April 24, 1978
EXXON GETTYSBURG Shipyard Repairs
Newport News Shipbuilding 4101 Washington Avenue Newport News, Virginia 23607
Attention: Mr. G. Guy Via, Jr. Vice President
Dear Guy:
The EXXON GETTYSBURG is nominated for ship repairs under the terms of our October 1, 1973 contract. The vessel should arrive in the yard on or about May 30, 1978. We will keep you advised of any changes to this schedule.
The work to be accomplished includes USCG Biennial Inspection, ABS Special Survey, Drydocking, cargo tank coatings, steel renewals, miscellaneous other repairs, and betterments which are described in detail in the attached specifications. We request your early preparation of the estimated material costs and man-hours for completing the work described in each item on these specifications. Please indicate the item(s) considered to be the control ling jobs, the amount of overtime necessary to expedite delivery by working overtime on the controlling jobs, and the amount of time which would be saved by authorizing overtime on this basis.
For purposes of Article IV of our contract, the forecast worth of the vessel is ATRS + 160 % which equates to $18,000 per day. Please indicate your agreement with, the vessel's value by signing and returning one copy of the letter.
Very truly yours,
H. P. Ley^hdecker Repair Superintendent
HPL: bt Attachment
c: Mr. H. J. Borgen Mr. R. E. Gordon Mr. L. A. Hanf t Mr. W. A. Ingham Mr. E. J. Worrel, Jr.
A DIVISION OF EXXON CORPORATION
(w/o attachment) (w/o attachment) (w/o attachment) (w/ attachment) (w/ attachment)
G. Guy Via Jr.
EXX-MOR-010575
GENERAL SPECIFICATIONS
The following are some general specifications pertaining to all work done during this repair period.
a. Cargo piping 6" or sore in diameter to be schedule 40, blasted in and out and coated with RB-191; less than 6" to be schedule 80 and blasted in and out and coated with RB-191
b. Steam and exhaust piping to be schedule 80 steel.
c. All steel installed aboard vessel including brackets, internals, ladders, etc. , to be blasted and coated with RB-191.
d. All pipe hanger bolts and ladder bolts installed on deck or in tanks to be
galvanized or cadnium plated.
.
e. All steel work to be cleaned and coated with primer at completion. All disturbed areas to be cleaned and coated with primer. All steel work on which the zinc coating has been disturbed due to welding shall be wirebrushed and recoated with RB-191.
f. All disturbed insulation in way of all repairs shall be patched and placed in good order as necessary.
g. All Rust-Ban 191 specified in these specifications will be supplied by the vessel, until those current supplies presently onboard are exhausted.
1. EQUIPMENT REMOVED FROM PLACE ABOARD VESSEL
Valves, motors, machinery parts, etc., not otherwise designated by Owner's
^
Representative for removal from vessel for repair or shipment, or scrap is to be
tagged as to origin and stored in midship house square.
All survey and inspections to be accomplished as soon after arrival as possible.
2. VALVE SPECIFICATIONS (GENERAL)
Pressure test all valves removed from place prior to opening up. All valves found tight required pressure to be repacked and replaced. Renew packing on all valves worked on. All valves to be repaired with new gaskets, bolts and nuts and proven tight. Replace and/or repair disturbed insulation.
3. PROTECTIVE PAPER AND TOPSIDE CLEANING - 503
Furnish necessary labor, equipment and material required to complete the following:
a. Furnish necessary labor and material to install fire retardant protective paper on decks in passageways of quarters. Secure paper with suitable tape.
SHEET NO. 1
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010576
9. TUG SERVICE - 905
Furnish necessary tug service to assist vessel from stream to pier, and from pier to stream and within yard.
10. LINE AND GANGWAYS - 905
Furnish necessary labor and crane service to handle lines and gangways upon vessel's arrival and departure of vessel.
11. FIRE MAIN - 905
'
Furnish necessary material and labor to connect and disconnect fire main to vessel at pier.
12. SHORE POWER - 905
Furnish necessary material and labor to run necessary shore leads and connect up shore power to vessel. Supply shore power to vessel during repair period.
13. SHORE STEAM - 905
Furnish necessary labor and material to run piping and connect up and disconnect shore steam piping to the vessel. Supply shore steam to vessel during repair period.
14. WATCHMAN - 905
Furnish services of watchman to maintain fire watch on vessel during period of
repairs.
.
SHEET NO. 4
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010579
14. GARBAGE - 905 Furnish necessary labor to dispose of garbage.
15. TELEPHONES 905
.
Furnish telephones in engine room and midship's office.
16. SCUPPER PLUGS AND STOCKINGS - 905
a. Before any paint is applied to hull, install wood plugs with extension pipes of sufficient- lengths or other approved means in all scuppers and overboard drains throughout vessel to prevent any water running on hull of vessel. Plugs to remain in until painting is completed and dry and then removed.
b. Install stockings on soil lines, scupper drains from washrooms and air conditioner, also ice machine overboard discharges, while vessel is on drydock to enable ship's personnel to use toilets and washrooms, preventing any water running on shell during painting.
17. PUMPING AND DISPOSING OF CONTAMINATED LIQUIDS - 905
When directed, furnish necessary labor and material to rig pumps and hoses aboard vessel, connect hoses to pump and barge or tank and dispose of contaminated liq uids in accordance with approved procedure. Wien all pumping is completed, disconnect hoses, rig pumps and hoses from vessel. Furnish Ship Superintendent a list of all pumping accomplished including date, spaces pumped, number of items pumped and reason for pumping.
IS. FRESH WATER, COOLING WATER FOR ICE MACHINE AND AIR CONDITIONING CONDENSERS - 905
Furnish necessary labor and material to supply fresh water as required (wash and drinking). Also run hoses and connect up and disconnect hoses to the vessel for ice machine and air condition cooling water; supply water to vessel during repair period.
19. CARGO TANK, MACHINERY SPACE AND ENGINE ROOM CLEANING - 902
Contractor to provide necessary labor to clean and remove debris, resulting from repairs, modifications and/or alterations during this year period, from all ma chinery spaces, pump rooms, cargo and ballast tanks including bilge areas of aforementioned spaces. These spaces to be in the same condition when vessel departs, as when vessel entered shipyard.
SHEET NO. 5
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010580
25.
CRANE SERVICE - STORES - 905
--.................. --
....J--'
L I-aBLagij
Furnish crane' service from time to time as requested by the Owner's Representstive to place stores aboard vessel.
Rig vessel stores from ashore to vessel as delivered by Vendors. Ship supply engine, deck and stewards stores.
26. RECEIVING, SHIPPING, HANDLING AND STORAGE OF OWNER'S MATERIAL - 905
Furnish labor and equipment to receive Owner's materials, as delivered to
<
: shipyard. Pay any -collect freight charges, Custom House brokerage fees, etc.,
due on shipments. Properly store material and, when directed, convey to location
on vessel as designated'.. Receive any material removed from vessel. Properly
store and/or ship' as directed by Owner's Representative, paying any freight
charges, Custom-House brokerage fees, etc., on prepaid shipments.
*'
' * `
27. ENGINE ROOM BILGES -'SHAFT'ALLEY - 905
"
-
Furnish labor and equipment for pumping out and disposing of engine room and shaft alley bilge water preferably designated port and stbd wing tanks of vessel.
28. SKYLIGHT REMOVAL' - . 1G2 . '
Furnish labor and' material to remove the skylights from the engine room and after pumproom. . ' . ` ; : .
Reinstall using new gasket-and bolting material as necessary, upon completion of
all work in way of same
.
29. CARGO PIPING SURVEY - 407
Upon arrival-of vessel in shipyard, provide manpower and material to conduct a hydrostatic test of all cargo piping including ballast and stripping piping test pressure approx. -125 psi, mark all leaks with white or yellow paint and report findings in writing to Repair Inspector. Five (5) copies.
Upon completion of repairs and just prior to ship departing shipyard, set up and test all cargo piping to .Chief Mates and Repair Inspector's satisfaction.
30. CARGO TANKS INSPECTION - USCG & ABS - 107
a. Provide necessary labor to assist USCG and ABS representatives to conduct survey and search out cargo tanks for fractures. Report in writing all fractures found to'Owner's Representative for examination. Five (5) copies.
b. Check condition of Shand and Jurs ''U" bolts - total (60) in (30) cargo tanks. Defective or wasted`bolts found to be dealt with in addendum to this item.
SHEET NO. 7
' '' `
EXXON GETTYSBURG
'
MAY 1978
EXX-MOR-010582
31. MAIN TURBINE AHEAD AND ASTERN THROTTLES - 206
Open main turbine ahead and astern throttle valve. Renew Owner furnished balance piston rings. Fit to recommended vertical height and gap clearance. Machine discs (as found necessary), grind in and lap in and make tight. Hone and polish shoulders from cylinders. Check and set to correct clearance between disc and valve stem. Renew stainless steel fillister head locking screw, tack weld the screw to nut. Renew defective ball bearings in gear train bonnet assembly. Ream all holes true and make and install new pins and bushings in control valve link ages to remove all excessive slack. Reassemble with new gaskets, renew valve stem packing with approved packing. Prove in good order. Harden all nuts after throttle is hot. Replace or renew all disturbed insulation. The vessel is to *be tied up sufficiently so that throttle valve can be tested out by running the main engine. While ahead throttle is disconnected, remove bonnet of oil governor as sembly and renew bonnet gasket. Reassemble governor after renewal of gasket. All of the above to be supervised by Newport News service engineer for Owner's account.
32. RUDDER - 105 '
'`
Carry out necessary work to obtain a certified chemist's gas-free certificate on
rudder before starting any hot work. Remove inspection plates for examination of pintle nuts and bushings and taking of bushing clearances. Test nut in presence of USCG, ABS and Owner's Representative. Reinstall inspection plates and pintle nut retainer stops. Weld solid inspection in place. Examine rudder and rudder horn for erosion and leaks, make all necessary repairs to leaks. Pitted areas are to be sandblasted and covered with red hand cement prior to painting.
33. RUDDER STOCK PACKING - 105
Provide necessary labor and material to remove all old packing and renew packing in top and bottom of glands on rudder stock. Prove grease connections clear.
Repack rudder post using John's Manville NAVALON Packing Style 1-5, Form C-175. Renew defective gland studs and nuts, size 7/8" x 6" stainless steel material.
34. PROPELLER POLISHING - 116
Clean, sand and polish all four (4) propeller blades, all areas including hub. Dress and fair minor dents in all four (4) blades.
35. AFTER PEAK AND FORE PEAK TANKS - 102 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open the after peak and fore peak tanks for ABS survey and examination. Hydrostatic test tanks to ABS requirements. Upon completion drain tanks as directed, close up in good order using new gaskets as necessary.
SHEET NO.. 8
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010583
36. CARGO TANK STRUCTURAL REPAIRS - 102
Allow for erection and subsequent removal of required staging.
Furnish services of audio gauge technician to audio gauge as directed and furnish copies of results.
Allow for cropping and insert renewal of approx, total of 40 ft. x 60 ft. of 1/2" blasted and RB-191 coated Longitudinal bulkhead plating.
Allow for "Teeing out" and welding from both sides an approximate total of 150 cracks.
Allow for cropping and renewing of side shell and/or under deck longitudinals, each approx. 10 ft. long x 15" x 1/2" flanged plate welded to shell or under deck - total of twelve (12).
Allow for cropping and insert renewal of horizontal and vertical brackets on lon
gitudinal and transverse frames for an approx, total of 100, ft. x 50 ft. x 1/2"
plate.
' '
37. SHELL AND BULKHEADS - 103
a. Flood bottoms of all cargo center tanks and fill wing tanks to cover outboard riveted plate, while vessel is on drydock. Mark and report all leaks to Owner's Representative. Repair as directed. Remove and replace plugs and drain water as necessary on completion. All as per ABS survey.
NOTE:
All riveted laps in wing tanks FR 69 to FR 121. Caulk and make tight seventy-five (75) scattered rivets and 100 ft. of seam in way of riveted laps. Vee out and reweld approx. 100 ft. of seams and butts.
b. Fill and test all cargo tanks as required by ABS for survey. Will require filling odd wing tanks and even center tanks. Locate and mark all leaks. Repair as directed. Pump out all water but the ballast tanks as requested by Master of vessel.
38. COFFERDAMS - ABS SURVEY - 102
Open the following cofferdams for ABS survey and examination. Upon completion survey, chip wire brush and clean all rusty areas of the five cofferdams. Upon completion of satisfactory cleaning, apply one (1) touch up coat of red lead primer to entire areas of cofferdams.
One (1) forward cofferdam port and stbd. One (1) aft cofferdam port and stbd. One (1) engine room cofferdam port. One (1) engine room cofferdam stbd. One (1) engine room lube oil sump cofferdam.
'
Close up in good order, renewing defective gaskets, bolts and nuts.
SHEET NO. 9
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010584
39. DOUBLE BOTTOM TANKS - 102 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open the following engineroom double bottom tanks: #1, #2, #3, port and starboard for ABS survey and examination. If found necessary, while vessel is on drydock, hose wash with fresh water, remove all sediment. Upon completion of examination, close up tanks, renew defective cover gaskets. Fill and test tanks as directed. Drain tanks as required.
4. FUEL AND BALLAST TANK - 102 ABS SURVEY - BOLD UNTIL AUTHORIZED
Open the following fuel and ballast tanks for ABS survey and examination. Fill_ and test to ABS requirements.
No. 1 deep tank, port and starboard. Upon completion of test, the tanks are to be drained and wiped dry and closed up in good order.
41. CLAPPER VALVES - SHIPSIDE - 126 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open for examination by ABS surveyors, all shipside clapper valves. Overhaul all valves, prove free, renew defective pins and clapper valve discs as found necessary.
Thoroughly clean and coat inside surfaces with two (2) coats of Coal Tar Epoxy. Renew gaskets, close up in good order renewing studs, bolts and nuts where necessary. Total of (12).
42. ANCHOR CHAINS - 107 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Range on dock forward port, starboard and stern anchor and chains, unshackling
same at bitter end connections, for examination by USCG and ABS. Chain lockers
to be thoroughly cleaned and dirt removed from vessel and suction pipes to be
proven clear. Sandblast and remove all scale, rust and dirt from all chains,
shackles, links, anchors, etc. The first through the fourth outboard shots of
chains to be removed, arid reinstalled on the inboard end of the chain and all to
be coated with fish oil. Remark with paint all shots of chain. Harden up on
anchor shackle pins,~crown pins, and patent link pins. Free-up three (3) anchor
chain swivels (one swivel each chain). Reinstall and stow chains in lockers in
good order.. .
-
SHEET NO. 10
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010585
43. MAIN TURBINE - HP AND LP UNITS - 26500 HP - 201 - ABS SURVEY - HOLD UNTIL
l&ffll"........."--......................................................
........-----
Make necessary removals and remove upper half of both HP and LP turbine casings, secure and raise both turbine rotors for examination and ABS survey. Check all blading. Examine all labyrinth seals and packing, straighten any bent packing, prove free. Examine all nozzle ring alien head bolts, prove same tight'and sound. Prove diaphragms free. Upon completion, reinstall rotors, take and record all blade and bearing clearances, check and adjust to proper thrust bearing clearance. Close up turbines in good order, renewing any defective bearings and etc. (furnished by vessel). Supply Owner's Representative with five (5) typewritten copies of all readings taken prior to and after all adjustments are made. Prove all in good order after running dock trial of four (4) hours. After exposed to heat, reharden all casing flange and pipe joint bolts, proving same tight. Replace all insulation and lagging in good condition, as original. Work to be done under constant supervision of Newport News Service Engineer for Contractor's account. Replace all removals in good order.
44. MAIN TURBINE HP AND LP HIGH SPEED COUPLINGS - 201 - ABS SURVEY - HOLD UNTIL
Open up and remove for inspection, two (2) high speed flexible couplings for HP and LP turbines. Thoroughly clean and check same for wear. Remove shoulders and wire edges by stoning as directed. Remove and clean oil supply pipes and nozzles. Reassemble couplings, oil lines and nozzles in good order. Renew neo prene rubber seal at forward end of coupling covers top and bottom.
