) YIELDS PIBERS/CC
20 1305-1402 Center of Containment, 27 Aug 91 Background Inside Building; Inside Work Area
15.00 855
9.0 < 0.006 100
21 1305-1402 Southwest Comer of Containment, 27 Aug 91 Background inside Building; Inside Work Area
15.00 855
19.5 100
0.009
22 1305-1402 East Wall of Containment, ,, 27 Aug 91 Background Inside Building; Inside Work Area
15.00 855
10.0 100
< 0.006
23 1305-1402 Northeast Corner of Containment, -27 Aug 91 Background Inside Building; Inside work Area
15.00 855
13.0 100
< 0.006
24 Aug 91
1448-1519 Bob Yantz, Left Side, Personal Inside Building; Inside Work Area
3.00 93
102.5 53
1,003
25 27 Aug 91
1448-1519 Bob Yantz, Right Side,
''
Personal Inside Building; inside Work Area
2.00 62
100.5 61
1.278
26 27 Aug 91
27 27 Aug 91
26 27 Aug 91
1448-1519 Jin Millette, Right Side, Personal Inside Building; Inside work Area
1448-1519 Jin Killette, Left Side Personal Inside Building; inside Work Area
1446-1510 Southwest Corner of Containment,
Area
Inside Building; Inside work Area
2.00 62
100.5 85
3.00 93
7.50 180
100.0 t 91
109-5-. 67
0.910 0.562 0.436
29 27 Aug 91
1446-1511 Northeast Comer of Containment, -
Area
Inside Building; inside Work Area
15.00 375
102.0 46
0.286
. 30 27 Aug 91
1044-1156 Area
Southwest Comer of Outer Containment, Inside Building; Outside Work Area
7.50 540
42.0 100
0.035
31 27 Aug 91
1044-1156 Area
Northeast Comer of Outer Containment, Inside Building; Outside Work' Area
15.00 1080
71.0 100
0.031
32 27 Aug 91
1044-1156 At Entrance to Decon, Inside
Area
Building, Outside Work Area
15.00 1080
14.0 100
0.005
KVA PROJECT NO. 0154 - MANCHESTER STEAM PLANT
TABLE I PHASE CONTRAST ANALYSIS (PCM)
THIRD TEST
SAMPLE
TIMS
DATS
SAMPLE TYPE SAMPLE DESCRIPTION
RATS (XiPM) FIBERS CONC IN VOLUME CL) FIELDS FIBSRS/CC
33 736-824 In Northeast Comer of Containsant,, 28 Aug 91 Background Inside Building; Outside York Area
15.00 720
9.0 < 0.007 100
34 736-824 In Southwest Comer of Containment,, 28 Aug 91 Background Inside Building; Inside work Area
15.00 720
4.0 < 0.007 100
35 736-824 In Center of Containment, 28 Aug 91 Background Inside Building; Inside York "Area
15.00 720
4.5 < 0.007 100
36 736-824 On East Vail of Containment, 28 Aug 91 Background Inside Building; Inside Work Area
15.00 720
5.5 < 0.007 100
37 J8 Aug 91
849-922 Bob Yantz, Right Shoulder, Personal Inside Building; Inside Work Area
2.00 66
62.6 100
0.440
38 28 Aug 91
849-922 Bob Yantz, Left Shoulder, Personal Inside Building; Inside Work Area
3.00 99
106.0 72
0.713
39 28 Aug 91
847-926 Jla Millette, Left Shoulder, Personal Inside Building; Inside work Area
3.00 117
50.5 100
0.198
40 28 Aug 91
41 28 Aug 91
847-926 Personal
845-920 Area
Jim Millette, Right Shoulder, Inside Building; Inside Work Area
Northeast Corner of Containment, Inside Building; Inside Work Area
2.00 78
15.00 525
56.5 i 100
107-5. 63
0.335 0.156
42 28 Aug 91
845-920 Area
Southwest Comer of Containment, , Inside Building, Inside Vork Area
7.50 262.5
85.5 100
0.154
43 28 Aug 91
845-920 Area
Northeast Comer of Outer Containment, Inside Building; Inside Work Area
15.00 525
41.0 100
0.035
44 28 Aug 91
845-920 Area
Southwest Comer of Outer Containment, Inside Building; Inside Work Area
7.50 262.5
41.0 100
0.071
45 28 Aug 91
850-909 Area
At Entrance to Decon, Inside Building; Outside vork Area
15.00 285
4.0 < 0.017 100
KVA PROJECT MO. 0154 - MANCHESTER STEAK PLANT
TABLE XI
TEN ANALYSIS 0? AIR SAMPLES DURING PACKING REMOVAL DIRECT PREPARATION*
KVA #
B2178
B2179
B2180
B2181
Field I.D.
