Document 4vvqvb5V6x0YJNz4DOnRBEgKp
W. C. Engm'.n WGK
February 2, 1971
STATUS OF PROGRAM FOR AROOTOR POLLUTION CONTROL
Mr. J. R. Savage - G.O.
cc.
;t Mess re . G. L, Bratsch C. F. Buel<ley/M. R. Foresmm B. V. Corlaw P. E. Helsler P. B. Hodges - 0,0. D, W. Jackso W, A, Krull R. M, McCut-chan F. McDonald - Newport. A, L. Rasmussen W. R. Richard - G.O. J, Corder - Anniston B. Young
This is the February 1, 1971 status of the PCB pollution control program.
I. PCB Levels In Sewer:
A. Aroclor losses from the Aroclor Department averaged ' about 0,6 lbs/day with a high of about 1.1 lbs/dry.
Losses from the treatment plant for the period 12/17 1/15 averaged 22 lbs/dp.y (ll1! ppb). Range for 6 samples was 2 to 55 lba/day (9-278 ppb).
B. Data gathering on Aroclor in the various plant severs is in progress. Samples are being composited twice weekly for analysis.
IX. Projects to Reduce Sewered PCB's from Aroclor Department
A. Design package for Estimate 2422 to pave and trench loading and storage areas was completed and issued in January,
III. Programs to Eliminate Severed PCE's from Using Departments
A. Thermlnol system in OHA (Dept. 222) was changed to Thermlnol 66 during the month.
B. Completion of design packages for 13 additional units is scheduled for 2/15/71. Changeout of all units is targeted for completion by 6/1/71.
C. Several alternates including use of a eutectic salt arc being evaluated for the Dept. 245 (PsS5) thermlnol unit Evaluation is scheduled to be completed by 4/1/71.
MONS 099473
Mr. J. R. Savage - G.O. Status of Program for Aroclor Pollution Control
Page 2 February 2, 1971 WGK
D. Decision on what hydraulic fluid to use to replace the PCB Fydraul in Dept. 251 will be made by 3/1/71,
E. In order to reduce the risk of PCB's being sewered from washing Aroclor trailers at Rogers Terminal, all Rogers trailers containing PCB's will be washed at WGK's Rip Track.
IV. Reach 10 ppb in the Treatment Plant Effluent* 1 2 3 4
At this time, it appears probable that PCB losses to the
sewer can be controlled at less than 2 lbs/day (equivalent
to 10 ppb at the treatment plant) by 9/1/71. This will
be accomplished by:
.
1. Continuing current control of losses from Dept. 246.
2. Changeout of all thermlnol units to non-PCB fluids.
3. Installation of pads and catch basin at the loading and storage areas In the Aroclor department.
4. Installation of a catch basin at the Rip Track.
Losses at the treatment plant are expected to remain above 10 ppb by 9/1/71 due to past sewer contamination. Projects to clean sewers could run several hundred thousand dollars. A preliminary estimate to clean the sewer from the Chlorine department to the plant fence was $70,000 and another $70,000 would be required to clean from the fence to the treatment plant.
Both main plant sewers appear contaminated with PCB's (30W and 24W). Our plan is to continue monitoring the main Bewers to determine extent of losses and loss dissipation rate. By 6/1/71, when essentially all thermlnol units have been ohangedout, we should be able to extrapolate to when the PCB level should reach 10 ppb at the treatment plant without sewer cleaning. Based on this information, we should decide promptly on whether or not sewer cleaning is Justified.
V. PCB Levels in the Atmosphere
Estimate 2675 for $6,000 expense was approved to replace the nitrogen purge with a nitrogen blanket at the mix tanks. Project package is scheduled for completion by 3/15/71.
MONS 099474
Mr. J. R. Savage - G.O. Status of Program for Aroclor Pollution Control
Page 3 February 2, 1971 WGK
VI. PCB Rework Project (Eat, 2095)
Project package was issued in January,
Ai/.e.
W. C. Engroan Technical Services Dept.
MQNS 099475