Messrs. W. G. Aiesio H. P. Cobb, Jr. J. F. Emerson R. J. Klotzboch F. H. Larrison O. J. Malacame
C. P. Martin J. L. Myers J. W. Rawlings J. C. Stephenson
December 23, 1974
Current Status of Plans for Expanding King City Asbestos Plant________
The purpose of this memorandum is to update my earlier communication of June 19, 1974, on the planning for a plant expansion at King City. During the interim, parameters relating to this proposed expansion have been further defined as summarized below:
1. Market projections covering the period 1974 through 1980 were developed and issued by the Colldria Sales Group. (Reference 1) The forecasted sales mix for 1979 was very simitar to the optimum mix presented in my June 19, 1974, memo, with the ex ception that a more conservative estimate of RG-244 sales was developed. Con sequently, Engineering was advised to assume in further plant expansion studies that the present RG-244 Phase II expansion could handle forecasted near-term market needs if augmented by limited future working budget expenditures. (Reference 2)
2. Based upon the assumed product mix. Engineering developed a concept for expanding the King City plant to 60,000 T/yr. which would use the existing mill circuit for standard and super-standard grade products and require construction of a new building and facility for high purity products as well as specialty? i-teros su.ch .as RG-^QQ. (Reference 3)
3. Cost estimates for operation at 60,000 T/yr. and 110,000 T/yr. levels were developed by plant personnel and these provided the bases for financial analyses to be subsequently discussed. (Reference 4)
4. In view of the fact that capital costs were escalating at an accelerating rate and market risks were high, it was decided to defer further consideration of a 110,000 T/yr. operating rate and focus on the more conservative 60,000 T/yr. rate. On this basis, the preliminary engineering estimate far the plant expansion was $8,670 MM, of which about $1.2 MM was attributable to RG-600 processing. This estimate for expansion to 60,000 T/yr. far exceeds the $2.4-MM which was being carried in the long-range plan.
- UCC 015437
-2-
Assuming that engineering commenced on 1-75, expanded plant operation was pre dicted to beain on 1-77. (Reference 5)
5. The financial Impact of the proposed plant expansion was analyzed on two (Afferent bases viz.
Cose I - Assisting the soles estimate provided by Calidria Marketing (Reference 1) and extending the 1990 projection unaltered through 1985.
Case 2 - Assuming the soles estimate developed by W. C. Thurber (Reference 6) for the 1975 UtPand extending the 1979 projection unaltered through 1935.
Cose II represents a much more conservative product mix and assumes a maximum of 14 M tons of High Purity and 6 M tens of RG-600 - both high margin products, in contrast. Case l assumed 20 M tons of High Purity and 12 M tons of RG-600. As can be seen below, the projected financial performance is highly sensitive to these product mix assumptions.
Financial Performance 1975 LRP
Sales Net Income %ROA %ROI NPV
$ 5.4M $ 0.7M
14.5% m
-
Incremental Performance Versus 1975
Average Year. Mid 1976-1985
Case 1
Cose II
$ 8.8M $ 3.4M
54.9% 64.3% S14.8M
$ 4.3M ) 0.8M
14.0% 15.9% , $ 0.5M
It is apparent that the quality of earnings from the expanded plant with the conser vative produet mix (Case II) Is no better then the base case although In total dollars the net Income U doubted* A dramatic Improvement In earnings quality Is possible If a Cose I mix conbe realized.
6. Attempts to acquire additional lands around the plant to support the expansion and pro vide a new area for tailings disposal have not been successful. Owners of the Sorenson property (Tract B^which we had sought for a tailings impound have refused to loose or sell. Negotiations are still in progress.regarding the so-called Tract C property which would provide about 18 acres of additional land along the Southern Pacific tracks.
Summary
In light of the Foregoing and other related considerations, expansion of the main circuit has
... UCC 015438
-3-
been deferred to the 1976-1977 time period. Specific factors contributing to this decision include the following:
A. Capital funds required for the expansion were substantially greater than those avail able In the 1975 budget.
B The financial success of the expansion is particularly sensitive to RG-600 sales where we have yet to establish a market.
C. The 1974 downturn in Union Carbide's asbestos business suggests that highest priority should be given to getting the existing operation back on track.
