Monsanto .
from (name & locationi
j. c. Landwehr - Anniston Plant
\
February 2, 1971
SUBJECT
AROCLOR REMOVAL FROM WASTE WATER
REFERENCE
\TO :
_ \
N. Badger - Newport
P. F. Cunningham - General Offices
John Durland - Tokyo
'
W. G. Engman - W. G. Kruramrich ^)on Pogue - General Offices
H. A. Vodden - Ruabon
CC: J. L. Brown/I. Ransaw D. Danna - General Offices F. Macdonald/H. Disley - Newport W. B.- Pajpageorge - General Offices J. R. Savage - General Offices
The attached R & D Report (446-514, No. 1) is the first formal j.ssue of Anniston data on Aroclor removal from waste water. This covers a filtrationadsorption experiment that lead to the pilot adsorption and pilot clarifica tion studies listed under the report's Future Work Section. We are developing capital and operating cost estimates on the alternates being studied, and expect that differing situations will require one or another, or combinations of techniques. For example, filtration may be applicable only under limited conditions because of blinding and probably costs for cleanout of a commercial unit. It seems now that continuous clarification following adsorption on solids inherently present or added to a waste stream is most generally applicable.
Where stream flow is within a reasonable range and solids content is low, con
ventional carbon adsorption has promise. Studies just completed indicate flow
rates and carbon capacity tor Aroclors are in an economical range. This data
will be published as soon as design and cost parameters are received from co
operating vendors. Carbon adsorption following clarification would be the
system with greatest assurance of removal to no detectable amount by present
analytical techniques.
>
At the other end of the spectrum sumps, limestone pits, and solids settling pits are adequate down to the 100-300 ppb level. Attachment 2 shows results and cost of pumping sludge from an Anniston settling pit.
Clarification ejqperiments started February 1. The attached report from Betz Laboratories (Attachment 3) describes the flocculation system that will be initially used. Results on jar test samples indicate very good removal of Aroclors upon clarification.
Attachment 4 is a revised PR&D work plan which summarizes status on the work and dates for future phases to complete the program.
:kd Attachments (4)
DSW 345510