Document 34EaLQQyBkx8Ny6d6dB3q2MO
'
or
COMPANY CONFIDENTIAL
Monsanto
'
Anniston Plant
TECHNICAL SERVICES DEPARTMENT
MONTHLY REPORT
Anniston
A. H. Hill G. L. Jessee L. C. Lahman J. C. Landwehr G. W. Miller H. Schulte W. P. Taffee H. L. Williams
Month
Summary December 1969
Cost Improvement Results
Est. Act. . Target
$57,515
$65,085
. % of Target 88.4%
General Offices
YTD
$591,846
$638,915
92.6%
H. S. Bergen
H. C. Carder
?
D. Danna (5) f'
P. B. Hodges
D. B. Hosmer (2)
W. A. Kuhn
C. F. Luecke
J. A. Morgan
Wv fii--Rafairdc
J. E. Smith
J. A. Stephens
R. J. Stratmeyer
ft r
Organic Division
Combined Production and TSD efforts to improve yields in the PNP Department have resulted in the best PNCB usage for any 1969 month.
Agricultural Division
Parathion recovery pilot test facilities were installed
and checked out. Field tests are scheduled to begin
January 7.
.
Plant Improvement
OTHER LOCATIONS
A. H. Forsten Alvin, Texas
Solid Incinerator Project (AFE 3094 - $20.0M) was approved. Corrosion proof channel in plant drainage to Snow's Creek (AFE 3088 - $8.7M) to protect City Water Main was completed and put in service.
D. W. Jackson WGK
T. M. Patrick So. 2nd St.
DSW 551194
M/,/,96e
COMPANY CONFIDENTIAL INFORMATION
"This document contains confidential information which is the property of Monsanto Company. Only those portions of the document relevant to a duly authorized individual's need to know may be exerpted for him. The report must not-fce sent outside the Company without written
annrnval and the rer.inient is arrmintahJp fnr its safe Ueenina pyprntina nr otherwise Hisrlnsino of its contents and for its nroner Hisnnsal *9
STLCOPCB4089611
D
Company Confidential 2.
Utilities Actual savings in 1969 for Utilities Cost Improvement will reach $10.8M ($20.2M/yearly rate).
Design & Drafting The old 175 KVA Niran Emergency Generator was rebuilt and returned to Plant. Installation is scheduled to be completed in January.
Pollution Control KemTech Labs Inc. conducted a three day Air Pollution Survey in areas in and around the Anniston Plant.
Quality Control The Plaint Quality Score was 80.2, up 2.2 from November, with a YTD score of 86.6 against a 1969 target of 95.0. A Process Capability Audit was completed, revealing restrictive speci fications in 19 out of 44 finished product control tests.
:kd
DSW 551195
STLCOPCB4089612
ORGANIC DIVISION 1969 TSD COST IMPROVEMENT
ANNUAL JAN FSB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Sol.Aro. Level TAR 1
Ind.& -Still SpG EST
AFE 3015
ACT
Solid Aro.
TAR
Lower 5060 Soft. Point
est; ACT
225012250 2250 2250 2250 2250 2250 2250 2250
--
-
---
"
---
---- "
2600 >600 2600 2600 2600 26oo 2600 2600 2600
77 SO-1500 5490 4390 215C 467 C soot 4230
3475
L1500 5490 4890 2150 46/ 80oc 4ioU 7730 3475
-
--
Sol .Aro.-Still TAR
Coolant temp. EST.
AFE ^*015
ACT
Sol .Aro. -Chlortcr TAR
Batch End
EST:
AFE 3015
ACT
160 170 160 170 160 170 160 170 160
--
"
---
""
".
590 390 390 390 390 390 390 390 390 ---""
~--
Sol.Aro. Yield TAR
SW/R Composition EST
AFE 3016
ACT
Solid Aro.
