AMERICAN BRAKEBLOK DIVISION CAPITAL ADDITIONS
Detroit
Land & Garage Bldg.Jennerstown Secondary Power Switchboard Office Additions to Bldg. #5 Three Do-All Special Twin Saws Two Compound Cooling Units One Hand Rolling Machine Three Automobiles for Testing One Special Hydraulic Press One Aldrich 2500# Press.Pump One Burroughs Acct'g. Machine Office Furniture Office Equipment Other Machinery & Equipment
Total
Winchester Bldgs., Machinery & Equipm't.
Total Additions, 1948
Cost
$ 7,700.00 12,052.29 17,294.73 34,378.39 7,738.91 5,292,35 6,655.97 8,160.86 3,375.13 2,742.65 2,025.76 2,672.59 16.002.63
$ 126,092.26
325,719.10 $ 451.811.36
Detroit Winchester
Total Depreciation, 1948
DEPRECIATION 1948
$ 80,517.48 82.457.49
$ 162.974.97