45. MAIN THRUST - 106 - ABS SURVEY - HOLD UNTIL AUTHORIZED Take clearance of main thrust bearing. Give reading to Repair Inspector.
46. MAIN REDUCTION GEARS - 205 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open inspection plates of main reduction gears for examination by ABS. Upon com pletion of examination, close inspection plates in good order, renew defective cover gaskets. Remove manhole cover of lube oil sump, clean and reinstall manhole cover with new -gasket.
47. LINE SHAFT BEARING - 106 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open for examination and ABS survey one (1) designated line shaft bearing, after examinaton close up leaving in good order. Renew oil, clean oil sump. Oil furnished by vessel.
SHEET NO. 11
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010586
48. MIN CONDENSER - 230 ~ ABS SURVEY -HOLD UNTIL AUTHORIZED
Open main condenser, removing access cover plates for examination. Wire brush and thoroughly clean tube sheets and tubes. Test condenser to 15 lbs. hydrostatic pressure and prove tight with spectrotest. Plug all leaking tubes and. tighten all leaking packing and renew any defective tube packing found.
Renew Swedish Iron plates and any defective studs, nuts and washers. Harden up on leaking exhaust flange joints.
Shore up condenser for hydrostatic test. Upon completion of work, condenser to be drained and shores removed. Close up in good order, renewing cover gaskets, defec tive studs and nuts.
Chip, power wire brush, thoroughly clean all pitted spots in covers and water box of condenser, fill areas with red hand cement. Remove all defective neoprene coating, thoroughly clean areas. Apply two (2) coats of Exxon Chemical Coal Tar Epoxy 6692 to all areas not coated with Neoprene.
49. AUXILIARY CONDENSER - 230 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open auxiliary condenser for examination. Wirebrush and thoroughly Clean tube sheets and tubes. Clean heads, test condenser to 15 lbs. hydrostatic pressure and prove tight. Repair any damaged areas of neoprene coating. Renew Swedish iron plates and any defective studs and nuts. Harden up on all leaky joints, prove tight. Upon completion of work, condenser to be drained and closed up in good order.
50. LUBRICATING OIL COOLERS (MAIN UNIT) DAVIS ENGINEERING CORPORATION - 233 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open for examination two (2) main lubricating oil coolers. Wirebrush and air lance, clean tubes also clean tube sheets, wirebrush, clean and apply one (1) coat of apexior #3 paint to water boxes and heads. Renew zinc plates, test tubes to work ing pressure, prove tight and close coolers in good order, renew gaskets, defective studs, bolts and nuts.
51. FEEDWATER HEATERS - 228 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Remove covers of the following feed water heaters for examination by ABS. Apply working pressure to shell, prove all tubes tight. Clean channel and cover, renew gasket and defective studs, bolts and nuts. Prove cover tight. Replace insula tion as original:
One (1) first stage feedwater heater Ross #2112 "EUA" Exchanger One (1) third stage feedwater heater Ross #1911 "EUH" Exchanger. Clean tubes. One (1) fourth stage feedwater heater Ross #1912 "EUH" Exchanger. Clean Tubes.
SHEET NO. 12
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010587
52 DEAERATING TANK - 237 - ABS AND USCG SURVEY - HOLD UNTIL AUTHORIZED
Open up deaerating tank for examination and cleaning. Thoroughly wirebrush and clean all internal surfaces, including dome. Remove all sediment and wash down inside of tank with fresh water. Test floats for leaks and make tight, also freeup and adjust all linkage for make-up and dump valves. Blow out, prove clear and tight all air lines. Remove spray nozzle valve assemblies, overhauling as required or if necessary, renew valve assemblies, supplied by vessel. Reinstall assemblies in good order.
Machine seats and disc, grind in, test and prove tight relief valve on deaerating tank -and set valve to lift at 60 lbs. pressure. Remove, clean, test and make tight and reinstall vent condenser. Upon completion of work and examination, close up in good order using new gaskets. Renew all defective studs, nuts and bolts. Replace disturbed insulation and blankets in way of repairs.
53. COMPRESSED AIR TANKS - 235 - ABS AND USCG SURVEY - HOLD UNTIL AUTHORIZED
Open two (2) compressor air tanks for examination by USCG and ABS.
Thoroughly clean, wirebrush internal surface and remove sediment. Upon completion close up tanks in good Order, renewing gaskets, defective studs and nuts.
Test relief valves and prove same in good order, overhaul or renew as found necessary. Size 3/4".
54. EVAPORATOR - 219 - -ABS AND USCG SURVEY - HOLD UNTIL AUTHORIZED
Open for examination one (1) make-up feed evaporator. Remove all coils and baffles, thoroughly scale, wirebrush and clean all surfaces of shell and headers. Remove all coils to shop, clean, test to working pressure, repair all leaking coils by brazing, anneal.all coils, free-up spud nuts, replace all coils in good order, test coils and headers to working pressure and prove tight.
Renew defective zinc plate. Close evaporator in good order, renewing all gaskets, defective studs, bolts and nuts. Test, prove all connections tight.
Machine seats and discs,, grind in, test, adjust, prove tight relief valve to re
quirements of USCG. Repair or renew as original all disturbed insulation and
blankets.
55* FEED PUMP TURBINES (GE 575 H.P.) - 208 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open top casings of No. 1, 2, and 3 feed pump turbines and bearings for examinations and ABS survey. Check and record clearances. Remove rotors' check nozzle plates, intermediate, spacer and etc., renew defective parts, also worn or defective bear ings. Open lube oil pumps and speed changers, check all parts for wear and defects, renew defective p$rts. Clean bearing housings and strainers, test lube oil coolers and prove tight. Polish shaft in way of carbon packing, renew carbon packing, ad just to proper clearances. Reassemble, install correctly, renew gaskets, defective studs, bolts and nuts. Install four (4) rings of carbon packing per box.
SHEET NO. 13
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010588
Clean carbon packing boxes and casing joints. Carbon packing and parts furnished by vessel.
Open governor and trip throttle valve assemblies also air-operated valves. Renew
all worn and damaged parts, close up in good order.
.
Adjust to proper clearances and connect up turbine shaft in correct alignment with pump. After plant in service, test and adjust overspeed trip, prove in good operat ing condition. Renew or replace disturbed insultation as original. Work to be under supervision of GE Service Engineer for yard's account.
56. PEED PUMP WARREN - SIZE 4-TMH-6, GPM 660 - 207 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open casing and hearings of No. 1, 2 and 3 feed pumps for examination and ABS survey. Disconnect and remove impeller assembly. Check and record all casing and impeller wearing rings, also inner stage clearances, check sleeves in way of packing, renew worn or defective parts. Renew worn or defective bearings. Reassemble and reinstall impeller assemblies, 'clean casingfaces, and renew casing gasket (giving special attention to thickness of gasket). Open up oil pump, check and renew defective and worn parts, clean, test, close up in good order. Repack glands with approved pack ing. Test out pumps and prove in good working condition. Parts for pumps, bearing and packing also oil pumps furnished by vessel. Work to be under supervision of Warren Service Engineer for yard's account.
57. CENTRIFUGAL PUMPS - WARREN - 209 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open up thefollowing centrifugal pumps for examination and ABS survey. Remove impell er assemblies to shop as found necessary. Machine and true up impeller in way of sealing rings and renew sealing rings. Renew casing rings, interstage seal and liner on shaft. Work to be under supervision of Warren Service Engineer for yard's account.
Renew sleeves in way of packing, renew bearings (pack with approved grease) adjust to proper clearances. Reassemble, rejoint, repack and prove pumps in good working order:
One (1) fire pump - size 2 1/2 DB6 - 400 GPM Two (2) first stage heater drain pumps - size 2-2CV-11-130 GPM One (1) auxiliary condensate pump - size 4-2CVP-13-380 GPM One (1) auxiliary circulating pump - size 14-DVB-16-GPM-6500,
renew casing studs, bolts and nuts Two (2) Main condensate pumps - size 4-2CYP-13-380 GPM parts
shipped by vessel.
58. MAIN CIRCULATING PUMP - WARREN - SIZE 30SLMV - 210 - ABS SURVEY - HOLD'UNTIL AUTHORIZED
Open up main circulating pump and remove impeller assembly for ABS survey and examina tion. Adjust impeller on'shaft for correct vertical height. Fit the new casing rings to casing. Close up circulator in good order, using manufacturer's prescribed thick ness gaskets. Prove grease fitting clear, repack, prove free and in good order. Renew defective studs, bolts and nuts. Test and prove in good working order.
Spare rotating element on board.
SHEET NO. 14
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010589
59. ROTARY PUMPS - DE LAVAL - 217 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Remove the following designated rotary pumps to shop. Open for examination and ABS survey. Remove rotors, housings, bearings, washers and so forth. Build up original size. Renew worn sleeves, bushings, bearings, washers and end plates.' Check and adjust end clearances. Reassemble in good order, using new gaskets, renewing defec tive studs, bolts and nuts. Reinstall and connect up pumps and motors in true alignment. Pack -couplings with approved grease. Test out and prove units in good operating condition. Repack glands with approved packing. All work to be under supervision of De Laval Service Engineer for yard's account.
Two (2) lubricating oil service pumps - Type A422AV #350, GPM 550 Two (2) fuel oil service pumps - Type A 314X #250, GPM 45
60. BILGE PUMP - WORTHINGTON HORIZONTAL - DUPLEX - SIZE 8 1/2" X 10" - 215 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open bilge pump in machinery space'for examination and ABS survey. Open liquid end, renew liners, renew plungers and rods, machine plungers to fix new rods, renew plunger packing, parts furnished by vessel. Repack rods, close up using new gaskets, renew defective or worn studs, bolts and nuts. Renew bushings if found necessary. Overhaul, machine and grind in seats and discs on suction and discharge valves, renew broken or worn springs and guide studs. Open up gear case for examination, clear out gear case, renew gaskets and renew oil furnished by vessel. Test and prove pump in good working order.
61. PUMPS - WARREN DUPLEX - 215 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open for examination and ABS survey the following designated duplex valve chests. Thoroughly clean all parts, machine suction and discharge valves and seats, renew damaged or broken valves, springs and stems furnished by vessel. Close up pumps in good order, renew gaskets, repack, rods and valve stems with approved packing, renew defective stud's, bolts and nuts. Test out and prove in good operating condition. Replace all insulation, renewing all missing or damaged insulation as original.
One (1)_bilge and general service pump, 16" x 14" x 18" machinery space. Renew seats and.discs liquid end, furnished by vessel. Renew liquid end plunger packing
One (1) fuel oil transfer pump, 10" x 7" x 12" machinery space One (1) bilge and fire pump, 14" x 14" x 12" forward pumproom
62. LUBE OIL COOLER CIRCULATING PUMP - WARREN - 1500 GPM - 233 - ABS SURVEY HOLD UNTIL AUTHORIZED
Open up lube oil cooler circulating pump and remove impeller assembly for examina tion and ABS survey. If found necessary remove coupling and install same on spare assembly. Adjust impeller on shaft for correct vertical height. Fit casing rings to casing as necessary. Close up pump in good order using gaskets of correct thick ness. Prove grease fittings clear, repack, prove free and in true alignament. Re new defective studs, bolts and nuts.
SHEET NO. 15
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010590
53. ONE Cl) GENERATOR TURBINE AND GEARS - 750 KW PE LAVAL - 240 - ABS SURVEY
Make necessary removals and raise upper casing of one (1) generator turbine for
examination and ABS survey. Check all blading, rotor and bearing clearances, hone
shaft in way of bearings. Free up diaphragms,- clean and straighten all damaged
labyrinth seals and packing.
'
Renew defective packing, also defective or worn bearings furnished by vessel. Check, adjust if found necessary turbine rotor and pinion shaft alignment, also adjust nozzle and thrust bearing clearances, when ready reassemble, replace all removals. Clean flexible coupling.
Open for examination nozzle val-ve chest, clean and free up all nozzle valves, adjust
to proper clearances. Close up nozzle chest in good order. Harden up on all casing
bolts after steam is. on.turbine and replace all insulation to its original good
condition.
Open reduction gear casing for examination and survey. Check and adjust alignment of gear-and generator shaft coupling. Check and. record all'1 clearances. Renew worn bearings and adjust to proper clearances.
Open up lube oil pump, check all parts for wear and defects, renew defective parts, examine all orifice plates in lube oil system for wear, open for examination nozzle strainer for gears, clean, renew gaskets and replace in good order, renew all enlarged orifice plates,- also overhaul and adjust all relief valves. Open up governors and controls, check relays, valves, etc., for wear and renew worn or defec tive parts. Open up bearing on generator shaft, check clearances, renew defective bearings, clean out bearing housings and shaft seals.
Upon completion of .work close up all in good order. Clean oil sump on completion of all work and close immediately after being inspected by Owner's Representative. Vessel to furnish necessary parts and bearings. Lube oil to refill sump furnished by owners. Furnish five (5) typewritten copies of all readings before and after adjustments are made to Owner's Representative. Test and adjust overspeed trip and prove turbines and gear in good operating condition under load. Replace all re
movals in good order.
Thoroughly clean, test and prove lube oil coolers tight, renew zinc plates.
All repairs under supervision of De Laval Service Engineer for yard's account.
64. ONE (1) 750 KW GENERATOR AND 7.5 KW EXCITER - 801 - ABS SURVEY
Remove cover and shield from one (1) 750 KW generator and 7.5 KW exciter. Thoroughly clean windings, rotor, 'field and armature if necessary with approved solvent. Check air gap and binding wires. Bake until satisfactory megger readings are obtained. Apply one (1) coat of approved insulation varnish. Machine slip rings of generator and commutator of one (1) 7.5 KW exciter after above work. Reinstall cover and shield in good order, test and prove in good working condition under load.
SHEET NO. 16
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010591
64. ONE (1) 750 KW GENERATOR AND 7.5 KW EXCITER (Continued)
Open for examination air cooler, wirebrush and air lance. Clean tubes, also clean tube sheets, scrape, wirebrush, clean and apply one (1) coat of Apexior #3 paint to water boxes and heads. Renew zinc plates or rods test tubes to working pressure, prove tight, and close coolers in good order, renew gaskets, defective studs, bolts and nuts.
65. INBOARD 1000 XW G.E. GENERATOR ELECTRICAL MODIFICATION - 240
1. Disconnect the old voltage regulator from the generator and remove it from in place.
2. Install the new static exciter in a suitable location.
3. Install the new static voltage regulator in a suitable location; this regulator should be installed in or near the generator switchboard control panel.
4. Install the new voltage adjusting rheostat (automatic),-the voltage adjusting rheostat (manual) and the new Off - Manual - Automatic SI control switch. These three items should be installed on the front panel of the generator control cubical.
5. Make all electrical wire and cable connections between the generator, the static exciter, the static voltage regulator, the voltage adjusting rheostats (manual and automatic) and the SI control switch. Make all these connections according to the attached wiring diagram No. 44F242252.
6. During the installation of the new equipment, the job should be inspected period ically, by one of our field engineers, to assure that the proper generator and exciter phasing is maintained.
7. After installation, the wiring should be inspected and all connections checked for proper phasing and control function.
'8. All pre-startup adjustments to the exciter and voltage regulator should be performed.
9. The unit should now be started up and the unit check out and start up should be performed.
10. The unit should first be started in manual and after satisfactory operation, the Auto-Control mode should be tried.
11. After satisfactory operation of the above, the generator should be loaded and all necessary regulator adjustments be made.
The attached control and wiring diagrams are the prints for the job and should be followed when making any wiring connections. Supervision by - General Electric Svc. Engineer - Owner's Acct.
SHEET NO. 17
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010592
66. AIR COMPRESSOR - SHIP SERVICE - SIZE 6" x 4 3/4" x 5" - 234 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Gardner Denver
Open up ship service air compressor for examination and ABS survey. Clear., grind in suction and discharge valve seats, renew valve strips. Examine crank pin and main shaft bearings, wrist pins and bushings, and oil seals, renew any worn or defec tive parts. Renew piston rings. Examine oil pump, renew defective parts. Clear out sump and renew oil supplied by vessel. Clean air filters. Reassemble using new gaskets. Parts supplied by vessel. Renew defective coupling links. Test and prove in good order.