TAR
Montar 5 Flake EST
AFE 2949
ACT
2750 2750 2750 2750 2750 2750 2750 2750 -- ~----
"
1080 1080 1080 1080 1080 1080 1080 1080
*" -
-
--
"- "
"
Sol.Aro. Blend 4465
TAR EST
ACT
2500 2500 2500 2500 2500 2300 .25,00, 2500 2500 2500 2500 2500
1690 1920 1680 1490 710 1180 990 220 1690 1920 1680 1490 710 1180 990 220
--
10 710 350 10 710
Sol.Aro.-Verti- TAR
cal Still Cond. EST;
AFE 2324
ACT
70 80 70 80 70
70 90 90 9 0 90 " - "
70 90 90 90 90 -
**
Sol .Aro.Cl^ T/C Dock AFE 2342
TAR EST. ACT
940 940 950 0-
0
Sol.Aro.-New Cl2 TAR
Unload - No Delay EST'
CED 1831
ACT
Solid Aro.-Flake TAR
& Drum
EST.
CED 1430
ACT
Liq.Aro.
TAR
48-53 M #/yr. EST
AFE 2545
ACT
950 940 950 940 950 940 950
900 2330 2050 2320 1650 2360 164C 2180 900 2 330 2050 2520 1650 2360 1640
5000 5000 5000 5000 5000 5000 5000 5000 5000 5000 5000 5000 0 0 1000 2000 2000 2000 300C 3000 3000 3000 300C 3000 0 0 1000 2000 200C 3000 300-: 3000 liOOO 3000 3000
ooo
5000 - - - - - - - - - -
0 550C 0 550C
-- -
Liq.Aro."No.2
TAR
Still Entjrain Sep. EST.
3000 3000 --
AFE 3093
ACT
Liq.Aro.-Montar TAR
Disposal
EST.`
AFE 2952
ACT
1080 1080 1080 1080 1080 1080 1080 1080 1080 1080
0 00
00 0 -
- -"
0 00
00
-
- -' *
Warehouse Reduce Manpower CEA 1452
TAR EST; ACT
2000 5000 3000 5000 5000 3000 3000 3000 3000 3000 3000 3000 2000 2000 200c 3000 3000 3000 300C 3000 3000 3000 3000 3000 2000 200C 20CC 3000 300C 3000 300C 300c 3000 3000 3000
Liq.Aro.New
TAR
Burners #3 Still EST
ACT
1500 1500 1500 1500 1500 1500 1500 1500 1500 1500
0 0 1500 3000 900 0 -
0 0 --
0 0 1500 3000 900 - -
0' "
Biphenyl Relocate TAR
No. 1 Preheat EST
CEA 1892
ACT
500 500 500 500 500 500 500 500 500 500 500 500
1500 150C
0 1560 1870 0 6 10 1370
0 0
0 15UO 0 0 1500 a
-
0 1780 1780 _ 1780
HB-40
2nd Autoclave AFE 3102
TAR
EST ACT
5000 5000 5000 3000 3000 3000 3000 5000 3000 3000 3000 3000
2230 2580 0 3490 2420 0
600 9000 6000 5600 4-2 uu 600 10/40C 8600 745U o950
5 UU 1000 4800 750 1400 4800
6000
DSW 551196
STLCOPCB4089613
ORGANIC DIVISION 19 69 TSD COST IMPROVEMENT
$ 4
ANNUAL JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Bi0 Improve Tower Treat. ARE *1155 Improve Pit. Power Factor
TAR
EST ACT TAR EST ACT
450 450 450 450 450 450 450 450
0U 00
0,, 584 645 0 585 645
50 725 700 50 725
~mr900 900 900 900 900 900 900 900
0 500 900
900 950 955 950
0 500 83O 990 980 940 955
Central Air System
TAR EST ACT
1000 1000 1000 1000
- - - -. ----
Optimize Rx Time
PNP Reduce Mole Ratio NaOH/PNCB PNP
TAR EST ACT TAR EST ACT
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
