Document 3N67raJ7M6nRjR6m9xrwpdR8E
Ethanolamines/glycol ethers
Tier 3 procedure
Section No.:
5009
Issue No.:
1.1
Original Date: 02-24-94
Author:
Date:
12-29-95
Title:
T-271 Boil Out (March 03, 1994)
References: Glossary Of Equipment Identification (Txt.114) Pdp-11
5009 T-271 Boil Out (March 03,1994)
1.0 Objective: 1.1 To complete this job in a safe and environmentally sound manner.
2.0 Responsibility: 2.1 It is the responsibility of the shift supervisor to ensure that this job is completed in a safe, environmentally sound and efficient manner.
3.0 Safety Equipment: 3.1 Block safety equipment.
4.0 Safety Notations: 4.1 We need to save an 8 oz. Sample of each boil out material for r&d. Fred I. Will pick these up.
4.2 Both charcoal beds will be changed out with new charcoal while t-271 is down.
5.0 Job Scope: 5.1 Boil out of tower.
6.0 Equipment: 6.1 A. (2) 20 ft. By 2" flex hoses B. (2) 20 ft. By 1" flex hoses C. (2) 2M flex gaskets D. (2) 18" pipe wrenches E. (2) 1 1/16" combination wrenches F. Big amines trailer empty G. Bullet trailer
7.0 Pre-Shutdown Procedures (3/2/94) 7.1 A. Make out tags & master for shutdown. B. Empty dv-243a & dv-272a/b before 3-2-94. C. Empty big amines trailer.
Date Printed: April 19, 1998 Paper Copies Of This Document Are Uncontrolled & Not Subject To Update. The Controlled Document Resides In File:
Page 1 Of 2
DO A 058931 CONFIDENTIAL
D. Assemble all equipments out in the field. E. Flush out cf-271 and cf272 on wed. Night so they could be re-charged.
Date Printed: April 19, 1998 Paper Copies Of This Document Are Uncontrolled & Not Subject To Update. The Controlled Document Resides In File:
Page 2 Of 2
qq a 058932 CONFIDENTIAL
8.0 Shutdown: 8.1 A. Remove east t-271 feed filter B. Hook up 2" flex hose from east filter to the 2" bleed on t-271 o/h line at the control loop. C. Put t-260 btms. To dv-272a thru e-272p. D. Pump t-271 empty to dv-275 thru the heel line. E. Hook up 1" flex hose to the d/s bleed on t-271 O/h c/I. F. Shutdown t-271 ejector and pressure up the tower with nitrogen to 35#. G. Blow tower btms. To dv-273a and o/hs to waste trailer. H. Isolate t-271. I. Open boil out valve. J. Hook up condensate at the u/s bleed on t-271 reflux c/I & start a flow. K. Hook up condensate at the t-271 recirculation c/I & start a flow. L. Tie flex hose at dv-273's to the big trailer. M. When level reaches 90%, start a btms pump on recirculation. Start steam to e270 & bring to a boil. N. Boil to the big trailer until t-271 btm's tod is less than 40,000. O. Open all bleeds & boil to the slab until stream is clear but no less than 8.0 hours, don't forget reflux. P. Blow N2 thru tower until all free water is removed but no more than two hours.
Q. Close all bleeds and put t-271 on the ejector in preparation for start up.
9.0 Revisions:
Revision No.1
12-29-95
Yearly Review
Date Printed: April 19, 1998 Paper Copies Of This Document Are Uncontrolled & Not Subject To Update. The Controlled Document Resides In File: