Document 6wyvwEQ6gvKNQKk0XaBYV9Qz9

INTEROFFICE CORRESPONDENCE GEN-80-17 (Object: DATE: REMOVING, DISPOSING OF AND REPLACING ALL ASBESTOS INSULATION - ESTIMATE April 1, 1980 office: from: Corpus Christi Refinery Engineering JC; ET; Ratchford, Jr. . to: W. C. Mil burn I )PLAINTIFF'S i EXHIBIT KRC-68 As requested by Mr. J. M. Connor, Corporate Safety Director, an estimate has been made of subject project. Accomplishing this project in the Corpus Christi Refinery would cost $15,200,000.00 and would require the controlled disposal of approx imately 1,526,000 pounds of asbestos insulation (see attached detail sheet). The following listed process units/areas are known to be asbestos-free and are not included in this estimate: a. All Storage Tanks b. Parex Unit c. Waste Water Treatment Plant and Sand Filtration d. New FCCU Reactor (DC-102) and Its Overhead Vapor Line e. New Hot Process (Water Treatment) and Filters f. New Vacuum Tower in Crude Unit (DA-4)' g. New FCCU VRU Section and Alkylation Unit Revamp h. New Power Generation (Gas Turbine Generators) i. New Ultraformer StabilizerSection It is assumed that the accomplishment of this project would require approximately two years; it is further assumed that no unscheduled shut down of process units would be required. This estimate is based on current estimating standards and contractor's furnished data. JER/grt Attachment cc: JHA, EBD, REF, TRH, JDJ, JRK, PWK, RCR UN-7*00.0 Does this correspondence really have to be filed? 1 K018514