0. The impact of toxicology considerations needs further assessment, especially with regard to Hie extent which OSHA revises existing regulations.
We will continue to assess the King City plant expansion question during 1975, with the following critical Issues clearly defined:
1. As new OSHA regulations are promulgated, evaluate the Impact on sales forecasts.
2. Through continuing market development activities, provide a better definition of future RG-600 markets.
3. Return the existing asbestos business at least to 1973 performance levels, (eg. 11% ROA, 9% sales return).
WCT/es
W. C. Thurber
_ UCC 015439
References 1. J. L. Myers* memorandum July 26, 1974 - "King City Plant Expansion" with attach
ments "Market Projections to 1980" and "Asbestos and Health". 2. W. C. Thurber's memorandum July 18, 1974 - "King City Plant Expansion". 3. V. D. Holt's memorandum to O. J. Malacame July 2, 1974 - "King City Plant Ex
pansion" 936-1148. 4. F. H. Lairison's memorandum August 14, 1974. 5. V. D. Holt's memorandum toR. J Klotzboeh September 13, 1974 - "King City Plant
Expansion Phase I" 936-1148. 6. W. C. Thurber's memorandum to J. W. Rawlings July 2, 1974 - 'Assumptions for
Revised Long Range Business Plan - 1975 through 1979".
UCC 015440
Mean. H. P. Cobb, Jr. V. D. Holt R. J. Klotzboch F. H. Larrlson O. J. Malacame C. P. Martin J. L. Mywt J. W. Rawlings
July 18, 1974 King City Plant Expansion
Reference Is made to my memorandum of June 19, 1974 regarding the King City plant ex pansion. For the 60,000 T/yr. ease (see Table II) I had Indicated a most probable require ment for RG-244 of 3,000 T/yr. and an optimum requirement of 5,000 T/yr. Marketing has new had the opportunity to review these guesstimates and feels that they are overly optimistic. Their considered projection indicates that a capacity of 2,000 T/yr. will handle our require ments through 1977 and that a capacity of 3,000 T/yr. would be required to meet 1980 sales estimates.
In view of these estimates, I would suggest that the most logical course of action at this time would be to consider an Initial plant expansion wherein no additional RG-244 capacity was provided beyond that already scheduled as part of the Phase II activity new underway. At a later date we can separately address the need for additional RG-244 capacity based upon demonstrative capabilities of the Installed Phase II equipment and continued growth of product tales over the next three or four years. Hopefully, the modest Incremental capacity required (!* 1,000 T/yr.) could be handled as a foture working budget item. Therefore, the only requirement at this time would seem to be to provide space In the expanded plant for additional RG-244 equipment which would need to be odded at a later date to bring the pdrcult to 3,000 T/yr. In 1980.
WCT:
W. C. Thurber
UCC 015441
Meun. W. G. Alesio H. P. Cobb, Jr. " J. F. Emerson R. J. Klotzbach F. H. Larrison O. J. Malaeome C. P. Martin J. L. Myers J. W. Rawlings J. C. Stephenson
June 19, 1974 King City Plant Expansion
The Asbestos SPU Is committed in 1974 to developing, documenting and bringing to capital budget status plans for a major expansion of the business, in order to provide proper perspective for the Management Committee on Union Carbide's Asbestos Business prior to (or perhaps concurrent with) requesting approval of a CBP fcr plant expansion. It will be necessary to display our strategic plans regarding asbestos. This memorandum provides a status report on the work com pleted to date and sets forth a schedule and further guidelines for fulfilling this commitment. Status of pertinent developments is as follows:
1. Studies conducted at King Ctty by W. C. Purls et ol in January and February demonstrated that the capacity of the existing rock-fiber circuit is 60,000 T/yr. of standard grade product. By way of comparison, 1974 total plant production based by five months actual experience Is 33,000 tons. (References 1,2,3 & 9)
2. A survey of markets for short fiber crysotiie was completed In April, 1974, by an outside consultant supported by the Asbestos Sales group. (Reference 8) This study concentrated on current and clearly identified future markets for Group 7 fibers, with especial emphasis on domestic consumption. RG-244 sales oppor tunities were not addressed. Pertinent results of this survey are Included in Table 1.