67. FIRE AND BPTTERWORTH TURBINE - 213 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Raise top half of casing of fire and butterworth turbine for.examination and ABS sur vey. Clean packing boxes and renew packing. Clean top and bottom casing joint faces. Replace turbine casing in good or^ier. Test and prove tight. \-
68. SHELL GAUGING - 103 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Supply necessary labor, staging and equipment to take two (2) complete belts of audio gauge readings as required by ABS to complete hull survey. Supply Owner's Represen tative with five (5) copies of all readings taken.
69. STEERING GEAR PUMP - 238 - ABS SURVEY - HOLD UNTIL AUTHORIZED
Open up port and starboard steering gear pump for examination by ABS. Renew all defective parts. Check all clearances, renew all bearings and oil seals if necessary. Close up pump with new gaskets. Renew any defective studs, bolts and nuts. Test and prove in good order.
Marine Hydraulics - Norfolk - 804 - 487,- - 8871 - Owner's Acct.
SHEET NO. 18
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010593
70. ITEM - CARGO DEEP WELL PUMP - ABS SURVEY - 401
This pump to be opened up in its entirety poor discharge performance. Pump bearings to be renewed. Owner furnished parts.
Rearrange lube oil sump cooling coil so that all fittings are outside unit to avoid possible eontaminization in event of leak.
Complete unit to be reassembled. Realigned and tested and proven satisfactory.
71. ITEM - CARGO BALLAST PIMP ROTATING ELEMENT - ABS SURVEY - 401 AFT PUMP ROOM
Open pump, remove impeller, survey casing for needed repair, install owner fur
nished spar impeller. Re-check coupling alignment, test with air controls, remove
all debris from vessel.
.
Spare impeller on order.
72. ITEM - VERTICAL DUPLEX STEAM CARGO PUMPS - ABS SURVEY - 401 .
A. Port stripper pumps ART pump room - Disassemble liquid ends sufficiently to install owner furnished "darcova" piston cups - reassemble test prove satisfactory. 16 x 14 x 18
_B. Vertical duplex steam solvent pump - portside foward pump room - disassemble suf ficiently to install owner furnished "darcova" piston cups - reassemble test and prove satisfactory. 16 x 14 x 18
C. Vertical duplex steam lube pump - stbd side forward pumps room. Disassemble liquid end - renew damaged liners spare liners aboard - install "darcova" owner furnished pistoneups. Reassemble, test and prove satisfactory. 16 x 14 x 18
D. Vertical duplex steam aux pump - apt stbd side of fwd pump room - disassemble liquid end sufficiently and install owner furnished "darcoua" piston cups, remove (1) one cylinder head and wasted studs - build up by welding and install new studs. Reassemble and test and prove satisfactory. 16 x 14 x 12
E. On all above pumps - over haul operating values and adjust and set valve linkage and prove satisfactory.
7 3. ITEM - (4) MAIN CARGO PUMP TURBINES AND (1) BALLAST PUMP TURBINE ABS SURVEY - 402
HOLD UNTIL AUTHORIZED
'
Make disconnects sufficient to renew all shaft seal chambers and new carbon packing.
Repair distorbed insulation. Test and prove satisfactory.
SHEET NO. 19
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010594
74. ITEM - BILGE PUMP STRAINER BOX - STBD SIDE - 407 SHAFT ALLEY
Disconnect strainer box - send to shop blast and coat and repair wasted section. Reassemble as original and prove tight.
75. ITEM - CARGO SYSTEM GAUGES AND GAUGE LINERS - USCG - 401
A. Disconnect and send to shop and calibrate following 97 gauges - affix test date to gauges and reassemble to place after pump room lower - 29 after pump room upper - 29 deep well pump - 4 risers - mid ships -10 FWD pump room lower - 12 FWD pump room upper -13
B. Test gauge lines to above gauges and prove tight or reneWTonly sections found
leaking.
'
-
76. ITEM - ENGINE DEPARTMENT MOTORS - ABS SURVEY - 805
Disconnect following motors - identify leads and send to shop - open, clean, machine slip rings, renew bearings coat windings, bake, reassemble - give repair inspector 5 copies of before and after megger readings and reassemble and prove satisfactory. .
A - Air conditioning compressor motor - AFT B - Large air compressor motor C - #1 and #2 fuel oil service pump motors D - Exhaust fan motor - fireroom - boat deck level stbdside - staging required E - exhaust motor and fan - AFT pump room portside
77. ' TAIL SHAFT - 106 ABS - USCG SURVEY DO NOT START UNTIL AUTHORIZED BY OWNER'S REPRESEN
TATIVE
-
Furnish necessary labor, equipment and material required to complete the following:
A. Waukesha bearing and seals installed. Vessel's engineers todispose of oil from system. Check centimeter gauge readings in presence of Owner's Representative. Make necessary removals disconnect and remove section of line shafting. Remove aft seal sleeve bolts from propeller face, install distance straps between sleeve and seal housing. Forward stern tube seal-remove bolts from sleeve to clamp ring, re move clamp ring, install distance straps. Remove propeller and draw tailshaft clean tailshaft. Magnaflux shaft taper and in way of keeway and search for frac tures in presence ofUSCG, ABS and Owner's Representative, stone and polish any scratches and bur found on shaft, check bearings, cover shaft to protect same from damage. Disconnect and remove forward and aft stern tube seal assemblies to shop, dismantle for examination of meals, springs sleeves, etc. Renew all defective parts furnished by Owner. Reassemble in good order, thoroughly clean and flange faces, renew defective gaskets and seal rings, replace renewing defective bolts and wire lacing, use monel wire for lacing bolts together.
SHEET NO. 20
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010595
Upon completion of examination, clean stern tube and drain tank Reinstall tailshaft propeller, aft and forward seals, line shafting and connect up in good order. Fill propeller hub and fairwater with Rust Ban #324 by filling through ABC holes as directed by Owner's Representative. As soon as aft and forward seals are installed, fill stem tube system with new oil furnished by vessel. After four (4) hours, re move drain plugs from seals and check for leaks, replace plugs. Take-and record gauge reading. Fill aft and forward seals with oil furnished by vessel. Replace all removals in way of work in good order. Three (3) copies of all guage readings taken to be given to Owner's Representative.
TAILSHAFT - 106 - (CONT.)
B. While tailskaft is withdrawn, renew, with Owner furnished spares, tailshaft bearings. This will required machining the O.D. and the I.D. of the new bearings to the proper dimensions. Three (3) copies of all stern tube dimensions and final machine size of new bearings to be given to Owner's Representative.
C. All of the above to be done under the supervision of a Waukesha serviceman. Cost of serviceman for Contractor's account.
78* TAILSHAFT BEARING CLEARANCE - 106 DO NOT START UNTIL AUTHORIZED BY OWNER'S REPRESENTATIVE
Furnish necessary labor, equipment and material required to complete the following:
A. Take aft tailshaft bearing clearance with centimeter gauge in presence of Owner's Representative. Drain oil from aft seal, catch in clean container. Flush and refill seal; oil furnished by vessel. Replace removals in good order.
79. SEAVALVES AND STRAINERS - USCG AND ABS - 126
Open up all sea valves in engine room, fire room, pumproom, and cofferdams, includ ing bilge injection, all steam blow out valves and all overboard discharge valves for examination USCG and ABS. Machine seats and disc as necessary, grind in, re pack, rejoint and close up valves in good order. Remove all sea strainers for examination of sea chest; thoroughly scrape and wirebrush sea chests to bare metal and apply two (2) eoats of Exxon Chemical Coal Tar Epoxy 6692. Replace sea strainers and renew defective and missing lugs, bolts, studs, nuts and cotter pins. Clean out and prove' steam blow lines clear between valves and sea chest. While above valves are open, clean and coat with two (2) coats of Exxon Chemical Coal Tar Epoxy 6692. Note some sea valves are coated with Neoprene. All damaged sur faces are to be scaled and wirebrushed and thoroughly cleaned and apply Exxon Chemical Coal Tar Epoxy 6692 to all bare areas. Secure aft pumproom sea valve discs to stem lock nuts by track brazing (3).
SHEET NO. 21
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010596
Valves are as follows:
1. One (1) 3-1/2" gate air conditioner cooling water overboard, aft Starboard side shaft alley. .
2. One (1) 5" angle low sanitary sea suction - Starboard side shaft alley.
3. One (1) 3/4" angle steam out valve at low sanitary sea suction - Starboard side shaft alley.
4. One (1) 5" angle high sanitary sea
suction - Portside shaft alley.,,
5. One (1) 3/4" angle steam out valve at high sanitary sea suction - Portside shaft alley.
6. One (1) 4" gate bilge overboard - Starboard side shaft alley. ,
7. One (1) 3" gate cooling water overboard (Reefers, fire and butterworth pumps and #3 feed pump) - Starboard shaft alley.
8. One (1) 10" angle fire and bu-terworth suction - Portside shaft alley.
9. One (1) 6" angle bilge and ballast suction - port side shaft alley.
10. One (1) 6" gate fire and butterworth overboard - portside shaft alley.
11. One (1) 3" gate cargo pump cooling water overboard - Starboard side forward
engine room - lower level.
'
12. One (1) 4" air cooler and generator cooler overboard - Starboard side - forward
engine room - lower level.
'
13. One (1) 16" angle aux. circulator sea suction - Starboard side lower engine
ctoom.
- ' _'
14. One (1) 16" angle aux. circulator sea suction - Starboard- side lower engine
room.- .. .. -
15. One (1) 6" angle fire pump sea suction - Starboard lower engine room.
16. One (1) 1" globe steam out valve at fire pump sea suction - lower engine room.
17. One (1) 16" gate aux. circulator overboard - Starboard side lower engine room.
18. One (1) 2-1/2" gate electric fire pump overboard - Starboard - lower engine room.
19. One (1) 4" low pressure evaporator feed suction - portside lower engine room (renew)
SHEET NO. 22
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010597
20. One (1) 28" gate main cond. high sea suction - portside lower engine room. 21. One (1) 3/4" globe steamout at high sea suction - Portside lower engine room. 22. One (1) 30" gate main cond. low sea suction - portside lower engine room.
23. One (1) 3/4" globe steamout valve at low sea suction - portside -lower engine room.
24. One (1) 30" gate main cond. overboard - portside - lower engine room.
25. One (1) 6" gate lube oil cooler overboard - portside lower engine room.
26. One (1) 8" angle lube oil cooling water pump suction - portside lower engine room.
27. One (1) 6" angle general service pump suction - portside - lower engine room.
28. One (1) 3/4" globe steamout valve at service pump suction - portside lower engine room.
29. One (1) 5" gate general service pump overboard - portside lower engine room.
30. One (1) 3" gate cargo oil heating coil drain cooler overboard - portside lower
engine room.
'
31. One (1) 2" globe make up evaporator overboard - portside lower engine room.
32. One (1) 3-1/2" globe low pressure evaporator overhead - portside lower engine room.
33. One (1) 3-1/2" globe distiller overboard - portside - lower engine room.
34. One (1) 3-1/2" boiler blow - portside - fire room.
34-B One (1) 28" emergency bilge suction - globe - engine room portside lower - FWD
FORWARD PUMPROOM 35. One (1) 5" gate - bilge pump overboard - starboard side. 36. One (1) 6" bilge pump suction - Starboard side. 37. One (1) 3/4 globe steam valve at pump suction - Starboard side.
38. One (1) 10" ballast pump suction - portside.
SHEET NO. 23
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010598
39. One (1) 3/4" globe steam out valve at pump suction - portside. 40. One (1) 10" gate ballast pump overboard - portside.
AFTER PIMPROOM
'
41. One (1) 16" angle cargo pump suction - portside.
42. One (1) 3/4" globe steam out valve at pump suction - portside.
43. One (1) 3/4" globe steam out valve at pump suction - Starboard side.
44. One (1) 4" gate stripper overboard - Portside.
80. LIFEBOATS - 108 USCG SURVEY
Furnish necessary labor, equipment and material required to complete the. following:
A. Remove all gear from four (4) lifeboats, including air tanks, provision boxes, etc., for inspection in accordance with USCG and ABS requirements. Profide storage boxes with locks and keys for stowing above gear. Keys for boxes to be given to Chief Mate and will be returned to yard upon completion of restowing lifeboats. Restow lifeboats as directed by Chief Mate.
B. Test, make necessary repairs, and prove tight all air tanks.
C. After all gear is removed from lifeboats, remove four (4) lifeboats from vessel to sandblasting area. Sandsweep entire hull to each boat to remove all paint and scale. Survey hull plates upon completion of this operation, and repair as directed by Owner's Representative. Upon completion of repairs, coat entire hull with RB-191. (Two lifeboats are diesel powered and will require protection to diesels during sandblasting and painting.) Apply one (1) coat of approved primer to entire hull allowing recommended drying time before finish coat is applied. Apply one (1) `coat of approved color coat to inside of hull.and one (1) coat of approved color coat to outside of hull. Restencil lifeboats as original and return them to vessel.
D. Allow for the renewal of four (4) hull plates (shaped) in each lifeboat (total of sixteen (16) plates 1/8" thick galvanized sheet metal, approximately 4' x 8').
81. LIFEBOAT WEIGHT TEST - 108 USCG
Furnish necessary labor, equipment and material required to complete the following:
A. Make necessary preparations as required and weight test four (4) lifeboats and related equipment as per USCG requirements.
B. Free up, grease and prove in good working order releasing gear on all four (4) lifeboats.
SHEET NO. 24
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010599
C. Open as required by USCG for inspection, limit switches, disconnect switches and motor controllers. Renew defective cover gaskets. While above switches and controllers are open, clean and free up and prove in good working order.
D. Adjust limit switches on all four (4) boats.
82. LIFERAFTS - USCG - 108
Provide necessary labor and crane service to remove two (2) liferafts from vessel to service truck (liferafts to be sent out for servicing cost of which is to be for Owner's account). Upon redelivery of liferafts, restow as original in liferaft racks.
83. ITEM - LIFEBOAT DAVITS - 121
Wash off and renew total of (4) four 2" x 2" x 3/8" x 4" long angle brackets on which lifeboat keel are landed - make sure of proper fit and location.
84. ITEM - LIFEBOATS - 108
Allow for renewal of 20% of internal wood structure in each of (4) four lifeboats.
85. ITEM - LIFEBOAT RUDDERS - #1, #2, #3, #4 - 108
Rebuild and or renew life boat rudder gudgeons and tiller assembly per USCG
specifications.
.
86. HEM - #3 STBD AFT LIFEBOAT AFT END DAVIT - 121 LINK CHAIN AND BLOCK
Renew deteriorateo chain and block. AFT chain wasted so that it is lengthened and boat cannot be raised by cable high enough to seat properly.
87. ITEM - LIFEBOAT DAVIT ASSEMBLY - 121
Sandblast to white metal entire davit "A" frame assembly including davit channel and releasing gear, and coat with R.B 191 on number 3 and 4 lifeboats. Said work does not include davit arms.
SHEET NO. 25
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010600
88. PRESSURE VACUUM RELIEF VALVES - 408 - USCG SURVEY
'
..
Open up for inspection of USCG and Owner's Representative- all pressure vacuum
valves to cargo tanks. Thoroughly clean, machine seats and discs, grind in and
renew defective flame screens. Close up valves in good order after being passed by
USCG and Owner's Representative. Renew all defective studs, nuts, screws, and
screens. A total of thirty (30) valves.
'.
89. FLAME ARRESTORS - 408 - USCG SURVEY
.
Open up six (6) flame arrestors for cargo vent system for examination by USCG.
Thoroughly clean and free-up. Renew defective flame screens. Close up in good
order. Renew defective studs on flame arrestors.
'
90. SPILL VALVES - 408 USCG SURVEY
"
Open up seven (7) spill valves located on vent piping for inspection in accordance
with USCT requirements. Thoroughly clean, machine seats and discs as found ne
cessary and grind in. Renew defective flame screens, gaskets-, -also defective of
missing brass capscrews and close up in good order.
''
91. FIRE DAMPERS - USCG - 110
Furnish necessary labor, equipment and material to complete the .following:
A. Free up, put in good working order, and grease all fire dampers to spaces
covered by fixed fire extinguishing system, including fore.-and after pumprooms
and after machinery space.
