Suggested Timeline from WP1 ,,RMOA" content plan - PFAS RESTRICTION
Milestones
Preparation of Call for Evidence (including questionnaire and information document) in agreement between MS
2nd version questionnaire Draft of information document (DE/NL CA)
Commenting round (all MS)
Revision and draft of 3rd version of questionnaire and information document for WebEx (DE/NL CA)
Detailed discussion of questionnaire and information document (all MS)
Final version (DE/ NL CA)
Notification into PACT (DE/ NL CA)
Call for Evidence (all MS and ECHA with news alerts and websites of all MS with Link to Helpdesk webpage)
Preparation of Restriction option analysis document (all MS)
Discussion of responses received so far, data (all MS) Decision on meetings with industry (all MS)
Discussion of restriction scope and options (all MS) Decision on which restriction options should be presented and discussed in RiME+ (all MS)
Meetings with stakeholders and industry
RIME+ Dortmund
1st draft of restriction option analysis document (all MS)
Contributions of first drafts of document parts according to lead in work packages and sub-work
packages (all MS)
Merge of contributions, redrafting (DE/ NL CA)
2nd draft of restriction option analysis document (all MS)
Redrafting by all MS
From
Till
30 April 2020
till 30 March 2020
31 March 2020
15 April 2020
17 April 2020
WebEx 20 April 2020 24 April 2020
27 April 2020
04 May 2020
30 July 2020
May 2020
Mid-November 2020
WebEx 24 August
WebEx 28 September
August/September 2020 20/21 October 2020 02 October 2020
24 September 2020
25 September 2020 05 October
02 October 2020 23 October 2020 16 October 2020
Merge of contributions, redrafting (DE/ NL CA) Finalisation of document, i.e. clarification of restriction options and scope (all MS) Last redrafting by all MS
Finalisation (DE/ NL CA) Restriction option analysis document to be
uploaded on CIRCA (DE/ NL CA) Commenting (by all other MS not part of group) Consideration of comments/if needed redrafting of document (DE/ NL CA in agreement with group)
RMOA-Conclusion, PACT-Update
19 October 2020
23 October 2020
20 November 2020
26 October 2020 10 November 2020
09 November 2020 20 November 2020
23 - 27 November 2020
01 December2020 01 January 2021
04 January 2021
28 January 2021
29 January 2021