Document 5LB8zj24a2b8o8dGXgx2VqJbN
UNITED STATESUNITED STATES ENVIRONMENTAL PROTECTION AGENCY
* *REGION 1
ENVIRONMENTAL
AGENCY5 POST OFFICEB OSSTQOUN,A RMAE ,0 21S0U9-I3T9E12
100
PROTECTION
Drafted Date:13 September 2021
Finalized Date:22 November 2021
Subj:Inspection Report
Clean Water Act - National Pollutant Discharge Elimination
System (" NPDES ")
Blackstone Reserve
From:Andrew Spejewski, Inspector
Thru:Stephanie Tougas, Inspector
To:File
I. Facility Information
A. Facility Name:Blackstone Reserve
B. Facility Location:Blackstone Drive
61 Lane Road
Raymond, NH 03077
C. Facility Contacts: David Haddad
DJ Development
107 Windham Road,
Derry, NH 03038
david@djlandscaping.com
D. NPDES ID No (s).: NHR1000MG
II. Background Information
A. Date(s) of inspection: September 8, 2021
B. Weather Conditions: dry
C. US EPA Representative(s): Andrew Spejewski
ED_019088A_00019810-00001
D. State / Local Representative(s): None
E. Federally Enforceable Requirements Covered During the Inspection: NPDES
General Permit for Discharges from Construction Activities (2017 Construction
General Permit)
F. Previous Enforcement Actions: None known
III. Type and Purpose of Inspection
Unannounced evaluation of compliance with the 2017 Construction General Permit
IV. Facility Description
The site is a residential development, lying west of Lane Road, covering about 60 house
lots total. The main road of the development, Blackstone Drive, runs west uphill from
Lane Road, then forms a loop with itself extending to the west. Two short dead - end spurs
extend from the northwest corner of the loop, and to the south from the central point
where Blackstone drive splits (making this a four - way intersection). A dirt road runs
parallel and north of the north part of the loop road.
The loop is generally on top and on the north side of a hill; the terrain slopes down to the
north slightly down to the west, and down to the east along the east part of Blackstone
Drive. To the south, the terrain slopes slightly down in the central part of the site, and
more steeply along the western part.
The road includes drains which lead to a basin adjacent to Lane Road, a pair of basins to
the northwest (north of the spur road), and to a basin northeast of the loop (and northwest
of the completed section); a very small basin is also southwest of the loop.
At the time of the inspection, the area from Lane Road up to the loop was completed,
with occupied houses and the basin and all lawns with established grass. The spur to the
south was mostly complete, with lawns that had just been hydroseeded. Houses along the
north part of the loop were mostly complete or well under way, with houses on the south
part either at the foundation stage or not yet started.
V. Inspection
Mr. Spejewski arrived at about 9:30 AM. After asking site workers for the
superintendent, he eventually was met by Mr. Haddad.
A. Opening Conference
Mr. Spejewski explained the purpose of the inspection, presented his credentials, and
provided a copy of the Small Business Resources Information Sheet.
Mr. Haddad said Mr. Spejewski could tour the facility unaccompanied, and then find Mr.
Haddad for a closing conference. Mr. Haddad gave his cell phone number to contact him.
2
ED_019088A_00019810-00002
Mr. Spejewski agreed and received permission to take photographs during the tour. Mr.
Spejewski then left to tour the site.
B. Facility Tour
The two basins to the northwest had well - established grass walls and vegetated floors. A
dirt stockpile between the two basins was unstabilized (except for sparse weed growth;
not enough to stabilize the slope); there was no sign of sediment carried off - site from the
pile.
South of the basins, where the backyards of the houses met the dirt road running to the
east, a drainage channel down toward the road showed some erosion with sediment
deposits along the road; there was no sign of sediment carried through the adjoining
woods.
The dirt road had no (or old and no longer effective) erosion controls on the downhill side
(north), but only small amounts of sediment could be observed in the adjoining woods
and it did not appear to have been transported beyond the woods.
The north - central basin was well - grassed with a forebay with water and dry main portion.