Description
24 Personal During Second Test
25 Personal During Second Test
37 Personal During Third Test
38 Personal During . Third Test
Asbestos Concentration (Fibers/cc)
All >$pm ?cx s<r
2.2 4.2 1.5 ' 2.1
1.5 2.6 1.2 1.5
* Phase Contrast Equivalent by Transmission Electron Microscopy
Counting. Asbestos fibers must be >5p in length and > .25 un In width.
APPENDIX A Diagram of Study Site
a
APPENDIX B
Transmission Electron Microscopy PCM Equivalent Data Sheets
HVA PROJECT # :0154 LAB SAMPLE ID :B2178 CLNT SAMPLE ID:24 INSTRUMENT 10 :CM12
MAGNIFICATION : 4.4 X
ACC. VOLTAGE : 100 KV
GRID NUMBER
:025G91
GRID OPENING (MM2):0.0082
OPENINGS ANALYZED ;
10
AMT COLLECT (L) :
93
AMT PREPPED (L) !DIRECT
FILTER AREA (MM2) : 385
ANALYST :RKW
DATE 110/03/97 COMMENT:PCM
. EQUIVAL.
STRU LENGTH WIDTH
GRID INDEX STR# TYPE <ua)
(urn) SAED
EDS
B3
1F
6.82 0.11 C
2F 3F
7.27 9.55
0.11 C
0.23 c
4F 5F
9.55 5.68
0.34 c 0.23 c
6F
9.09 0.26 c
7 F*~ 5.23 - 0.68' -c
8 F 15.91 1.14 c
E9
9F
5.68 (1.23 c
10 F
5.68 0.23 c
11 F
5.91 0.23 c
H8 12 F 15.23 1.82 c
13 F 15.91 0.91 c
14 F 15 F
7.95 9.09
0.23 c 0.23 c
16 F
6.82 0.45 c
15 17 F 9.77 0.57 c
18 F 34.09 0.45 c
19 F 14.09 0.23 c
20 F
7.05 0.34 c
J2 21 F 5.68 0.23 c 22 F 11.36 0.23 c
23 F 35.23 2.27 c
24 F
7.73 0.80 c
08 25 F 5.68 0.34 c
26 F
6.82 1.14 c
FI 0 27 F
7.50 0.23 c
28 F 10.91 0.45 c
29 F
9.55 0.57 c
30 F
7.95 0.45 c
31 F
7.27 0.11 c
G6 32 F 7.27 0.34 c
33 F
5.68 0.91 c
34 F 20.45 0.45 c 35 F 11.36 0.11 c
36 F 25.00 0.34 c F2 37 F 5.45 0.45 c
38 F
6.82 0.57 c
A1
39 F
7.95 0.45 c
40 F 13.64 1.59 c
MVA PROJECT U :G154 LAB SAMPLE ID :B2178
CLOT SAMPLE ID:24 INSTRUMENT ID :CM12 MAGNIFICATION : 4.4 X
ACC. VOLTAGE : 100 KV
GRID NUMBER
:02SG91
GRID OPENING (MM2):0.0082
OPENINGS ANALYZED :
10
AMT COLLECT (L) :
93
AMT PREPPED (L) : DIRECT
FILTER AREA (MM2) : 385
ANALYST:RKW
DATE :10/03/91 COMMENT:PCM
EQUIVAL.