3. The Asbestos Sales group Is In the process of translating the results of the market survey Into specific quantified opportunities for Calidria products. Preliminary results are available which suggest a 1980 potential market af at feast I10M tons. A formal report should be completed by July 1, 1974.
4. Preliminary discussions have been held with PG&E establishing the cost and avail ability of additional natural gas to support expanded operations at King Gty. (Reference 4)
5. The question af tailings disposal has been examined in some detail, if we con tinue to dump at the current location, filling the existing gully only to a mere
UCC 015442
-2-
or less level contour (i.e. no tailings pile) which could be easily stabilized, land is available to hj;.die about 180,000 tons of production, assuming 60% product recovery from are. Based upon disposal of the existing tailings pile Immediately adjacent to the plant tailings conveyor and using estimated yearly production levels from the 1973 Long Range Business Plan, available land would be exhausted by early 1978. Alternatively, a tailings pile could be created using much of the land behind the plant. Assuming that this approach was en vironmentally and politically acceptable, we could handle from 832M to 3, 876M tons of production, depending upon the amount of land committed to this approach. A mete desirable approach aver the long term would be to ac quire some land southeast of the existing property which contains a large natural depression Ideally suited for tailings disposal. Engineering estimates that this land a>uld handle tailings generated over at least a thirty-year period. Tailings could either be pumped or trammed from the miii to this new dump. (References 5,617)
6. Cgciaeostrtwith ^5 above, inquiries have been Initiated with a view toward acquiring that land containing the large natural depression for tailings disposal. Two tracts are Involved. Tract A owned by the Johnson family Is likely to be unavailable since certain covenants In a deed of sate for adjoining lands to a vineyard require that use of unsold land be confined to agricultural or grazing purposes. Since this tract Includes only the narthernNmcst end of the depression, we could do without by building a tailings dam across the depression on the large adjacent Tract B.
Tract B , owned by the Sorenson family, contains most of the land of Interest (approx. 112 acres). This land 1$ held for tax purposes in an agricultural preserve and discussions with the Monterey County Land Board indicate that obtaining re lease and rezoning of such land is without precedent. The possibility does exist that we could obtain a long-term lease on Tract B from the Sorenson family and a special land use permit from the County for tailings disposal. This possibility it being explored currently.
We are aba Investigating the possibility of acquiring about 18 acres (Tract C) Immediately south of the mill side along the Southern Pacific railroad trades. This tract would provide additional bulk car loading space and area for storage bins. The kmd has been appraised and the next step is for Union Carbide to make a positive offer to the owners. This will probably be in the form of a five-year lease with option to purchase contingent upon rezoning, etc. (References 10, 11, 12, 13 & 14)
7. Extensive cast studies documenting the merits of hydraulically transporting asbestos from the mine to the mill site were made in 1964. A quick and dirty update of
UCC 015443' '
-3
these studies was carried out In February. This update suggests that a pipeline Is Favored at 180,000 tons per year product rate but Is not economical at 100,00QT/yr. In addition, the pipeline appears to be more energy Intensive than truck haulage. For these reasons, hydraulic transportation will not be further considered now. (Reference 15)
Based upon the Information generated to dote. It appears that the next step is to develop pre liminary capital and operating cost estimates far two sizes of plants. The first Iteration would be to expand the existing plant up to the capacity of the rock fiber circuit (l.e. 60,000 T/yr. standard grade). In this context the ramifleotlons of two product mixes should be examined, viz. (1) a "most probable* mix where about 25% of the output Is standard grade material and(2) an "optimum1* mix where most of the output Is xiper standard and high purity product. De tails on mix are Included In Table II. It Is recognized that nominal 60,(XX) T/yr. rate applies to standard grade product and that the capacity would perforce be down-graded as more higher quality products are produced. Features included In this plant are (1) expanded RG-244 capacity to 3 - 5 T/yr. versus the 2.1 T/yr. available when the Phase II expansion Is com pleted) (2) ability to make DMBP-treated product (RG-600) at a rate of 12 T/yr., and (3) space to add other treatment equipment for add leaching, etc*
The second Iteration Is a tIOMT/yr. plant (50MT/yr. standard grade and 60MT/yr. super standard and high purity). Conceptually this might Involve producing a nominal 6QMT/yr. of high quality products in the present plant as expanded and 50MT/yr. standard grade products In an additional new plant. Such an approach would offer the possibility of a two-step expan sion (l.e. from 35 to 60 T/yr* now mid from 60 to 110 T/yr. later). Desirable aspects of a two-step expansion include:
1. Cess capital required in the near femg
2. Reduced expeexe to negative Impact from unfavorable changes In asbestos regulations:
3. Hedge against non-asbestos floor Hie making amfer Inroads Info existing HU market*
Summarizing than the following cases should be examined:
Cose \
Expand plant to capacity of rock-fiber circuit assuming "mart probable" product mix in Table ii.