No outlet pipe was observed; an emergency overflow to the north showed no staining or
signs of regular water flow towards wetlands to the north.
In the main part of the site along the north part of the loop most houses were complete (or
at least walls and ceiling up). Most lawns were bare dirt, but there were no signs of
serious erosion or channeling.
To the east, a slope led down steeply behind the backyards of the houses. The slope was
stabilized with rip - rap or grass. The eastern part of the southern border also sloped down
steeply, with a rip - rap wall in place down to undisturbed woods. In one backyard, a large
puddle / small basin was in place (Mr. Haddad later confirmed this was a temporary
basin).
Minor sediment deposits were at the foot of the rip - rap wall; they did not appear to
extend into the flat wooded terrain to the south.
In the center of the south edge, a few large stockpiles were in place along the border. In
one spot, the stockpile spilled slightly over the silt fence along the south border of the
site. The terrain to the south was at the level of the site, with undisturbed woods, and no
sediment appeared to be traveling through the flat woods.
The loop to the south has been recently hydroseeded, including lawns and a slope along
an access road to the west (south of the previous phase of the development).
C. Closing Conference
Mr. Spejewski called Mr. Haddad who said to meet him at his residence (in the
completed first phase of the development). Mr. Spejewski met Mr. Haddad there. Mr.
3
ED_019088A_00019810-00003
Spejewski pointed out the unstabilized stockpiles and the erosion at the west end of the
dirt road. Mr. Haddad said he would address them. Mr. Spejewski then thanked him for
his time and left the site at about 10:45 AM
Picture List:
IMG 2383.JPGBackyard, west of the loop, facing north
IMG 2384.JPGRetaining wall, west of the loop to the north
IMG 2385.JPGFacing north over retaining wall to west of spur
IMG_2386.JPGFacing north and east over western northwest basin
IMG 2387.JPGNorth wall of western northwest basin, facing east
IMG 2388.JPGFacing south over area between northwest basins
IMG 2389.JPGFacing east over eastern northwest basin
IMG 2390.JPGFacing southwest to spur from northwest basin
IMG 2391.JPGFacing south along east side of spur
IMG 2392.JPGFacing south, from west end of dirt road
IMG 2393.JPGFacing west to west end of dirt road
IMG 2394.JPGSmall previously cleared area north of dirt road
IMG 2395.JPGDetail, edge of dirt road
IMG 2396.JPGFacing east along dirt road
IMG 2397.JPGNorth edge of dirt road
IMG 2398.JPGFacing southeast, east end of dirt road
IMG 2399.JPGNorth - central basin, facing north
IMG 2400.JPGNorthwest side of north - central basin
IMG 2401.JPGHouse to northeast of loop
IMG 2402.JPGFacing north to center of loop
IMG 2403.JPGFacing north, from center of north part of loop
IMG 2404.JPGFacing west, from center of loop
IMG 2405.JPGBackyard, house due west of loop
IMG 2406.JPGFacing south, backyard at southwest of loop
IMG 2407.JPGFacing east over south edge of site from southwest of loop
IMG 2408.JPGFacing east over backyards, southwest end of site
IMG 2409.JPGNorth edge of site, north of loop
IMG 2410.JPGFacing west along west end of north edge of site
IMG 2411.JPGFacing east, stockpiles at north edge of site
IMG 2412.JPGFacing west over stockpiles, north edge of site
IMG 2413.JPGStockpiles north edge of site
IMG 2414.JPGBackyards, houses on south spur road
IMG_2415.JPGHouse east of south spur road
* END *
Unless otherwise noted, this report describes conditions at the facility / property as
observed by EPA inspector(s), and / or through records provided to and / or information
reported to EPA inspector(s) by facility representatives and as understood by the
inspector(s). This report may not capture all operations or activities ongoing at the time
of the inspection. This report does not make final determinations on potential areas of
concern. Nothing in this report affects EPA's authorities under federal statutes and
regulations to pursue further investigation or action.
4
ED_019088A_00019810-00004