STRCJ LENGTH * WIDTH
GRID INDEX STR# TYPE (um)
(uo) SAED
EDS
2 A1
41 F 42 F
43 F
9.55 6.14 8.41
0.45 C 0.68 C 0.57 C
MVA PROJECT U :0154 LAB SAMPLE ID :B2179 CLOT SAMPLE ID;25
INSTRUMENT ID :CM12 MAGNIFICATION i 4.4 X ACC. VOLTAGE : 100 KV
GRID NUMBER
:025G91
GRID OPENING (MM2):0.0082
OPENINGS ANALYZED :
10
AMT COLLECT <L) :
62
AKT PREPPED (L) :DIRECT
FILTER AREA (MM2) : 385
ANALYST:RXW DATE :10/03/91 COMMENT:PCM
EQUIVAL.
STRU LENGTH WIDTH
GRID INDEX STR# TYPE (um)
(urn) SAED
EDS
1 H7 13 El B5
D9 2 CS
1F
9.55 0.11 C
2 F 19.32 0.34 c
3 F 35.23 1.14 c
4F
6.14 0.45 c
5 F 11.36 0.45 c
6 F 10.68 0.11 c
7F
9.09 1.14 c
8 F 21.59 0.11 c
9 F 10.91 0;23 c
10 F 15.91 0.34 c
11 F 15.91 0.91 A
12 F 17.05 0.68 c
13 F
7.27 0.34 c
14 F . 8.41 0.45 c
15 F
6.36 0.11 c
16 F 17 F 18 F
9.09 6.14 6.82
0.11 0.11 0.11
c
c c
19 F
5.45 0.91 c
20 F 20.45 0.34 c
21 F 17.05 0.45 c
22 F 15.45 0.80 c
23 F
8.41 0.57 c
24 F
8.86 0.23 c
25 F 13.64 0.45 c
26 F
7.50 0.23 c
27 F 40.91 2.27 c
28 F 11.36 0.68 c
29 F 17.05 0.91 c
30 F
5.00 0.80 c
31 F 32 F
7.95 5.68
0.23 c 1.14 c
33 F 12.50 0.23 c
34 F 12.50 0.23 c
35 F 23.86 0.57 c
36 F 37 F
5.68 7.05
0.23 c
0.68 c
38 F 15.91 0.45 c
39 F 21.59 1.59 c
40 F
7.50 0.23 c
Y Y
MVA PROJECT # 20154 LAE SAMPLE ID :B2179
CLOT SAMPLE ID525 INSTRUMENT ID :CM12 MAGNIFICATION : 4.4 K ACC. VOLTAGE : 100 XV
GRID NUMBER
:025G91
GRID OPENING (MM2) ;0.0082
OPENINGS ANALY2ED :
10
AMT COLLECT <D) :
62
AMT PRSPPED (L) 1DIRECT
FILTER AREA (MM2) : 385
ANALYST RXW
DATS
10/03/91
COMMENT PPM
EQUIVAL.