. '. '
'
Allow for eight (8), no staging required.
. ... '
' -
92. EIRE EXTINGUISHERS AND C02 SYSTEM - USCG - 110 HOLD UNTIL AUTHORIZED
Furnish necessary labor, equipment and material required to complete- the following:
Goldsmith Chesapeak - 804.543
.'
:
A. Weight all main cylinders, also portable cylinders for -C02 Kidde. firefighting
system. Recharge all underwight cylinders. Check with-compressed air and assure
free operation of all pullers, controls, pipelines, nozzles, alarm sirens, etc., and
prove everything in good working condition.
'
''
SHEET NO. 26
EXXON GETTYSBURG
. MAY 1978
EXX-MOR-010601
Supply Owner's Representative with six (6) certified copies of weights of cylinders and also attesting to full efficiency of system.
93. BOILER SAFETY VALVES - USCG - ABS - 315
Furnish necessary labor, equipment and material required to complete the following:
A. Disconnect and remove two (2) superheater relief valves and four (4) safety valves from two (2) boilers. Valves are to be repaired by an approved safety valve service shop. Valves are to be thoroughly cleaned, including all working parts. Seats and discs machined as found necessary, ground in defective parts including nozzles, etc., renewed. Test and prove valves steam tight at working pressure with proper-relief and blow back pressures. Reinstall valves on boilers. Renew ing gaskets, defective studs and nuts. Test out valves and make all necessary adjustments after steam has been raised on boiler. Prove all in good order accord ing to U.SCG and ABS requirements. Connect up lifting gear and replace all removals in good order. Cost of repairs for Contractor's account.
B. On vessel's arrival at'yard, and before plant is shut down, arrange for USCG and ABS inspectors' attendance to test all safety valves in place. Arrange for necessary labor to gag and make any required adjustments during the tests.
94. FOXBORO CONTROLS FOR MAIN FEED PUMPS - 311
Overhaul and service the Foxboro controls for the main feed pumps renewing all worn parts furnished by vessel. Test and prove in satisfactory working order.
95. INTERNAL CLEANING - MAIN BOILERS - 302
Open up two (2) babcock and Wilcox boilers for internal examination and cleaning, including steam and water drums, water wall headers and superheater tube headers. Remove all handhole plates on each boiler for examination and cleaning boiler tubes and headers. Thoroughly wash out boilers with fresh water. Clean and remove all sludge and sediment from drums and tube headers. Build up by welding in way of defective handhole seat landings,, a total -of thirty (30) handholes. Set up and machine landings true. Renew all removed gaskets. Close up boilers with new gaskets on doors after boilers are steamed to 400 psi and plates have been hard ened up. Replace all removals. Apply working pressure hydrostatic test prior to steaming. Report all tube leaks to Owner's Representative.
96. EXTERNAL CLEANING - MAIN BOILERS - 303
Scrape, wirebrush, and thoroughly clean all external heating surfaces of two (2) Babcock and Wilcox boilers, including stack, uptakes, fan damper vanes, casing, air ducts, air heater tubes, economizer, generating and superheater tubes. Wash air heater, economizer, generating and superheater tubes with fresh water under pressure and at approximately 150F. temperature. Special attention to be given to the cleaning of superheater, economizer and generator tubes, hand lancing when found necessary. Upon completion of cleaning, remove all sludge and sediment from
SHEET NO. 27
- EXXON GETTYSBURG
MAY 1978
EXX-MOR-010602
boilers and vessel and replace all boilers casing access doors renewing asbestos tape gaskets as necessary plus air tight. Renew all missing or defective studs and bolts. Special attention to completely cover electric and mechanical equipment in shaft alley under boilers before washing is started. The shipyard is to pro vide all thenecessary drain hoses and pumps to keep the shaft alley bilges and engine room bilges pumped out during entire shipyard period. During the washing process on boilers the furnace fronts in way of the burners are to be covered with water proof material. The bailey board fireroom and engine room peabody console are to be-boxed in with plywood to prevent damage to same.
97. BOILER REFRACTORY - PORT AND STARBOARD - 304
Repair brickwork and refractory in furnaces of two boilers. Repair of renew front
wall of each furnace including burner arches in way of eight burner openings.
Renew defective short bladed grids and flame diffusers. Grids and diffusers to be
supplied by vessel. Remove blades in grids and cut proper openings in diffusers
for ignition and flame detectors before installation. Renew missing or defective
studs, bolts, and nuts. Repair refractory in way of side back and roof tubes and
superheater supports. Renew bottom baffles and repair top with Crome Ore. Renew
two (2) baffles. Repair floors. Floor level to be 3'9" from center of bottom
burner. Renew corbel in way of front wall, side wall, rear wall, lower drum and
top rear wall header.
Note: Make sure of opening above lower drum. See Babcock and Wilcox Boiler
Drawing.
If existing floors have pebbles, they are to be renewed with Oceanite pebbles and binder to a depth of 2 1/2".
98. INTERNAL DESUPERHEATER TEST - TWO (2) BOILERS - 307
While boilers are opened up for internal cleaning, remove necessary baffles, grating,
etc. from top drums for examination of internal desuperheater, pipes and connections.
Apply hydrostatic working pressure of maximum 150# to desuperheater, pipes and con
nections and locate all leaks. Repair as directed. Prove tight. Replace all
removals in good order.
'
99. PEABODY AUTOMATIC FIREMAIN - 311
Individually clean, dehydrate and keep dry three console cabinets. Furnish and install protective covering during repair period.
100. PEABODY BOILER CONTROLS - 311 HOLD UNTIL AUTHORIZED
Check out entire system and repair as required for proper operation. This work to be performed and supervised by Smith Marine Service Technician. Charge -- Owner's account.
SHEET NO. 28
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010603
101. BAILEY AIR OPERATED BEEP WATER REGULATORS - 307
Disconnect and remove to shop two (2) automatic feed water regulators, size 4" open up, machine seats and discs, grind in, repack, rejoint, test, prove tight at working pressure. Renew defective cages, cages, disc, valve stems, and diaphragms using only Bailey parts, replace on vessel in good order, renewing gaskets, defec tive studs and nuts.
Make necessary adjustments and prove in good working order when boilers are operat ing under light and full load capacity. Repairs to be carried out under supervi sion of Bailey service engineer. Follow up on nuts when valves are hot. Replace insulation as original.
102. HULL PAINTING (SPECIAL COATING SYSTEM) - 61-501
GENERAL
A. The entire exterior shell surface from turn of bilge to rail, oil and grease to be removed using Owner supplied cleaner, and entire area; then wash down with fresh water under pressure. No. 8555 Exxon Chemical Company Cleaner, or equal.
B. Before any paint is applied to hull, install wood plugs with extension pipes of sufficient lengths or other aproved means on all scuppers and overboard drains throughout vessel to prevent any water running on hull of vessel. Plugs to remain in until painting is completed and dry and then removed.
C. Install stocking on soil lines, scupper drains from washrooms and air condi tioner, also ice machine overboard discharges while vessel is on drydock to enable ship's personnel to use toilets and washrooms, preventing any water running on shell during painting.
D. Piant will be supplied by Owners.
E. Paint may be sprayed on. Drying time allowed between each coat of paint to be in full accordance with manufacturer's recommendations. All surfaces are to be inspected and approved by Owner's Representative before applying painting coat and before applying each additional coat. All- painting to be done only during clear and dry weather.
NOTE: Before starting abrasive sweeping or painting, cover transducer, hull anodes and reference ceils. Upon completion, remove in good order.
KEEL TO LIGHT LOAD LINE
A. Abrasive sweep entire bottom to light load line to remove all fouling, grass, rust and dirt.
B. Apply one (1) spot coat of Devalum Aluminum Barrier MD-2548. (Light) or equal to a thickness of 5 wet mils (2 mils dry).
SHEET NO. 29
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010604
HULL PAINTING (SPECIAL COATING SYSTEM) 61-501 (CONT.)
C. Apply onefull coat of Devalum Aluminum Harrier MD-2548 Bottom Composition. (Dark) or equal to a thickness of 5 wet mils (2 mils dry).
D. Apply one full coat of Devoe Raynold Super Tropical Anti-Foul MD-2771 to a thickness.of 3 wet mils (1.5 mils dry).
NOTE:
External Hull Areas in square feet
Bottom - light load line - 68,100
Boottop
26,100
Deep Load Line - Rail
25,240
LIGHT LOAD LINE TO DEEP LOAD LINE
A. Abrasive .blast to near white metal all rusty and bare areas including rusted weld seams, port and starboard (see below). Apply the following Devoe paints.
B. Apply one (1) coat Cathacoat 302 Inorganic Zinc to a thickness of 4 mils dry to all blasted areas. Minimum recoat interval is 8 hours at 77 F. , and 50% relative humidity.
C. All areas not covered by spot blasting in Section (a) of Part 3 will be given an extra heavy abrasive sweep to remove all rust stains, loose and brittle coatings.
D. Apply one (1) full coat Devoe Special Primer MD-4368, one component epoxy, to a thickness of 5 wet mils (1.0 mil dry). Product may be thinned with TH 5859 up to one (1) pint per gallon as required. Minimum drying time before recoating is 4 hours at 77 F., and 50% relative humidity.
E. Apply one (1) full coat of Devoe Polyurethane Red Oxide (MD-4622/4619) to a thickness of 6 wet mils (2.5 mils dry).
HULL PAINTING (SPECIAL COATING SYSTEM) 61-501 (CONT.) DEEP LOAD LINE TO RAIL .
A. Abrasive tonear whitemetal all rusty and bare areas including rusted weld seams, port and starboard. Apply the following Rust-Ban paints.
B. Apply one (1) coat of Cathacoat 302 Inorganic Zinc to a thickness of 4 mils dry to all blasted areas.
C. All areas not covered by spot blasting in Section a of Part 4 will be given an extra heavy abrasive sweep to remove all rust stains, loose and brittle coatings.
SHEET NO. 30
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010605
D. Apply one (1) full coat Devoe Special Primer HD-4368, one component epoxy, to a thickness of 5 wet mils (1.0 mil dry). Product may be thinned with TH5859 up to one (1) pint per gallon as required. Minimum drying time before recoating is 4 hours at 77 F., and 50% humidity.
E. Apply one (1) full coat of Devthane Polyurethane Dark Gray MD 46Z0/4619 to a thickness of 6 wet mils (2.5 mils dry).
HAILING PORT, VESSEL NAME, AND DRAFT MARKS A. Paint in above markings using Devthane 4618/4619 white.
103. RIVETS - 103
..
DO NOT START UNTIL AUTHORIZED BY OWNER'S REPRESENTATIVE
Furnish necessary labor, equipment and material to complete the following:
A. Caulk and make tight fifty (50) rivets in bilge strake.
B. Caulk, then ring weld and prove tight a total of fifty (50) rivets.
C. Caulk 300 ft. of riveted seams as designated.
D. Test and prove tight by air pressure or other suitable means.
E. While vessel is on drydock, blast to near white metal bilge strake rivets and rivet seams (a total of 2,000 ft approx. 15" wide) between fwd bulkhead of #1 port and stbd and thru after bulkhead of #12 port and stbd. Coat blasted area with coating supplied by Owner's (matcoate). Coating to be applied under supervision of Owner furnished serviceman.
104. BOTTOM WELDING - 103 DO NOT. START UNTIL_AUTHORIZED BY OWNER'S REPRESENTATIVE
Furnish necessary labor, equipment and material required to complete the following:
A. Chip out and reweld 300' of eroded welds on bottom shell seams and butts.
B. Supply, erect and remove staging on drydock. Stipulate standard width of sec tions.
SHEET NO. 31
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010606
105 PROPELLER - 116 DO NOT START UNTIL AUTHORIZED BY OWNER'S REPRESENTATIVE
Furnish necessary labor, equipment and material required to complete the following:
A. Heat, fair and dress edges of all four (4) propeller blades.
B. Drill stopper holes at ends of all cracks, heat, braze and dress also in way of old repairs. Allow for repair of three (3) cracks.
C. Upon completion of any repairs, polish entire propeller and hub to satisfaction of Owner's Representative.
D. Prior to any paint application, coat wheel lightly with grease in order that paint does not adhere to wheel.
106. DOMESTIC WATER TANKS - 103
Port - 48 Ton Capacity and Stbd
Chip and scale all loose -material from entire internal surface of port fresh water tank. Wooden plugs to be inserted in all suction and discharge connections prior to cleaning to prevent line from being clogged. Remove plugs prior to securing tank. Clean tank and remove all debris from vessel. Apply one (1) spot coat cement wash to all bare areas and one (1) full coat for the entire internal area of both tank. Flush out both tanks with fresh water. Chlorinate tank, fill and dump tank twice. Refill tank and leave tanks ready in all respects for human consumption as per USPHS requirements. Renew all disturbed manhole plate gaskets and replace all defective nuts and studs as required.
107. ITEM - MAIN CONDENSER TO AUX CONDENSER CROSSOVER VALVES - 227
.A. Remove (1) one 20" gate valve to shop and repair and or renew - repack and prove satisfactory and reinstall.
B. Remove (1) one 10" gate valve to shop 'and repair and or renew repack prove satisfactory and reinstall.
108. ITEM - THROTTLE LEAK OFF TO 35// DUMP VALVE -227
Renew existing defective planges 1 1/2" check valve.
109. ITEM - BOILER ATOMIZING STEAM VALVES - TOTAL (8) - 227
Remove these valves to shop. Open, clean, machine, grind in, repack and prove satisfactory.
SHEET NO. 32
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010607
110 ITEM - RECIRCULATING LINES FROM FEED PUMPS TO DEAERATOR -227 2 1/2" VALVE
Location overhead in shaft alley above #3 feed pump. Install (1) one 2 1/2" valve in recirculating line from feed pumps to deaerator so that when the valve is open to distilled tanks and this valve is shut. The recirculating valves and nozzles can be changed on various feed pumps without shutting down plant.
111. ITEM - #3 MAIN FEED POMP SUCTION VALVE PACKING GLAM) - 227 Renew wasted packing gland.
112. ITEM - FEED PUMP SUCTION FROM DEAERATOR 10" valve - 227
Located under deaerator remove valve bonnet clean, lap in, repack, renew gasket and reassemble.
113. ITEM - STEAM TO WHISTLE BY PASS VALVE - 1 1/2" 900# - 227
Remove defective (fermanited) existing valve and replace with owner furnished
spare. ' '
.
.
114. ITEM - FIRE AND BUTTER WORTH 4" SPRING LOADED TURBINE - 227 EXHAUST VALVE
Remove bonnet and determine why valve cannot be opened normally. Presently exhaust pressure has to be built up before valve opens. This condition trips out feed pump. Correct problem and reassemble.
115. ITEM - ffl - #2 - #3 MA-IN FEED PUM 6" EXHAUST VALVES TURBINE- 227
Open, clean, lap in, -repack, make sure these valves operate in half and full open positions, reassemble as original.
116. ITEM - GENERATOR LUBE AND AIR COOLER SALT WATER VALVES -.227 Repair or renew two (2) 3" globe valves from 30it water service.
- 117* ITEM - MAIN CONDENSER TO CROSS OVER LINES - 4" GATE VALVES - 227
Located lower stbd side engine room below floor plates advacent to main reduction gear foundation.
Repair or renew (2) two 4" gate valves.
SHEET NO. 33
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010608
118. ITEM - BOILER SUPERBEATER 1" - 1500# ANGLE WELDED VALVES - TO FUNNEL BELOW FLOOR ELATES - TOTAL (2) two - 315
Renew these defective valves.
119. ITEM - #2 MAINEEED PUMP RECIRCULATING VALVE TO DEAERATOR - 227 Renew flange gasket - previously fermanited.
120. ITEM - 2 AUTOMATIC DUMP VALVES 10 lb. and 30 lb. EXHAUST SYSTEM SO STACK VENT LINES - 227
Remove to shop for over haul and make tight, leaking @ present. Location @ after port side of main operating plat form.
