TEN N EC 0INTER OFFICE MEMO CHEMICALS, INC to C. G. Thompson from E. V. Schenke Subject EPA PROJECT SCHEDULES BURLINGTON/FLEMINGTON at Piscataway at Burlington date December 2, 1977 copy TO D. C. Coldiron R, E. Harmond I. This memo is to advise you that: A. IhefeEPA;projects;:for*Burlington/Flemington are drifting further-behind<the*schedules -that*were*promulgated with tjje C^Rtebecauseof*design*changes,* mis s ing-tinformation, and concept reevnluations,*anddiweiare in- jeopardy-of exceeding- the mandated 107J&i*l'on,,stream^date. B. Additional major equipment purchase orders must be placed during the month of December (stripper column skid, etc.) in anti cipation of extended delivery dates. XI. The attached memos dating from November *76 are self-explanatory. Weua,xe afeill^operating*without:,, a-*"slurry-pump design -package'.Lat Elemington;approved^ water^balance-changes^related ~toincinerators ata-Flemington j^and^ requirements* for-j et-aleaning-systems at Burlington* Because most of these project costs are already in the CAR together with a short description of the proposed installation, the changes which are made or proposed will have to be covered by scope changes, even if they result in a lower net cost. III. Because the CAR's have not yet been approved, I am requesting Management approval to commit an additional $380,000 (Burlington Water Stripping Column Package Skid unit, Nash or Sihi Vacuum system, Water Stripper Feed Tank, and Slurry Pumps) in addition to the $350,000 which has already been committed for the three(3) incinerators and $70,000 which has been expended for outside engineering. EVS/ib Attachments E. V? Schenke COLORITE 019210 1 'i 5