STRU LENGTH WIDTH
GRID INDEX STR# TYPE (um)
(um) SAED
EDS
2 B9
41 F 19.32 0.57 C
FI 0 42 F
5.68 0.23 A
Y
43 F
8.41 1.36 C
44 F 30.68 0.45 C
45 F 12.50 0.11 C
J7 46 F 38.64 0.23 c
47 F 22.50 0.11 c
48 F 18.86 1.59 c
49 F 17.27 0-11 c
H2 50 F 6.14 0.34 c
H7 51 F 7.50 0.34 c
52 F
5.91 0.45 c
53 F
7.73 0.11 c
( 54 F 13.64 0.57 c
55 F 23.41 0.45 c
MVA PROJECT $ :0154
LAB SAMPLE ID :B2180 CLNT SAMPLE ID: 37
INSTRUMENT ID :CM12 MAGNIFICATION t 4.4 K ACC. VOLTAGE : 100 KV
GRID NUMBER
025G91
GRIG OPENING (MM2) 0.0082
OPENINGS ANALYZED
10
AMT COLLECT <L)
66
AMT PRSPPSD (L)
DIRECT
FILTER AREA (MM2)
385
ANALYST2RKW DATE :10/4/91 COMMENT:PCM
EQUIVAL
STRU LENGTH WIDTH
GRID INDEX SIR# TYPE (urn)
(um) SAED
EDS
1 Cl
1 F 15.23 0.45 C
2 F 23.86 0.57 C
3 F SI.14 1.14 C
4F
7.95 0.45 c
5 F 17.05 0.45 c
6F
5.91 0.23 c
7F
5.91 0.45 C
A7 NSD*
10
8 F 13.64 Chll C
9 F 11.82 1.82 c
19 10 F 27.27 0.57 c
11 F 46.59 0.45 c
12 F
7.95 0.45 c
13 F 42.OS 0.68 c
J6 14 F 6.14 0.57 c
2 H2
IS F
6.82 0.45 c
B3 16 F 25.68 0.23 c
9 17 F 7.95 0.23 C
G8 18 F 24.09 1.93 A
19 F
5.68 0.45 c
20 F 14.77 0.34 c
F4 21 F 8.64 0.57 c
Y Y
* No Asbestos Structures Detected
MVA PROJECT 0 :01S4 LAB SAMPLE ID :B2181 CLNT SAMPLE ID: 38 INSTRUMENT ID :CM12 MAGNIFICATION : 4.4 K ACC. VOLTAGE : 100 KV
GRID NUMBER
:025G91
GRID OPENING (MM2):0.0082
OPENINGS ANALYZED :
10
AMT COLLECT <L) AMT PREPPED <L)
: 99 :DIRECT
FILTER AREA (MM2) : 385
ANALYST:RKW DATE :10/4/91 COMMENT:PCM
EQUIVAL.
STRU LENGTH WIDTH
GRID INDEX STR# TYPE (tan)
(um) SAED
EDS
B2
1F
7.05 0.23 C
2F
7.50 0.11 C
3 F 11.36 0.45 C
Y
C6 4 F 11.82 0.80 c
5F
6.82 0.34 c .
6 F 15.23 1.14 c
G9 7 F 22.95 0.68 C
8F
9.09 0.45 c
9 F 20.45 1-.59 C
10 F 10.23 0.34 c
11 F 11.36 1.36 c
K5 12 F 10.23 0.57 c
( 13 F 17.05 2.27 c
FI
14 F
5.68 0.11 c
IS F 12.95 0.45 C
16 F 47.73 0.80 c
17 F 18.18 1.14 c
18 F 12.50 0.45 C
19 F
7.05 0.34 c
A1 20 F 10.23 0.45 c
21 F 13.64 0.11 c
22 F 69.32 0.68 c
23 F
7.95 0.23 c
24 F 17.05 0.91 c
25 F
6.14 0.11 c
D6 26 F 6.82 0.80 c
27 F
5.68 0.57 C
28 F
5.45 0.68 c
29 F
7.95 0.45 c
30 F 26.14 0.57 c
Gl 0 31 F 10.23 0.91 c
32 F 29.55 2.05 c
33 F 11.14 0.34 c
14 34 F 5.68 0.11 c
35 F
6.14 0.34 C
36 F 19.77 0.23 C
37 F 12.50 0.11 C
38 F
6.14 0.11 c
39 F
6.14 0.11 c
40 F
7.50 0.45 c
MVA PROJECT M :0154 LAB SAMPLE ID :82181 CLNT SAMPLE ID : 38 INSTRUMENT ID :CM12 MAGNIFICATION : 4.4 K
ACC. VOLTAGE' : 100 KV
GRID NUMBER
:Q25G91
GRID OPENING (MM2) :0.0082
OPENINGS ANALYZED :
10
AMT COLLECT (L) :
99
AMT PREPPED (10 :DIRECT
FILTER AREA (MM2) : 385
ANALYST:RKW DATE :10/4/91 COMMENT:PCM
EQUIVAL
STRU LENGTH .WIDTH
GRID INDEX STR# TYPE (urn)
(um) SAED
EDS
2 14 F2
41 F 11.36 0.23 C