121. ITEM #102 - HIGH PRESS DRAIN LINE VALVE TO DEAEREATOR - 227
Overhaul high pressure drain line valve to deaerator and renew mounting gasket, both flanges size and type valve 3" angle steel 125 lb. class.
122. ITEM - (2) STEAM VALVES TO if3 FEED PUMP - 3" - 1500# - 227
Disconnect, remove to shop, open, clean, machine and grind in seat to disk, repack, shop test. Reassemble as original.
123. ITEM - EXTERNAL DESUPER HEATER AND INLET STOP VALVE TO SAME - 317
Disconnect and remove to shop in let stop valve and external desuper heater and
mixing chamber for examination and repair. Repair or renewal will be determined
after examination by concerned parties.
.
124. ITEM # 1 - -GENERATOR TURBINE RELIEF VALVE - 227
Generator turb.ine relief valve between leslie valve and throttle valve disconnect send to-shop. Repair or renew and reassemble as original and rpove tight.
125. ITEM - VENTILATION DUCT WORK ENGINE ROOM - 236
A. Crop out wasted area with branch off with 90 bend approximately 10 linear feet, fabricate and install new duct work and reinsulate location. Main lower engine room after starboard side at fuel heaters level.
B. Fireroom ventilation duct crop out wasted duct at branch off fabricate and install new duct restore insulation. Location upper fire room fidely port side aft over boiler drum. Approx. (10.) ten ft.
C. Allow for additional 60 ft. of ductwork renewal and reinsulation - approx. 24" X 12".
SHEET NO. 34
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010609
D. Crop away entirely wasted away section of engine room ventilator duct 20"x20"x40" length replace duct insulation padding of fibre glass 2" thick over all. Location operating platform deck main engine room port side at front of lube oil storage tanks.
126. ITEM - -OLD FOAM SYSTEM - SUPUR FLUOUS PIPING - 110
Remove remaining piping for original foam system in lower main engine room, @ motor driven pumps sea suction line, also steam driver fire butterworth pump in shaft alley, also crop to buldhead, and blank off 1 1/2" former foam liquid supply lines bulk head penetration.
127. ITEM - CONTAMINATED DRAIN COOLER - 227
Heater coil returns, cooler (salt water coolant). Remove forward unit to shop
renew tubes, at present thru plugged and remaining tubes in poor condition. Blast
and coat head with rust ban or equal reinstall and mind insulation in every of repairs.
Approx 50 tubes
-.
128. FLOOR PLATE SUPPORTS - BRACING IN CARGO PUMP TURBINE CONTROL AREA - 102
Remove all floor plates from in and around all cargo bullast pump turbines.
Crop back to stank and cofferdam top all deteriorated supports brucing for floor
plates, renew from pump room bulk head to main engine room bilge gunwhale and from
the bulk head of the port wing bunker tank to the starboard bunker tank, with one
correction, reestablish the entire floor plate level at least six inches lower than
@ present. .
'
'
Ninety percent of existing floor plates can be reused. Approx 200 ft 2" x 2" x 1/4" angle iron Approx 80 sq ft - diamond tread floor plate.
129 ITEM - JURGUSON GAUGES IN ENGINE ROOM @ THROTTLE - 227 Renew approx total of defective 80 ft section of 1/2" high pressure tubing.
!30. ITEM - FOAM SYSTEM SALT WATER GAUGE FITTING - 227
Relocate fitting for salt water gauge on recently installed foam system. Present location clogs line with foam.
131. ITEM - VERTICAL - 2nd STAGE FIRE AND BOTTERWORTH HEATER AND TUBE BUNDLE - 232
Disconnect and remove existing defective patched (pressure vessel) heater shell and tube bundle. Take delivery of owner furnished complete new shell and tube bundle and install to place as original. Test and prove satisfactory.
SHEET NO. 35
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010610
132. ITEM - PORT AM) STBD BOILER EXPANSION VOINTS - 313
Port and stbd boilers original expansion joint @ base of each boilers uptake, rumove 10 ft of wasted metal fabricate clean smooth shut metal fit in place of cropped out areas to make a smooth line to exterior of uptake at this point.
133. ITEM - PORT STBD BOILER AIR HEATER TUBES - 308
A. Pressure test air heater tubes, replace or correct any leaking (by deterioration) tubes found upon testing.
B. On starboard boiler expose air heater by pass dampen and fare up operating shaft internally for eliminating difficulty in operating.
Furnish and install updated stock pyrometers and metors, for both boilers, original equipment seriously damaged'and deteriorated during the life of the ship.
134. ITEM - BAILEY FUEL OIL REGULATORS PORT STBS - 315
'
Disconnect and remove to shop. Overhaul reinstall test and prove satisfactory under supervision of dorsic owners account.
135. ITEM - PORT AND STBD BOILER INNER DOOR LUG BOLTS AND NUTS AND (1) ONE DOOR HINGE - 319 A. Renew total of (40) forty studs and nuts on inner doors of both boilers. B. Renew hinge on inner door of stbd boiler (middle).
136. ITEM - AUTOMATION PORT ARP STBD BOILER STEAM TO BURNER 3/8" STRAINERS - 311
Port Boiler - #1 #2 and #4 Burners 'Stb Boiler - #1 #2 #3'#4.Burners Renew total of (7) seven 3/8" check valves on steam to burner lines, parts on board.
137. ITEM - PORT AND STBD BOILER AIR REGISTERS - TOTAL OF (8) eight - 318
Disconnect send to shop blast and coat, renew parts as found necessary, parts on board, return and reinstall as original.
138. ITEM - STBD BOILER MAIN STEAM STOP VALVE - 315
Renew hand wheel timkin bearing.
139. ITEM - STACK PYROMETERS - 312
Furnish and install stack pyrometers for both boilers original equipment damaged and
and wasted.
SHEET NO. 36
- EXXON GETTYSBURGH
MAY 1978
EXX-MOR-010611
40. ITEM - CARGO SYSTEM PUMP RELIEF VALVES - USCG - 405
Remove the following valves to shop - open clean, overhaul and test and prove tight and set pressure, reassemble to place.
A. (4) Main cargo pump relief valves - AFT pump room B. (1) Ballast, pump relief valve - AFT pump room C. (2) Stripper pump relief valves - AFT pump room D. (3) Cargo pump relief valves - FWD pump room E. (1) Cargo deep well pump - main deck portside
-
.41. ITEM - AFT PUMP ROOM' 16" GATE VALVE BULKHEAD " 405 On "B" Line. Renew existing defective valve newspare valve on order.
142. ITEM - #8 CARGO TANK HEATING COIL 3" - 300# GLOBE - 405 Valve to manifold. 'Repair or renew valve, test and prove-''satisfactory.
L43. ITEM - 12" GATE BLOCK VALVE SUCTION SIDE BALLAST PUMP AFT PUMP ROOM - 405
Disconnect send to shop open, clean machine grinding, repack and shop test and prove tight and reassemble as original.
144. ITEM - FWD PUMPROOM VALVES - 405
Renew six (6) four (4") inch valves and/or remove existing four (4") inch valves to shop repair - sand blast and coat with R.B. #191 and reinstall.
One (1) valve to Port Cofferdam One (1) valve to Starboard Cofferdam One (1) valve to Dry Cargo Space Two (2) valve to Forepeak One (1) valve from bulge suction line to Manifold.
145. ITEM - AFT PUMP ROOM STBD STRIPPER PUMP SUCTION AND DISCH VALVES - 405
Disconnect, send to shop, open, clean, machines, grinding, repack and shop test and prove tight and reassemble as original.
(1) one 10" gate (1) one 6" gate
.
SHEET NO. 37 - EXXON GETTYSBURG
MAY 1978
EXX-MOR-010612
146. ITEM - CARGO TANK VALVES "-405
Disconnect and send following valves to shop. Open, clean, machine, grinding, repack. Shop test and prove tight and reassemble to palce as original or renew.
A. #3 center #2 center hisuction in #3 center 16" gate B. #6 stbd 8" gate stripper valve C. #6 stbd 12" gate main suction valve
147. ITEM - DECK WINCH VALVES - 117
Remove and replace with owner furnished spare valves six (6) designated 5" flanged exhaust valves and three (3) designated 3" 300# flanged globe steam valves.
148. ITEM - CARGO HEATING SYSTEM VALVES - 405
- A. Cargo heating steam supply line to #7 .main cargo tanks and return line. Furnish and install 3 inch globe valve on steam supply from deck steam line, crop back existing line install flunger locate or position valve as close to deck steam line as possible. Valve is to be of 300 lb. class. Furnish and install 2 inch globe valve on return line from #7 MCT heating coils, again locate as close to main return line as possible. Valve is to be of 125 or 150 lb. class.
B. Furnish and install 2 inch globe valve on heating coil returns line from #8MCT to be located as close as possible to return line. Valve is to be of 125 or 150 lb. class.
149. ITEM - (4) FOUR 16" ANGLE GLOBE SUCTION VALUES TO A.B.C AND D MAIN CARGO PUMPS IN LOWER AFT PUMP ROOM.- 405
Remove bonnets of valves, install grease fittings @ packing glands and at yoke bushings. Grind and lap in seats to disks repack and reassemble and prove tight. This item to be done in-place.
150. ITEM - AFTER STBD FORCED DRAFT FAN - 316 '
Located AFT boat back forced darft fan room disconnect and remove fan inpeller to shop, heat and pair blading. Dynamically balance, renew bearings, test in place under load and prove satisfactory.
151. ITEM - LOW PRESSURE EVAPORATOR OPERATING PLATFORM LEVEL - 219
Renew mesh separators in 1st and 2nd effects,parts on order.
SHEET NO. 38
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010613
.52.. ITEM - PORT AND STBD AFT AND PORT FWD AIR CONDITION EVAPORATOR COILS IN AIR CONDITION
FAN ROOMS - 702
.
Disconnect and remove existing wasted coils. Fabricate and install new drip pans (3). Take delivery of new owner furnished coils and install to palce. .Recharge system, test for leaks and prove tight test systems in operation and prove satis factory.
L53. ITEM - FORCED DRAFT FAN CONTROLLER BOXES - 806
Fire room ports side FWD buldhead open, clean, spot in magnetic core faces, dress contacts, check all connections and prove satisfactory.
154* ITEM - ENGINE ROOM AM) SHAFT ALLEY TANK TOPS AMD PUMP SUPPORTS - 102
Clean areas where bitumastic was formerly applied and replace these areas with new application of bitumastic coating. Approx 50% of tank top areas; involved. 155. ITEM - 1" PIPE FROM 30// STEAM LINE TO GENERATOR SEAL STEAM LINE - 227
Renew 1" pipe union and nipple from 30 lb steam to generator seal steam line. Lower engine room stbd side.
156. ITEM - 6" DIAM LUBE OIL OVERFLOW LINE FROM LUBE OIL GRAVITY TANKS TO MAIN LUBE OIL SUMP - 227
Located lower engine room portside near lube oil purifiers - 12 ft suction with multiple off sets remove section, crop and renew wasted section where pipe has been chafed from contact with a 16" salt water line. Alter pipe contour to prevent further contact with other pipe. Reassemble and prove satisfactory.
157. ITEM - DRAIN LINE 2" DIAM APPROX 10 FT STBD - 227 Side of machine shop. Renew flanged section with (1) one bend and prove tight.
i58. ITEM - TANK TOP IN MAIN CARGO PUMP TURBINS AREA HOLE IN TANK TOP UNDER BALLAST PUMP TURBINE - 102
Furnish and install a 12" x 12" x 3/8" doubler.
SHEET NO. 39
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010614
159. SANITARY PUMP f 1 and #2 FOUNDATION - 102
#1 and #2 sanitary pumps after lower engine room. Fabricate, and install new support
base for pump and motor. Base in use is badly wasted away. Sketch and dimensions
are attached. Blasting coat with RB 191.
- '-------
jL__ ZiS gCfdjc.n--
\ cf chftnovvX
i-- /,Jii__lc
h' ?/" .<
I TfrZ. ^'fl-(Wmcs4V_i5ao Pimp.-
SHEET NO. 40
EXXON GETTYSBURG
HAY 1978
EXX-MOR-010615
L60. FIRE-AND BUTTERWORTH PUMP PEDESTAL - 212
Disconnect and remove pump from place and set to one side. Crop off wasted support plate for pump foundation. Using the cropped section as a sample, fabricate a new pump foundation.
Material required - (approx, sizes) (1) one 32" x 28" x 1/2" plate foundation support (1) one 24" x 28" x 1/2" plate fitted with a 3" rolled lip on each edge of
28" width and welded to the afore mentioned foundation plate. (2) two 3" x 8" x 1/4" channel iron pump supports 16" long, welded to top flat
of rolled edge plate drilled to receive hold down bolts and alignment chocks for pump pedestal feet. (2) two 13" x 8" x 3/8" radiused closing plates to be welded to ends of 3" x 8" channels. Plates to have proper swipe holes to prevent water reten tion inside pump foundation. Prior to reassembly, all new material to be sandblasted and coated with Rust ban #191. All new work to be fully welded and fitted in true align ment with existing turbine drive support plate on foundation. Reassemble fit necessary chocks. Renew all disturbed nuts, bolts and gaskets. Align pump to turbine drive. Pack coupling with owner furnished grease. On completion, test and prove satisfactory.
161. ITEM - PLUGGED HOLE IN DECK #5 center cargo tank formally steam smothering supply - iq2 Weld plug to place - 1 1/2"
3.62. ITEM - STEAMLINE TO FIXED BUTTERWORTH MACHINE - 121
Pipe 2" diam x approx 20 ft - shaped to #6 port tank crop and renew existing defective pipe.
163. ITEM - HEATING COILS TO CARGO TANKS ON DECK - 409
(Heating coils - cargo) Renew from manifold to deck penetration steam and return line size 1 1/4" and 1", approximately one hundred running feet, with multiple offsets and bends. As directed also approx 20 twenty five pipe brackets.
3-64. ITEM - DOMESTIC WATER LINE TO MIDSHIP HOUSE - 131
Blank off existing wasted 1" diam line - in multi gang insulated pipe run @both ends. Run separate new 1" pipeline from AFT pump room to midship house and connect up original - insulate line and prove tight. Approx 250" of 1" galuarized pipe, flanged and screwed couplings with (1) capped nipple branch off for shore connection approx so pipe hangers.
SHEET NO. 41
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010616
165. ITEM - DECK STEAM LINE THRU UPPER FWD PUMP ROOM AFT AND FWD BULKHEADS - 131 Crop and renew deck steam line bulkhead penetrations.
166. ITEM - BTJLDHEAD CABLE RUN PENETRATION - 102
-
After bulkhead of FWD pump room crop and renew bulkhead penetration doubler
167 ITEM - AIR TO DECK PIPE LINE - 131
Item - A - 1 1/2" x approx 10 ft section air to deck pipe line - shaped and welded pipe. Renew same in upper FWD pump room
B - Renew approx 100 ft of 1 1/2" air to deck pipe line on FWD deck between midship house and focsle head
168. ITEM - DECK STEAM LINE PENETRATION - FWD PIMP ROOM AFT BULKHEAD ABOVE MAIN DECK TO PORT PUMP ROOM VENT BLOWER - 102
Renew bulk head penetration.
169. ITEM - STBD STRIPPER PUMP DISCHARGE LINE AFT PUMP ROOM PIPING - 407
Remove existing 8" diam" flanged tee dresser one leg fabricate new section, elimin ating dresser and substituting glanges approx 8 ft. Also renew existing wasted 8" flanged elbow connected to "tee" and stripped pump discharge outlet. Also renew additional 8" flanged "tee" in same line - approx 8 ft long.
170. ITEM - HEATING COIL RETURN LINE - 407
AFT of mid ship pump man locker. Renew gasket on 3" diam heating coil lines
flange.
'
SHEET NO. 42
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010617
171. ITEM - 8" FIRE LINE EXPANSION JOINT - 131 Just AFT of mid ship house. Renew 8" expansion joint on order.
172. ITEM - STEAM TO MIDSHIP HOUSE EXPANSION JOINT - 131
'
Adjacent to deep well pump. Remove expansion joint. Renew packing gland bolts and studs. Repack and reassemble and prove tight.
