Document 4qq79YNkbGxjn0oXDz8OX8JV
FILE NAME: WR Grace (WRG)
DATE: 1972 DOC#: WRG299
DOCUMENT DESCRIPTION: 1972 Request for Capital Appropriation for Vermiculite Ore Silos
\ACD 130N (Domestic)
REQUEST FOR CAPITAL APPROPRIATION
Division_____ Construction Products Division_______________ RCA E72-125
Project Title Vermiculite Ore Silos - Trenton New Jersey
Amount to be Authorized:
Per This Request
$U8,000
As Budgeted
U2.000
Under/(Over) Budget ($ 6,000)
Time Schedule Begin Spending Complete Spending Begin Operations
April, 1972 August, 1972 September, 1972
Authorization is requested to: Install four 200-ton vermiculite ore silos at Zonolite's Trenton, New Jersey expanding plant. This equipment will replace six open ore bins which are fully depreciated.
The present ore bins are located within the plant and are not covered. Any ore handling creates considerable airborne dust and the bins have been cited as a pollution hazard by the New Jersey Department of Environmental Protection. Failure to correct this deficiency will result in a shutdown of the Trenton facility. The proposed silos, located on concrete pads outside the plant, have been reviewed and approved by the pollution control authorities. In addition, they will provide needed space in the plant.
The Trenton plant services the metropolitan New York and Philadelphia
7
area. In 1971* it contributed $392,000 in gross profit.
The requested authorization of $U8,000 is $61,000 (lhi5) over budget. This overrun reflects higher design and material costs than orgiaally indicated.
AVERAGE CAPITAL EMPLOYED AND OPERATING RESULTS
________Z0N0LITE________ (Based on 1973 Estimate)
Avg. Grace Capital Enrol.
Net Income
% Return GCE
Cash Excess/(Def) From Operations
With This Project
$23,797,500 $2,539,700
10.7*
$1,5^0,000
Without This Project
23,753.700
2.5U2.200
10.7
1,537,70.0
Difference Fav/(Unfav) $ (U3.800) $ (2.500)
- % nts. $ '2.300
APPROVALS
Financial V.P. Manufacturing V.PC / y Operations V.P. / Presi dent_____ /"flL*- \
-
s
-c-t./- ...
Date
WB
SCHEDULE I - CAPITAL EMPLOYED
1. Fixed Assets
Four 200-ton Steel Silos $8,500 each (erected)
Concrete Pad -1*0 ft. x 1*0 ft. Design and Engineering
$3b,000 10,000
U.000
$1*8.000 ^
2. Assets to be Retired
Date Acauired
Six Open Ore Bins
1931
Purchase Net Book Value Price A/0 6/31/72
$3,000
$--0--
' SCHEDULE II - DEPRECIATION Cost
Annual Depreciation
Equipment (10 year straight line) $1*8,000
$1*,800
(l) This capital expenditure qualifies for 1% Investment Tax * Credit of $3,1*00.
t