42 F
5.91 0.45 c
43 F 52.27 1.82 c
44 F . 18.18 0.11 c
45 F 11.36 0.80 c
(
Notea on TEH Air Analysis Sheets
Explanation of Headings;
MVA PROJECT #
- Number assigned by MVA to the project
LAB SAMPLE ZD
* Code assigned to each sample logged into
the laboratory
CLNT SAMPLE ID
- Client identification, usually a field number
INSTRUMENT ID
- Electron microscope used. CM12 is a TEM model
produced by Philips.
MAGNIFICATION
- Actual magnification at the microscope screen.
19.4 X is 19,400 times.
ACC. VOLTAGE
- Accelerating voltage of the TEM
GRID NUMBER
- Box grid was placed in for analysis
GRID OPENING (MM2) - Average area of a grid opening in square
millimeters
OPENINGS ANALYZED - Number of grid openings examined
AMT COLLECT (L)
- Volume of air for the air sample collected in
liters
AMT PREPPED (L)
- For direct preps, the volume
prepared is the same as collected. For
indirect preps the equivalent volume
prepared from a portion of the air
sample. A dilution factor can be calculated
by dividing amount propped by amount
collected.
.
FILTER AREA (MM2) - Area of the final filter used in the
preparation process in square millimeters
GRID
- Number of grids analyzed, usually two grids
are analyzed per sample
INDEX
- Grid opening location
STR#
- Number of structures counted
STRU TYPE
- F-fiber, B-bundle, Clcluster, M-matrix
LENGTH (um)
- Length of structure in micrometers
WIDTH (um)
- .Width of structure in micrometers------
SAED
- Selected Area Electron Diffraction Pattern
C-chrysotila, A*amphibole
EDS
- Energy Dispersive X-ray Spectroscopy
Yyes, spectrum consistent with c or A
Calculation of Asbestos Structures per Cubic Centimeter:
Str/cc * <*STR x FILTER AREA) (OPENINGS ANALYZED X GRID OPENING X AMT PREPPED x AMT COLLECT)
APPENDIX C
Polarized Light Microscopy Analysis, of Packing Removed from Valve During Third Test
Millette, Vender Wood * Associates/ Inc. 5500 Oakbrook Parkway, Suita 200 Korcross, Georgia 30093 (404) 662-8509
PLM ASBESTOS ANALYSIS
KVA #: 0154
Client: Farad, Guadagnino, Lange & Johns
Sample ID: B1992
Client Sample ID: J082791-7
Macroscopic Description: SI 992 is a white fibrous woven material with a black flaky coating*
Asbestos Minerals:
Other Fibers:
Chrysotile Amosite
Crocidolite Anthophyllite Asbestos Tremolite/Acfcinolite
Asbestos
-85% __ _____ _____
Glass Fibers Cellulose Synthetic Fibers Other
Total Asbestos
-as*
Fillers/Binders/Pigment %
Fillers/Binders/Pigaent Identified (*):
Mica/Vermicullte Synthetic Foam
Gypsum Carbon and iron oxides
________ ________
__
Perlite/Pumice Carbonate Pigment
Comments: Labeled "3rd Valve, 2nd Sxpl(
Analyst: Maureen C. Bottrell
Date: 09/04/91