173. ITEM - HEATING COIL MANIFOLD TO #8 CARGO TANKS - 409
Renew wasted 3" diarn manifold with (4) four flanged spuds and (1) one 3/4" drainspud.
174. ITEM - HEATING COIL PIPE DECK PENETRATIONS - 409
#8 Port, #8 center and #8 stbd. Crop existing defective penetrations total of (8) eight steam and return. Furnish and weld to deck penetration new extra heavy nipples with threader 90 elbows and reconnect heating coil lines to same.
175. ITEM - PORT VERTICAL DUPLEX CARGO PUMP FWD PORT SIDE FWD PUMP ROOM STRAINER BOX - 401 Build up (4) four wasted stud holes by welding retap and renew studs and bolts.
176. ITEM - AFT PUMP ROOM PORT STRIPPER PUMP SECTION OF 8" pipe - RETURN TO SUCTION FROM RELIEF VALVE _ 407
Renew approx 8 ft section - flangen - prove tight.
I
SHEET NO. 43
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010618
177. ITEM - 8" STRIPPER LINE BULKHEAD PENETRATION BETWEEN #4 CENTER AND #4 STBD CARGO
TANKS WASTED SECTION APPROX 1 FT LONG - 407
'
Renew wasted section of pipe. .
178. ITEM - 8" STRIPPER LINE APPROX 5 FT LONG #3 PORTCARGO TANK _ 407 Renew wasted section where it goes thru striffiner. Has boiler plug in same.
179. ITEM - SOIL LINE PIPING - 131
A. Allow for renewal of approx 100 ft of 4" soil line piping various designated
sections.
"
B. Allow for renewal of approx 10 ft of 2" soil line piping various designated . sections.
180. ITEM - #11 WINCH 5" STEAM EXHAUST LINE PIPE - 117
'' ' . '
Renew plange and dresser on #11 winch steam exhaust line (5"); present flange
worn to where bolts show through flange.
'
181. ITEM - CARGO TANK VENT LINE PIPE - 408
' ' ..
A. #4 center tank access trunk and #4 stbd tank access trunk
Renew 6" diameter pipe spool piece 4" length welded to access hatch at one
end desser coupling at other.
'
SHEET NO. 44
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010619
B. Cargo tank vent line .<? #2 port deep tank access trunk. Crop out and renew 6" diameter 3 1/2" lenght spool piece of vent line one end welded to. tank access hatch other end fitted to dresser coupling.
't
Z>CK
/ '1 n .
& /. FtfC ^ .
CouyOj-i^ Ii -
!
182. ITEM - #2 CENTER CARGO'TANK STRIPPER LINE Bell mouth - furnish and weld to place on longitodihal (1) one pipe hanger.
i83. ITEM - #4 STARBOARD TANK - STRIPPER LINE PIPE - 407
Crop off existing tihree <3) inchlast gallon stripper line and renew with coated pipe. Approximately twelve. .(12) feet of piping - fabricated. Present piping red handed. Furnish and install two pipe hangers.
1.84. ITEM - #7 CENTER CARGO' TANK 8" STRIPPERLINE PIPE - 407
.
Renewal approx'25' of prefabricated 8" stripper line in 7ct cargo tank.
Presently hoses in this-line at after bulkhead and forward of port stripper master volue (buld head penetration weld leak).
SHEET NO. 45 ` EXXON GETTYSBURG
MAY 1978
EXX-MOR-010620
185. ITEM - SOLVENT'PUMP SUCTION LINE SPUD PIPE - FWD PUMP ROOM - 407
Solvent pump suction line in bilge of foreward pump room has a spud which leads to a drain valve. This'spud is leaking at its weld to the suction line. Spud is 2" pipe. Reweld or replace' this spud and prove tight with a pressure-test.
!86. ITEM - "C" LINE MIDSHIP RISER MANIFOLD - 116" FROM "E" RISER- 407
Crop out dresser coupling in line. Furnish and weld to place 16" pipe section
to replace existing dresser.
'
187. CARGO PIPE RENEWAL - 407
Renew, test and prove tight the following main deck cargo piping. All new pipe and fittings to be sand blasted and coated with Rust Ban #191 internally and externally. Schedule 40 steel pipe is to be used. Renew all gaskets and use cadmium plated nuts and 'bolts. Wirebrush and recoat with Rust Ban #191 all welds made after pipes are coated.. All wasted hangers and collars are to be renewed and coated with Rust Ban .#191.
(1) "A" line drop; One (1) 16" - 90 elbow approximately 5*-6" long, flanged on one end and deck penetration on other; with one 2 1/2" wash-out spud and valve, and one 2 1/2" drain line spud.
(2) "B".line drop; One (1) 16" - 90 elbow approximately 5'-6" long, flauged on one end and deck penatration on other; with one 2 1/2" wash-out spud and- valve, and one -2 1/2" drain line spud.
(3) ~"C" line drop; One (1) 16" - 90 elbow approximately 6'-6" long, flauged, on one end and deck penatration on other; with one 2 1/2" wash-out spud and valve, and one 2 1/2" drain line spud.
(4) "D" line drop; One (1) 16" - 90 elbow approximately 5'-6" long, flauged on one end and deck penatration on other; with one 2 1/2" wash-out spud and valve.
(5) "C" line drop; One (1) 8" - 90 elbow approximately 2'-0" long, flanged on one end and deck penatration on other.
SHEET NO. 46
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010621
(6) "7C" stbd stripper line drop; One (1) 8" - 90 elbow approximately 3'-6" long, flanged on one end and deck penatration on the other; with 2 1/2" drain spud.
(7) "7C" port stripper line drop; One (1) 8" - 90 elbow approximately 3'--6" long, flanged on one end and deck penatration on the other-.
(8) Stbd side discharge manifold - "A" line; One (1) - 16" straight section approximately 11'-8" long, flanged on one end and weld on
the other, with one spud.
(9) stbd side discharge manifold - "B" line; One (1) ~ 16" straight section approximately 10'-0" long, flanged on one end and weld on the other.
(10) Stbd side discharge manifold - "C" line; One (1) - 16" straight
section approximately 9'-8" long, flanged on one end and weld on
the other.
- ''
IT
-
(11) Stbd side discharge manifold - "U" line; One (1) - 165' straight
section approximately 11' - 8" long, flanged on one end and weld
on the other.
(12) Stbd side discharge manifold - stbd stripper line; One (1) - 8" straight section approximately 13'-8" long, flanged each end, with one (1) - 5" shaped offset spud approximately 3'-4" long, flanged on one end and weld on other.
L88. ITEM - #5 PORT CARGO TAM 8" STRIPPER LINE PIPE - 407
Renew 10 ft section of 8" pipe - straight bulkhead penetration - (2) two dresser couplings.
189. ITEM - AFT PUMP ROOM "C" MAIN CARGO PUMP 16" DISCHARGE LINE PIPE - 407 Renew wasted section. 14 ft long flangen both ends.
190. ITEM - AFT PUMP ROOM 16" CROSS OVER LINE PIPE BETWEEN "B" AND "C" MAIN CARGO PUMPS - 407 20 ft long - 4 flanges - 1 dresser
191. ITEM - AFT PUMP ROOM "D" MAIN CARGO PUMP DISCHARGE LINE PIPE - 407 Renew section 14 ft long - 16" - 3 flanges
192. ITEM - AFT PUMP ROOM - BALLAST PUMP SUCTION LINE PIPE - 407 Renew 12" diam section approx 12 ft long - 3 flanges.
SHEET NO. 47
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010622
193. ITEM - EDUCTOR - FWD HJKP ROOM - PIPE - 131
A. Renew 4" diam s approx 10ft section of suction line to eductor - flanged with (3) three bends. .
B. Water supply line to eductor - renew 3" diam x approx 8ft section - flanged (2) two bends.
194. ITEM - FWD PUMP ROOM BILGE SUCTION PIPE - 131
,
Renew 3" diam x approx 20ft section - flanged - (4) four bends - located on AFT bulkhead.
3-95. ITEM - FEW PUMP ROOM - FUSB OUT LINE TO SOLVENT SYSTEM - PIPE - 131
Renew 2 1/2" diam x approx 8ft section. Flanged one end, welded other end - stbd
: side aft in pump room.
-
.
196. ITEM - DECK EXHAUST 8" LINE BULKHEAD PENETRATION - 117 AFT pump room pipe tunnel, 6ft long section crop and renew.
197. ITEM - DECK EXHAUST LINE EXPANSION JOINT ALONG SIDE CAT WALK - FWD OF MIDSHIP HOUSE - 117
Furnish and .renew expansion joint pedistal and two (2) pipe brackets 5" line.
198. ITEM - UNIVERSAL MOORING CHOCKS - 129
"Wash off deck total of (4) four designated irrepairable universal mooring chocks. Furnish and install to place (4) four new Pallister mooring chocks to place as original and prove satisfactory.
SHEET NO. 48
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010623
199. ITEM - OUTER STACK VENT LOUVERS - 102
Cropout and renew existing frame and louvers port and stbd sides approx - overall 4ft x 5ft each.
200. ITEM - SKYLIGHT DECK (4) ENGINE VENT AND COMPARTMENT FIRE DAMPERS- 102
Crop out wasted guide racks and operating levers fabricate new ones and install as original.
201 * ITEM - CAPTAINS BEDROOM DECKHEAD SALT WATER LEAK LEAK APPEARS TO BE COMMING FROM WHEEL HOUSE WINDOWS - 102
Remove necessary paneling - locate leak and correct fault. Replace paneling.
-202. ITEM - AFT PUMP ROOM VENT FAN REMOVAL - USCG - 835 LOCATED STBD SIDE OVER "B"
' MAIN CARGO PUMP - 236
'
Main pumproom booster fan, foundation, all pertinent piping to be removed. Install vent opening in way of casing removal, for continued air supply from king post gooseneck ventilator.
Also remove unused pipe as indicated by ch/engr to shore (already disconnected) Brace up remainder of duct work as needed after removals are made, prime and paint all surfaces, remove all debris from vessel.
23. ITEM - FOCSLEHEAD FWD P AND S ANCHOR CLAWS - 113
Weld 3/4" round steel handle to each claw to facilitiate placing same in position for safety in handling.
204. ITEM - CARGO TANK ACCESS TRUNK VILLAGE OPENINGS - 102
Crop and renew a total of (10) large 10" openings and (10) - 6" openings - reuse hinges and covers furnish and install new gasket material and prove tight.
SHEET NO. 49
EXXON .GETTYSBURG
MAY 1978
EXX-MOR-010624
205. ITEM - WINCH FAIR LEADS - 102
A. #1, #2, #3 and #4 - Wash off deck - send to shop. Renew "A" frame angle iron foundations, blast and coat and free up drums and reweld to place as original. Prove satisfactory.
B. Total of (4) winch fair leads opposit #7 and #8 winches free up drums and prove satisfactory.
206. ITEM - PLATFORM STBD FWD END ANCHOR WIND LASSON FOCSLE HEAD - 102 Reweld broken hand rail.
207. ITEM - ACCESS COVER TO STOPS DRY CARGO STORAGE AREA BOAT DECK AFT - 102
Disconnect cover remove to shop - approx 5ft x 5ft x 1/4" - Reuse hard ware and
balance weight and renew cover and furnish and install gasket material and prove
tight.
'' .
'
208. ITEM - STACK DECK DRAIN COLLECTION TANK 2-1/2" 25" GOOSE NECK VENT - 227
Crop at deck - fabricate new vent and weld to place as original.
209. ITEM - AFT PUMP ROOM OVER HEAD PIPE TUNNEL - 102 "Vee" out and reweld (2) two cracks in tunnel as directed.
210. ITEM - AFT PUMP ROOM SKYLIGHT COVERS (2) TWO - 102
Remove covers to shop - blast and coat and renew 1 1/2" cover lips around covers. Covers approx 41 x 51 .
211. ITEM - STACK DECK - 102
Furnish total of <6) six - 12" x 12" x 3/8"'steel doubleas and weld to place @ designated areas of stack deck.
SHEET NO. 50
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010625
212. ITEM - BOAT DECK'AFT - 102 Furnish and weld to place total of (5) five 12" x 12" x 3/8" doublers as directed.
213 ITEM - BOAT DECK GALLEY SKY LIGHT - 102
Unbolt and remove to shop. A. Blast and coat and renew wasted sections as required and replace as
original with new' gaskets.
B. Remove from place and replace with flat plate gasketed cover approx
20ft x 5ft x 1/4"
.
214 ` ITEM - CARGO GAIRE S .W. AIR COOLER - 414
A. Located dry cargo space - stbd side under focsle head renew leaking and
patched brazed fittings -use extra.heavy brass.
-
B. Renew drum rollers, motor belt and reduction gears - parts on order.
215 ITEM - WINCH STEAM AM) EXHAUST PIPING - 117
A. Crop and renew total of (3) three 3" flanged deck penetrations 300# pressure. (5) five designated 5" flanged deck penetrations.
B.' Repair (2) two pinhole leaks in 5" flanged exhausts pool copper nickle. @
#11 poop deck winch.
216. ITEM - CARGO CAIRE 3" EXPANSION JOINT - 414
Foward -deck AFT of focsle bead. Disconnect existing defective joint and replace with owner furnished spare expansion joint and prove tight.
217. ITEM - FORE AMD AFT CAT WALK - 102
A. Needle gun cat walk a frames between AFT end of midship house and AFT pimp room and coat with RB' - 191.
B. Prove all catwalk sliding feet free.
C. Allow for renewal of total of (30) thirty thwartship 2" x 2" x 1/4" x 36" long angle iron supports.
D. Allow for renewal of approx 200 ft of 6" x 6" x 3/8" cat walk side member angle iron.
SHEET NO. 51
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010626
E. Allow for renewal of total of 40 various size additional pipe hangers under cat walk. ' . .
F. Allow for croping and renewal of (20) twenty nA frame" triangular pipe run
support brackets each approx 30" x 14" x 3/8".
--
218. ITEM - ANCHOR WINDLASS ENGAGING BLOCKS - 113
Disconnect total of (4) four from port stbd sides of anchor windlass - (too much lost motion) build up blocks and remachine to nominal clearance and reinstall as original and prove satisfactory.
219 ITEM - STACK :DECK RUDDER ANGLE INDICATOR - 601 Renew cracked glass approx. 10" x 1/4".
220. ITEM - POOP DECK FLUSH MOUNTED SCUTTLE TO LAZARET - 102
Crop existing wasted, defective scuttle furnish new scuttle. Weld to place as original and prove .tight. .
221. ITEM - MAIN ANTENNA HOUSING OVER PADIO ROOM -605
Crop off main antenna'housing. Remove two (2) antenna insulators - crop out old pedestal and renew with coated material. Prove new pedestal is water tight prior to reinstalling antenna -housing. Insulators to be replaced with new gaskets and canmium plated bolts and'nuts. All work to be proved in good order.
222. 'ITEM - SHIP RADIO- ANTENNA - STACK DECK - 604
Install two (2) two arid one half (2 1/2) inch extra heavy galvanized piping each piece approximately seven (7) foot long with two (2) inch padeye at upper end. Top section to be' capped.
Install-in line of king posts at after corner of stack deck. One (1) port side and one (1) starboard side r- to support ship radio antenna.
223. KING POSTS AFTER BOAT DECK LEVEL - 102
Crop off and remove from vessel two (2) king posts - at deck level. Remove all stays padeyes and grind smoth all work and prime coat.
SHEET NO. 52
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010627
224. item _ DIESEL TANK DECK - AFT - 102
Furnish and weld to place total of (3) three 12" x 12" x 3/8" doublers over presently patched holes in deck.
225. ITEM - DECK STORES LOCKER DECK - BOAT DECK AFT - 102
Deck in Deck stores locker on the boat deck AFT has several holes. Weld in doubler plate approximately 4' x 5' x 1/4" steel. Coat with RB 191.
226. ITEM - FOCSLE HEAD RUNNING LITES - ARMOURED CABLE - 809
Disconnect existing defective cable. Furnish and install approx 75ft of new cable and junction box to port and stbd running lite outlets, and furnish and install approx (6) six dozen cable chips.
