COST ESTIMATES ASARCO December 2000
The following are cost estimates for the asbestos abatement of the materials found in the specified at the ASARCO Plant. These cost estimates reflect the cost for removal of the Asbestos Transite Board. The cost includes all cost associated with asbestos abatement, such as, but not limited to, insurance, bonding, certifications, labor, equipment and material. (NOTE; This estimate does not include repair or replacement costs.)
Licensed Asbestos Abatement Contractor
Abatement Costs ACM Black Insulation ACM Pipe Insulation 6 "-8" Fittings ACM Pipe Insulation 8"-15" Fittings ACM Black Insulation on Venturi Lines
LOW $85,800.00 $ 1,980.00 $ 1,500.00 $ 2,630.00
HIGH $97,350.00 $ 2,300.00 $ 2,000.00 $ 2,980.00
TOTAL
$91,910.00
$104,630.00
ASARCO ELP 0014-003
PRE- BID SIGN IN SHEET
Sheet or
DATE: 11/07/2000
Project Number OOEP-326
Client ASARCO
Project Name Asbestos Abatement at ASARCO Various sites. Nov.2000
Name/Company
Address
PhAW
I Emaii
ASARCO ELP 0014004