Document 3eokg6RBXNLQnN5ByaX6OnOba
Monsanto
fROM (NAME & LOCATION
H. C. Carder - B-2-N
DATE August 2, 1967
SUBJECT
AROCLOR CAPACITY INCREASES
REFERENCE
TO
J. Cresce
G. R. Buchanan L. C. Fuhrmeister P. E. Heisler D. B. Hosmer J. W. Molloy H. L. Williams R. S. Yates
The status of our plans for increasing Liquid Aroclor capacity via debottlenecking effort is as follows:
W. G Krummrich
There are two projects at WGK that should be completed around September 1, that will result in an increase in Liquid Aroclor capacity of about 1.5 M lbs./yr. These projects involve an increase in the size of the transfer chlorine line and an in crease in chlorine vaporization capacity. In addition, we are proceeding on verbal approval authority to install a still pre heater that should result in 5-7 M lbs./yr. increase and a capital project cost of $6,500. Timing on this project is still a bit indefinite, but we hope to have it
completed in order to meet our 1968 forecast
of 33 M lbs. for WGK.
Anniston
The project for installation of larger pumps and instruments on the stills should be com pleted by October 1, with October 15_as a
target date for demonstration of 53 M lbs./yr.
capacity at Anniston.
If there is any significant change in these plans, I will advise you.
bt DsW 200724 STLCOPCB4058788