227. ITEM - FWD PUMP ROOM OVERHEAD LIGHT CABLE - 809
Renew total of (20) twenty wasted cable chips.
228 * ITEM - EMERGENCY SHUT DOWN SWITCH FOR MAIN CARGO PUMPS - 806
Rebuild 1/4" steel box for emergency switch @ after bulkhead of midship's house main deck port side, box @ 18" x 12" and 6" deep, rebuild interior controls replacing worn parts as needed.
Furnish and install new emergency shut down switch for main cargo pumps @ FWD bulkhead of focsle head ART bulkhead (? end of catwalk. Install controls to pumps, uncase in 18" x 12" x 6" deep 1/4" steel box test both emergency cargo shut down switches to satisfaction of chief mate and chief engineer that switches are in good working order.
229. ITEM - SPEARY GYRO AND AC GENERATOR MARK 14 - MODEL 2 - 602
General overhaul and cleaning to be done by sperry service man owners account.
SHEET NO. 53
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010628
230. ITEM - WATER TIGHT DOORS FWD AMD AFTER HOUSES - 120
Renew pad eyes and hooks on 20 (twenty). Water tight doors on FWD after houses.
These hooks and pad eyes are to keep door in open position and prevent it from
swinging; these should be sandblasted and coated.
-_
231. ITEM - MIDSHIP RISER MANIFOLD 3" x 3" x 3/8" - EACH APPROX 4ft LONG - ANGLE IRON BRACKETS
Crop and renew defective wasted and bent brackets total of (8) eight. (4) four on each side.
232. ITEM - MIDSHIP CATWALK SUPPORT BEAM @ FWD END OF PUMP ROOM
Crop out wasted beam and two (2) support pillars. Replace beam with 3/8" x 4" x 6' 3" angle iron to be butt welded to pump room each end. 3" diameter pipe pillar support 20" long (2 supports) to be welded to top ofr>pump room and new beam.
Midship catwalk @ pump Toom, under side. Renew all bridge control and electrical conduit support hangers to new support beam.
233. ITEM - CO2 CONTROL SYSTEM @ MIDSHIP CATWALK - 102
Straighten or replace protective guard conduit for co2 control cables, 40ft and 2 90 turns. Renew and fasten 14, 1" x ;/4" x 18" steel support securing brackets for above conduit. Test to satisfaction of chief mate and chief engineer that all controls are in good working order.
234. ITEM - #1 FIRE STATION UNDER FOCSLE - 102
Remove existing box and replace with 1/8" sheet metal box of dimentions 32" x 48" and fitted with a hose retention bar box to be welded to bulkhead.
235. ITEM - #1 MOORING WINCH FOCSLEHEAD STBP -114 A. Weld bracket for clutch lever fulcrum pins. B. Cut hole in gear guard - 3" diarn so gears can be greased. C. #4 winch renew (1) one fulcrum pin bracket.
SHHET NO. 54
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010629
236. HEM - CARGO BOOM WINCH - 114 Braze hole In "boom winch copper nickle exhaust pipeline and prove tight.
237. ITEM - WINCH BED FOUNDATION COAMINGS #4, #7, #8, #9 and #12 - 102
'
Crop and renew wasted sections 3" x 1/4" flat bar total of approx 80ft.
238. ITEM - #3 MOORING WINCH FWD GUARD - 114
Furnish and weld to place (1) one 18" x 6" x 1/4" support.
239. ITEM - NAVAGATION LIGHTS PORTS AND STBD BRIDGE WINGS - 810
Renew present side lights due to complete deteriation of casing making it unable . to renew bulbs and lenses. .
Replace with Terkins Marine Lamp sidelight red 1164-RB, sidelight green -1164-GB
240. ITEM - NAVAGATION LIGHTS - MASTHEAD - RANGE AND STERN - 810
Renew so that lights contorm to regulations; presently deteriated as to need
constant attention to meet regulations; also to enable easy changing of power
bulb.
Renew with Perkins Marine Lamp 1165-B (Range and Mast) Renew with Perkins Marine Lamp 1166-B (Stern)
241. ITEM - REACH RODS - 413
Reach rods in following tanks require freeing up partial renewal of wasted sections
of reach rods* renewal of various sleeves, bushings and hangers. Some staging
required. Also some renewal of for assembly @ valves.
Fore Peak Tank
#1 center cargo tank
#5 center cargo tank
//3 center cargo tank
#6 port cargo tank
#4 center cargo tank
#6 stbd cargo tank
#4 stbd cargo tank
#7 center cargo tank
#5 port cargo tank
#8 port cargo tank
#9 center cargo tank
#10 center cargo tank
Allow for renewal of 20 reach rod forks 100 - lignum vita bushings
100 - sleeves 200 - ft of 1-1/4" reach rod.
SHEET NO. 55
EXXON GETTYSBURG
MAY 1978
EXX-MOR-010630
242. ITEM - CARGO TANK EXPANSION TRUNK GASKET - 102
SEATING RIM- SURFACES
'
Build up wasted areas and grind smooth to original configuration and prove water
tight.
. -;
243. AFT WINDLASS/MOORING WINCH - AMERICAN ENGINEERING - HOLD UNTIL AUTHORIZED - 107
Open cylinders and valve chests of aft windlass/mooring winch for examination and ABS survey, Remove pistons and rods, reassemble, rejoint, repack and close up cylinders in good order. Open up control valve, remove valve and rod, renew worn valve rod, reassemble, rejoint, repack and close up control valve in good order. Free up, renew worn bushings and pins in operating gear. Renew all de fective and broken studs, bolts and nuts.
Open crosshead bearings, guides, crank pin bearings, and shaft bearings, also eccentric straps. Recut oil grooves, scrape, fit and adjust to proper running clearances bearings and eccentric .straps. Open main shaft,-, intermediate and pinion shaft bearings for examinations, refit and adjust to proper running clear-, ances. Close bearings .in good order.
Disconnect, make necessary removals, remove and renew brake lining. Chip, wire brush, apply two (2) coats of primer to bank landing. Scale and clean brake drum. Free up all linkage- and .pins, renew all defective, worn or bent pins using stain less steel material. Renew grease fittings. Reassemble. Test out windlass under load and prove all bearings and brakes in good working order.
244. ITEM - SKYLIGHT OVER AFT. PUMP ROOM - 102
Disconect (4) four approx 3' x 4' steel skylight covers and send to shop - wash
off and renew all ,1 1/2" cover lips, wash off and renew wasted channel landings,
furnish and install new gasket material blast and RB - 191 coat and replace as
original.
245. ITEM - HAND RAILS AND LADDERS - 128
.
'
A. Hand rail cable,allow for renewal of 150 ft of 1/2" diam cable 20 clamps
30 pad eyes.
..
B. Allow for renewal of 150 ft of 1 1/4" top rail and 150 ft of 1" mid rail.
C. Allow for heating and fairing total of 60 ft of hand rail and (10) ten rail
stanchions. .
D. FWD pump room allow.for renewal of 120 ft of 1" hand rail.
E. Reweld broken hand rail #2 stbd cargo tank near top.
F. Reweld broken hand rail #8 port cargo tank at lower platform.
SHEET NO. 56
EXXON GETTYSBURG
.
MAY 1978
EXX-MOR-010631
5. ITEM - ENGINE ROOM LADDER BETWEEN TOP & SECOND LANDING - 102 Crop and renew four (4) wasted ladder steps. Vessel to furnish new steps.
7. ITEM - BOAT DECK TO DIESEL TANK DECK TO STACK DECK LADDERS - 102
Crop existing wasted ladder steps total of four (4). Eabricate new steps approximately 24" x 6" x 1/A". Rolled lip, weld top half as original.
8. ITEM - HAND RAILS & LADDERS - 128
A. Ladder Platform.- Main Deck - Just aft of midship house. Crop and renew wasted frame and supports of platform 62" x 45" 3" x 3" x 3/8" angle iron Four (4) 3" x 3" x 3/8" angle iron legs - each 20" high.
B. #2 Port Cargo Tank.- Crop and renew entire ladder handrails (wasted) 3/4" approx. 40 ft. .each'side and crop and renew total of ten (10) (wated) Diamond tread ladder steps, each'approx 6" x 14" x 1/4" with rolled lip.
_
C. (/I Stbd. cargo tank - 1st platform.landing from top. Renew (wasted) plat form Diamond tread approx. 5 ft x 3 ft x 1/4" staging required.
D. #2 Center Cargo Tank - Crop and renew entire lower ladder, handrails and brackets. 3/4".rails. Diamond tread steps - approx, length 25 ft. staging required.
E. #6 Stbd. Cargo Tank - Crop and renew entire ladder, handrails, securing brackets, approx, length 50 ft. Rails 3/4" and renew both ladder platforms each Diamond tread. Approximately 4 ft x 4 ft x 1/4". Staging required.
F. Ladder Top Platform by #6C Tank - Maindeck - Crop out wasted top ladder plat form from catwalk aft of midship house to stbd. main dec. Approximately 26" x 21" x 1/4" diamond tread plate. Fabricate new, blast and ^191 coat, and weld to place as original.
G. #3 Center Cargo Tank - Renew various ladder brackets and bolts and weld middle platform-to bulkhead where present weld is cracked.
H. it4 Center Cargo Tank - Crop and renew upper ladder. Handrails 3/4" brackets Ladder steps Diamond tread. Staging required. Length approx. 20 ft.
I. #5 Center Cargo Tank -'Crop and renew entire ladder, handrails 3/4". Length approx. 50 ft. and brackets. Staging required.
J. #5 Stbd. Cargo Tank - Crop and renew lower ladder handrails, brackets. Diamond Tread steps. Approx, length 25 ft. Staging required.
K. #10 Center Cargo Tank - Reweld broken hand rail @ lower platform.
SHEET NO. 57
EXXON GETTYSBURG
MAY, 1978
249. ITEM - PORT & STARBOARD BOILER SOOT BLOWERS - 305
Remove (3) three soot blowers in way of generating tubes from each boiler. Total
of six (6) for examination. Any required repairs to be covered in addendum to
this item. Replace as original and prove satisfactory.
__
250. ITEM - MAIN STEAM STOP VALVE 8" - TO H.P. TURBINE - 227
Engine room upper level. Remove to shop. Open, machine, grind in, repack. Shop test and prove tight and reassemble as original. Repair or replace disturbed insulation.
251. ITEM - STEAM PIPE INSULATION - 5" & 6" PIPE - 241
Located after pump room.
.
A. Renew approximately 100 feet of wasted insulation on 5" steam line. B. Renew approximately 100 feet of wasted insulation on 6" steam line., 252. ITEM - STARBOARD STRIPPER LINE #10 CENTER CARGO TANK - 407
Renew wasted section of 8" pipe, approximately 20 feet long with two (2) bends. Dresser coupling both ends.
253. ITEM - MUSHROOM VENTILATORS - STACK DECK - 236
Furnish and install approximately total of 20 square feet of sheet metal doublers over areas of designated mushrooms.
254. ITEM-POOP DECK BULKHEAD - PORT SIDE - BETWEEN GALLEY DOOR AMD DOOR TO COMPANION WAY - 102
Crop existing wasted bulkhead 1-1/2" pipe braces furnish new pipe approx, total of 10 feet and weld to place as original.
255. RECOAT IMG OF #3 CENTER TANKS AND #4 WING TANKS AS DESIGNATED - 502
EXXON is subcontracting to recoat #3 center tanks and #4 wing tanks. Specifications call for near white surface preparation (SS SA 2-1/2). Contractor is to apply 3.5-5 MDFT of Cathacoat 305 inorganic zinc (owner furnished).
Contractor is to supply all supervision, labor, equipment, and grit material to perform the work outlined above.
The following shipyard services will be required to support the above named contractor:
1. Crane service. 2. Electrical service and hook up. 3. Necessary internal and shell penetrations. 4. Dry gas-free tanks. 5. Contractor is to remove spent grit from tanks for shipyard disposal. 6. Necessary water/steam supply.
SHEET NO. 58
EXXON GETTYSBURG
MAY, 1978
EXX-MOR-010633
!56. 7. Area for office/equipment trailers. 8. Yard phone service. 9. Labor to provide necessary services above.
Note: Tanks to be recoated are #5 and #7 center, #4 across, #2 wing_ tanks.
>57. RECOAT AFT BOAT DECK AND STACK DECK (APPROX. 7,500 SO. FT.) - 504
Aft boat and stack decks are to be sandblasted to near white metal (SS SA 2-1/2) Apply one (1) coat of owner furnished Joton Balto Flake or equal to 25 - 30 MDFT. Prior to cure, broadcast spent grit into coating to act as antiskid. Applica tion to be in accordance with manufacturer's recommendations and to satisfaction of manufacturer's representative.
Application to be done in such a time that it will not interfere with other repairs.
SHEET NO. 59
EXXON GETTYSBURG
MAY, 1978
EXX-MOR-010634
258.
CONVERSION OF EXISTING DINING AND GALLEY FEEDING SYSTEM TO NEW CAFETERIA
MODE SYSTEM
_____________
A. The following are general notes concerning the refurbishment (betterment)
of the ship's galley and Officers' and Crew's Mess:
__
1. General Criteria: Removed equipment and furnishings are to be held -for re-use or disposition by the Owner. All interior surfaces are to be prepared and prime coated. Exposed interior surfaces shall be color coated. Exterior surfaces shall be coated with inorganic zinc and appropriate colors. Refrigerated spaces are located below the galley and mess area. These spaces shall be inerted prior to and during all adjacent hot work, if necessary. New galley and mess room equipment shall be stored and protected untiltime of installation. All contractor furnished materials shall be in accordance with the applicable plans.
2. Removals: Remove all galley, pantry, officer mess, CPO mess, crew mess
equipment and furnishings ashore and hold for re-use or disposition.
Remove all piping and electricals not required for new installations.
Rip out transverse bulkhead in its" ^entirety, at Frame . '-Remove
all bulkhead and overhead sheathing within the area created port and star
board between 'frames and ______________ . Crop openings in the following
locations to receive new doors and frames: Bulkhead -- port and
starboard passageways. Transverse bulkhead --
______ starboard.
Crop opening in bulkhead for passing windows in accordance with plans. Remove existing port light located in aft galley bulkhead, starboard.
a) Messrooms port and starboard and galley: Furnish and install closure bulkheads in port and starboard passageways at Frame_. Fur nish and install new joiner doors with view ports and hydraulic closures in way of these bulkheads. Doors to be non-locking type. Relocate vent piping as necessary, starboard, and blank off pene trations. Relocate radiators and modify air conditioning system ducts as necessary. Existing insulation to be retained. Install new insulation on bulkheads, and overhead as necessary.
Relocates%eneral alarm and telephone systems to suit new compartments. - Install foundations for new Owner's equipment port and starboard.
Install new Owner's equipment and secure. Supply and install stainless steel tables, shelves, storage, and counters in accordance with plans. Furnish and install new drop ceiling in port and starboard messrooms in accordance with plans. Furnish and install new formica bulkhead system in port and starboard messrooms in accordance with applicable plans. Port lights, doors and passing windows to be framed out with Stainless steel.
b) Galley: Install foundations for new equipment. Modify electrical systems and piping and install new insulation and sheathing as required. Furnish and install new stainless steel shelves, sinks, shelves and counter surfaces in accordance with plans.
SHEET NO. 60
EXXON GETTYSBURG
MAY, 1978
EXX-MOR-010635
CONVERSION OF EXISTING DINING AND GALLEY FEEDING SYSTEM TO NEW
CAFETERIA MODE SYSTEM (continued)
________________________________
Install Owner-furnished ranges, refrigerators, dishwasher and
associated equipment and secure properly.
"
Existing galley exhaust duct is to be modified for use as a supply system. Install supply fan and ducting complete with all electrical switches and vent risers as necessary. Existing exhaust riser shall be held for re-use. Install galley exhaust system in way of fryer and ranges complete with fan, hoods, filters, gaylord shutdown and . dampers. Re-use exhaust riser relocated above.
Upon completion of renewals and installations, existing deck is to be repaired and resurfaced. All equipment is to be covered and galley painted out with gloss white enamel.