Case Ift Same as Case I but with "optimum'* product mix from Table it.
Case II
Case (A Implemented In 1975 followed by addition of SO-T/yr. standard grade capacity in 1978*
UCC. 015444
Case HI Expand the plant to 110,000 T/yr. capacity immediately.
Milestones
July 1, 1974
Complete market analysis ^
J. L. Myers
July 15, 1974
Proride year" by-year breakdown of sales by product
mix at levels at 6QM and llQMT/yr. through 1980
J. L. Myers ~
August 1, 1974
Prepare assumptions for operating cost estimates
O. J. Malacame/ F. H. Lorrison/ H. P. Cobb, Jr.
August 15, 1974
Complete preliminary capital costs estimates and Schedule for expended plants sized at 6GM and llOMT/yr.
O. J. Molooame
September 1, 1974 Complete preliminary operating cost estimates far expanded plants
O. J. Malocame/ F. H. Lairlson
September 13, 1974 Complete financial analysis of Asbestos Business based upon above operating and capital costs
H. P. Cobb, Jr./ W. C. Thurber
September 18, 1974 Prefect Review
AH Concerned
September 25, 1974 Initiate scope engineering, assuming favorable prefect economics
O. J. Malacame
November 25, 1974 Complete scope engineering package
O. J. Malacame
December 15, 1974 Present strategic plans and CBP to Management Committee
W. C. Thurber/ J. W. Rawlings
January 1, 1975
Initiate King City Plant Expansion
Alternate Schedule
October 15, 1974 Present strategic plans to Management Committee
December 15, 1974 Submit CBP on expanded plant to Management Committee UCC 015445
W. C. Thurber/ J. W. Rawlings
W. C. Thurber/ J. W. Rawlings
5I would appreciate any comment* which you may have on these guidelines and schedules.
WCTres Attachments - 2
W. C. Thurber
References:
1. O. J. Malaoame memorandum December 19, 1973, Plant Expansion * King City Phase I (935-1148).
2. N. L. Grauerhob Trip Report February 4, 1974, Visit to King City.
3. O. J. Malocame, et ol. Trip Report February 6, 1974, Trip Report No. 74-T-2.
4. A. K. Seefeldt (PG&E) letter to F. H. Larrison April 1, 1974.
5. R. O. Morsten memorandum February 4, 1974, Tailings.
6. R. O. Moisten memorandum January 14, 1974, Tailings.
7. O. J. Malocame memorandum January 3, 1974 - King Gty Tailings - Recommended Silo (935-1148).
8. G. Vtielhe *CrysottIe Asbestos Market Analysis* Group 7 (Shorts) April, 1974.
9. W. C. hris report "ftoducflan Rate Tests at the King Gty Plant* February, 1974.
10. C. P. Martin nmoron Jum to W# C. Thurber February 13, 1974, Land Acquisition King Gty, California.
11. C. P. Martin momorandum to W. C. Thurber April 17, 1974, Land Acquisition King Gty, California, Appraisal - Tract C.
12. C. P. Martin memorandum to P. J. Morgan March 29, 1974, Laid Acquisition King Gty, California - Tract A.
13. C. P. Martin memorandum to W. C. Thurber March 21, 1974, Land Acquisition King Gty, California.
UCC 015446
14. C. P. Martin memorandum to W. C. Thurber February 27, 1774, Land Acquisition King City, California.
15. T. J. Kagetw memorandum to W. C. Thurber February 14, 1774, Hydraulic Transpor tation of Asbestos 935-3016.
TCC 015447