3. Electrical: To the extent that is possible, existing cable shall be utilized and relocated to suit the above installations. Supply and in-
stall cable, outlets, panels, circuit breakers and switches new and exist ing to be as shown on isometric plans.
4. Piping (General): In way of removals, existing piping shall be removed to header and blanked. Galley piping is to be rerouted and connected to suit the new installations. Supply all necessary piping, fittings, valves and fixtures necessary to complete this work. All installation, new and existing, to be as shown on as built schematic.
5-. Fire plan; Vessel's fire plan shall be modified to show new compartments created by this modification. Furnish two (2) framed copies of revised plans and install as directed by the Chief Officer.
B. Provide manpower and material to accomplish refurbishment (betterment) of the ship's galley and Officers' and Crew's Mess in accordance with shipyard's drawings and Owner's instructions.
Time and material charges are to be made to proper items as noted below:
1. Material procurement: Procure all contractor-furnished material required to accomplish refurbishment modifications.
2. Engineering requirements: Provide engineering services to develop draw ings and procedures for approval by ABS, USCG representatives, and U.<S. Public Health Service.
3. Sheetmetal shop fabrication: Provide labor and material as required to shop fabricate sheetmetal components. (To include vent ducting, stain less steel bulkhead sheathing, counter tops and equipment racks.)
4. Sheetmetal shipboard installation: Provide labor and material as required to install and relocate shipyard and Owner-furnished equipment. (To include all shipboard removals and installations.)
SHEET NO. 61
EXXON GETTYSBURG
MAY, 1978
EXX-MOR-010636
CONVERSION OF EXISTING DINING AND GALLEY FEEDING SYSTEM TO NEW CAFETERIA MODE SYSTEM (continued)........................ ................................................
5. Piping modifications to ship's galley, Officers' and Crew's mess: Provide labor and material as required to accomplish shipboard piping modifications. (To include removals, relocation and shipboard tests.)
6. Electrical modifications to ship's galley, Officers' and Crew's Hess:
Provide labor and material as required to accomplish electrical modi
fications (To include removals, relocation, electrical maintenance and
shipboard test.)
.
7. Shipfitter modifications to ship's galley, Officers' and Crew's Mess (S/F/Welders) : Provide labor and materials to accomplish removals, shop fabrications and shipboard hull modifications. (To include equipment foundations, bulkhead removals, strengthening, after removals, if required.)
8. Rigging services: Provide all rigging and crane service for refurbishment modifications. (To include shop and shipboard requirements,' and from receiving department to vessel.)
9. Transportation: Provide labor and equipment to transport all material and equipment during refurbishment modifications.
10. Overhead ceiling installations: Provide labor and material to accomplish overhead ceiling installation. (Provide shipyard assistance as directed by Ship Superintendent.)
11. Decking requirements: Provide labor and material to accomplish decking modifications as reuqired. (Provide shipyard assistance as directed by Ship Superintendent.)
12. Paneling installation: Provide labor and material to accomplish paneling modifications as required. (Provide shipyard assistance as directed by
* Ship Superintendent.)
13. Reefer box relocation: Provide subcontractor to assist shipyard in the relocation of the non-self contained reefer box.
14. Clean-up (P/L): Provide labor, make removals, clean up and remove debris from work areas during modifications.
15. Painting touch-up (P/L): Provide labor and material to prime coat and touch up all disturbed areas.
C. Exxon Jamestown Class - Removals and Preparation of New Layout
1. Remove bulkhead between P, 0. Mess (Old) and crew mess pantry (old). Level deck of new larger room. Remove table, P0 mess, all buffets, ice maker (retain for new location, ice maker), coffee stand dresser, sink dresser, dishwasher, dish racks, etc. and dispose of according to instruc tions of Exxon Representative.
SHEET NO. 62
EXXON GETTYSBURG
MAY, 1978
CONVERSION OF EXISTING DINING AND GALLEY FEEDING SYSTEM TO NEW
CAFETERIA MODE SYSTEM (continued)
2. Remove framing of serving window, door to galley. Enlarge door . opening for installation of serving window, to new Officer's mess hori zontally, and fill in under serving window installation with bulkhead material as required.
3. Bulkheads are to be covered with formica wood grain (African teak, Honeytone oak, Cherry) panels or equal as selected by Exxon represen tative.
4. Overhead is to-be covered with acoustic type material. Fluorescent lighting, as instructed by Exxon rep., to be installed in overhead.
5. Crew mess (old)--- remove framing for serving window. Enlarge vertically,
to accept door framing in same location. Remove tables. Remove bulkhead
for serving window opening'.
-
'
6. Galley - remove equipment for relocation or disposal as per instructions of Exxon representative. Only cook's sink dresser remains in place. Other item relocated. Present 24" wide dresser in middle of galley may be incorporated in .24" wide dresser new installation forward side of galley if acceptable to Exxon representative, or other alternative as described under cook's serving dresser.
7. Old officer's mess - remove tables as required, or other items, to provide an area, as-per -instructions of Exxon representative, for installation of
. GYM equipment, or other recreation items.
8. Remove coffee maker from present location, old crew mess pantry, and install in old Officer's mess pantry (new night lunch pantry) as per instructions of Exxon representative.
9. Remove Scotsman ice flaker from present PO mess, and relocate to old Officer's mess .pantry, or mess room, as per instructions of Exxon Represen tative. Relocate scoop holder if on bulkhead to site adjacent to flaker.
10. Relocate drinking fountains, crew mess and New officer's mess to location as instructed.by Exxon Representative.
11. Relocate dish racks, old crew mess pantry, to new location galley, on aft bulkhead near dishwasher, as per instructions of Exxon Representative.
12. Relocate can opener, Galley, to new location.
13. Relocate slicer, Hobart 1612, to new location.
14. Relocate hand sink, paper towel dispenser, soap dispenser to new location as shown in layout. Relocate soiled paper towel holder, or provide new one adjacent to new location.
SHEET NO. 63
EXXON GETTYSBURG
MAY, 1978
EXX-MOR-010638
CONVERSION OF EXISTING DINING AND GALLEY FEEDING SYSTEM TO NEW CAFETERIA MODE SYSTEM (continued)
15. Relocate exhaust hoods, or replace with new as per Exxon representa tive's instructions, so as to provide suitable exhaust air from galley. Disconnect exhaust going to old dishwasher. Hoods to be extended or relocated over new location of new ranges and fryer.
16. Remove Hobart A-200 mixer from galley, relocate in Butcher shop on deck below, as per Exxon Representative's instructions.
17. Relocate Toaster, 4 slice Toastmaster Institutional type from present location to between Officer's and Crew's serving shelves, setting on Cook's Serving Dresser.
D-l Exxon Jamestown Owner-furnished Equipment
Amount
2 GENERAL ELECTRIC Marine Model MR07 ranges, 230/60/3 phase, SS front and sides (no overhead panel, controls on range) 3 12" x 24" hotplates.
1 Hobart AM 12 dishwasher
1 Traulsen Model RHT 2-32 N UT Refrigerate, remote condensor and compressor.
1 Traulsen Model R1T 2 32 N UT Freezer, remove condensor and compressor (Remote installation of compressor in lower passageway)
2 CORY IFW-248-U-2 500 watt infra red overhead heating device for installation over serving windows for keeping served food hot.
2 ALLMETAL refrigerated salad and dessert display #1215-30 S, with SS sides and base.
2 KELVINATOR or approved equal 2 SF ice cream cabinets
2 SHELLEYMATIC or approved equal SD 575 dish dispenser
2 ROUND DIPWELL or approved equal ice cream dipping sink
1 BUNNOMATIC D-2 B coffee stove or warmer, with sea rails and sea legs
1 BUNNOMATIC F-20 coffeemater, with sea rails and sea legs 120/AC/20 amp.
2 LITTON SYSTEM 70/15 Microwave ovens
2 BLOOMFIELD 1096 Stainless steel silva-tainers, with 6 1086-N cylinder inserts
32 L & B chairs, #6422-A (GE-15 rawhide upholstery, padded back and seat, Dark Oak #5 wood finish)
1 Gym set. Owner-furnished, to be installed in old Officer's mess as per instructions of Exxon Representative.
SHEET NO. 64
EXXON GETTYSBURG
HAY, 1978
conversion of existing dining and galley feeding system to new
CAFETERIA MODE SYSTEM (continued)............................
''
Amount
__
2 Litton System 70/15 Radar ovens, to be mounted on top of display cases ALLMETAL 1215-30 S, one in crew mess, one in officer's mess.
1 Shelleymatic #SD 1013H drop in dish dispensers, 110 Volt for 9-3/4" dinner plates (#SD1013H)
1 Shelleymatic #SD 813 H drop in dish dispensers, 110 volt, for 7" side
plates.
.
D-2 Shipyard Furnished Equipment
1 T & S spray for scraping dishes, to be installed in accessible location at back of dish scraping sink.
1 Dresser, RANGE, 3' x 30", 1 stainless steel perforated shelf under, to be installed between ranges, modularly fitted to ranges, at a height from deck of upper surface of approximately 36" (matching level of range top). To have marine rolled edge on aisle sides. All stainless steel construction.
1 Dish scraping dresser, 6' 9" long (approximate) x 24" wide, stainless steel construction, with marine rolled edge on aisle side, flashed to bulkhead on bulkhead side.. To have 24" x 20" x 14" deep dish scraping sink as shown in layout. Hot and cold water supply to be provided, drains.
1 Stainless steel backsplash to be installed on bulkhead in dishwasher area as required to fill in areas not now protected by backsplash, in area above dresser. Most of area now protected. Dresser must be contoured and fitted for entry and removal of trays of soiled and clean dishes to and from dish
' washer (AM 13 Hobart). Dresser to have area under for placement of dish scraping garbage can under dresser, so no braces should obstruct removal or
' placement of garbage can under dresser. Opening to be starboard side of sink.
1 Alter as required,
edge of old cook's dresser, and install stainless
steel addition as required, with proper entry of trans of soiled and clean
dishes into and out of dishwasher, AM 13 Hobart, Port side.
1 Stainless steel stand or shelf for mounting GENERAL ELECTRIC HK-3 fryer as shown, adjacent to FRYER/RANGE DRESSER.
1 Stainless steel construction, 24" x 36" dresser, modularly fitted to adjacent range, top level of dresser level with range, marine rolled edge on other sides. 1 stainless steel perforated shelf under.
SHEET NO. 65
EXXON GETTYSBURG
MAY, 1978
EXX-MOR-010640
CONVERSION OF EXISTING DINING AND GALLEY FEEDING SYSTEM TO NEW
-CAFETERIA MODE SYSTEM (continued)
____________________
' Amount
1 10* x 24" wide stainless steel dresser, with marine rolled edges on aisle sides, flashed as per USPHS on bulkhead sides, to be installed as the COOK'S SERVING DRESSER as shown in layout. AS PER INSTRUCTIONS OF Exxon Represen tative, utilize present dresser in place, and add as required; or utilize center serving dresser (OLD LAYOUT), adding or deleting material as required; or build all new construction. 1 Stainless steel perforated shelf under, 1 cook's drawer,
D-3 Exxon Jamestown Class Shipyard Furnished Material and Equipment
1 SERVING SHELF, STAINLESS STEEL 12" wide x 4' long approximate, depending on
final serving opening, to be installed at a height of approximately 12-13"
above level of cook's serving dresser^ Crew mess side.
smoothed or rolled
retaining edges for rough weather. Shelf extends over bulkhead, forward side
of shelf approximately even with bulkhead (finished, if covered) of Crew
MESS
1 SERVING SHELF, Stainless steel, 12" wide x 4' 6-9" Approximate length, installed as detailed for Crew's mess serving shelf, on Officer's mess side.
NOTE:
Structural supports may alter suggested dimensions of serving
openings. Intent is to provide convenient and ample area for
.
Chef to serve food to crew members, and as along as this criteria
is met, adjust serving openings to structural support requirements.
1 Provide door, with door frame, and enclosure of area to create janitorial area, also serving as opening to Port side of galley to deck. Provide wall mounted hooks, brackets, etc. for mops, brooms, mop bucket, etc. Remove inner screen or plastic fitted door in this area if required.
2 OPTION 1 Purchase and install 30" x 5' buffet/dresser, formica or stainless steel top.
OPTION 2 Provide and install 30" x 5' stainless steel construction dresser, 2 shelves under, stainless steel. Upper surface to have smoothed retaining edges (or marine rolled edge). Shelves to have h" approximate smoothed or rolled retaining edges on aisle sides.
Silva-Tainers, Coffee warmers, Coffee makers, etc. are to be mounted on upper surface of dresser, and constuction should be suitable for that pur pose. These items should be placed near bulkhead insofar as possible to permit possible use of aisle side for sliding trays if used.
2 Tray slides, stainless steel sheet, with smoothed or rolled retaining edges on aisle sides, to be installed at a height from deck of approximately 36". To be approximately 4*6" long x 15" wide. (No slotted or pipe construction, Marine use).
SHEET NO. 66
EXXON GETTYSBURG
MAY, 1978
EXX-MOR-010641
CONVERSION OF EXISTING DINING AND GALLEY FEEDING SYSTEM TO NEW
CAFETERIA MODE SYSTEM (continued)
__________________________
Amount
__
1 OFFICER'S MESS TABLE, 14' Long x 42" Wide, storm rails, surface to be
''
, installed on pedestals secured to deck
as per approval of Exxon Representative, using old pedestals from tables
removed with renovation as per instructions.
D-4.
Exxon Jamestown Class Shipyard Furnished Material and Equipment
"
1 CREW MESS TABLE, 36" wide x 14' long.
Option 1.
Use 8' table combined with 6' table from crew mess to make 14'
table. (81 table from old PO mess). Combine according to
instructions of Exxon Representative.
.
Option 2 At discretion of Exxon Representative, build 14' long x 36" wide crew mess table, storm rails, pedestal mounted as per instructions of Exxon Representative
UPPER SURFACE OF TABLE TO be covered with
.
2 Stainless steel shelves, 11" wide x 5' long, with 2V smoothed or rolled retaining edges on sides other than bulkhead side, to be installed as shown in layout. Care should be taken that supporting braces should not interfere with placement of equipment under.
NOTE:
If USPHS requires excessive area for cleaning under equipment, such as the coffee maker, it would be preferable to shorten shelf, rather than raise it because of this clearance problem to a height such that it would be hard to reach. Approximate height of 15" to 18" from upper surface of dresser could be usually considered convenient for average person.
Lighting, Crew and Officer's mess - Fluorescent
lighting,.............. ............. '
to be installed as per instructions of
Exxon Representative.
2 Stainless steel dresser/buffets 24" x 24" top surface, fitted against adjacent ice cream cabinet, bulkhead, and salad display. Marine rolled edge, or smoothed-rolled retaining edge on aisle side, to be mounted even with top surface of ice cream cabinet adjacent. To have 2 stainless steel shelves under and doors at front. (No shelf required in area, middle shelf where dipping sink and dish dispenser are present at back) 12" backsplash against bulkhead,
In addition to power supply for aforementioned items, provide double 110 volt receptacles as shown in layout, for use with small portable items such as toasters, etc.
SHEET NO. 67
EXXON GETTYSBURG
MAY, 1978
EXX-MOR-010642
COHVERSION OF EXISTING DINING AND GALLEY FEEDING SYSTEM TO NEW CAFETERIA MODE SYSTEM (continued)...............................................................
D-5 Exxon Jamestown Class Shipyard Furnished Material and Equipment
Amount
4 Two outlets each, on bulkhead behind item #28, Buffet
2 1 outlet each, item #34, ice cream dipping dresser on bulkhead
2 2 outlets on bulkhead behind item #24, cook's serving dresser
1 1 outlet, at back of Item #22, range dresser .
1 1 outlet, on bulkhead behind item #24, dish scraping dresser, STBD area
1 1 outlet, on bulkhead behind
FWD side of old Cook's dresser (sink
and Pot Washing, which remains in place.)
2 1 outlet, on bulkhead behind ALLMETAL 1215-30S salad display, above
display area, for possible use with stereo equipment which may set on
display cabinet. One on each of ITEM #6, SALAD DISPLAY.
'
SHEET NO, 68
EXXON GETTYSBURG
MAY, 1978
EXX-MOR-010643