0 3420 0
0 0 2940
0 0 0 4130
0 3420 0
0 0 2940 2370 0
00
4000 ,4000 4000 4000 4000 4000 4000 kooo 4000
0
00
0 0' 0
00 0
0
00 0 0 0
00
New Wash Water Pump - PNP
AFE 2998 Automatic pH Control PNP
TAR EST ACT TAR EST ACT
50 50 50 50 50 50 50 50 25 50 50 50 50 50 50 50 50 50 50 25 50 50 50 50 50 50 50 50 50
500 500 500 00 0 00
HC1 Filter Pump
TAR EST ACT
330 330 340 330 330 340 33O 3 3C 340
New Blow Tank HC1
TAR EST ACT
200 200 200 200 200 200
200 200 200 200 500 200 200 200 200 200 200 200
150,000 Gal.-HCl Storage Tank AFE 2468
TAR EST ACT
1760 17$0 1780 1760 1760 1780 1760 1760 1780
"
U -
0 2640 3290 2990 3500 3500 3500 0 2830 3430 3125 3200 3700
Produce Staley Grade Acid AFE 3076 Cla Plt. Shutdown
CEA 1831
TAR EST ACT
TAR EST ACT
780 7Q 790 790 780 790 - - --- - - - - --
8880 8880 8880 8880 8880 8880 8880
8880
+2335' L9900 k-1990C 19900 1990019900
223C 6655 +2855 19900 1990C 19900 19900
Hg Recover from Residua
TAR EST ACT
250 50 250 250
3910 0 3910 0
00 00
Hg Wash Tank
AFE 2802 Biphenyl Productivity
Total Organic By Month M $
Total Organic YTD M $
TAR EST ACT TAR EST ACT
TAR
EST ACT TAR EST ACT
250 250 250 250
00 00
00 00
.5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600
0 1 9U0U IBTxx 0
0
0 50733} 12700 0
00
0
1800) 5900 13500 0
0
0 3078C 2700 0
00
a^0280230! 26.8 29.3 37.5 42.3 51.1 51.6 51.6 51.
.7 53.5 50.6
27.1 30.2 11.5 36.3 39.^5 107.4 53.844 49.41040820
16.5 23.3 27.3 11.4 25 .75 45.9 11052 258J6 51,930 40410^7.340j
23.3 50.1 79.4 116.9 159.2 210.3 261.9 313.5 Wl 417.8 471.3521.9
16.5
46.9 40.3
78.8 68.1
79.6 115.9 79.5 105.2
144.4 151.1
258.5 261.20
3315l9JL.43L5;33678]..S3364l41l21.,72904^5598.233552 0941!
* $2^55 adjustment included for May & June.
** $27,780 adjustment included for months
January thru June.
DSW 551197
STLCOPCB4089614
T>
-
AG DIVISION 1969 TSP COST "IMPROVEMENT
ANNUAL JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Cooling Tower Repiping AFE 2598
TAR
EST ACT
4?0 420 410 410 420 420 410 420 420
0 00
Oj 0
0
000
0 00
00
0
O0
Optimize N2 & Cl2 Levels
TAR EST ACT
6600 6700 6700 6600 6700 6700
0
00
00
0
0 00
00
O
Increase Waste Acid Sales
TAR EST' ACT .
400 300 300 400 300 300 400 300 300
00 0 0 00
O0
0
00
0
0
00
00
Chlorinator R.I. AFE 2244
TAR EST ACT
250 250 250 250 250 250
00
0
O0
0
0 0 0 00
EVOP Condensation Rx.
TAR EST' ACT
750 750 500 0 0 12,615 0 0 12,615
500 750 750 O 0 2165 00
Cl2 Unloading CEA 1831
TAR EST ACT
5000 5000 5000 2000 2000 2000
. 0 0 1580 730 4150 3800 0 0 1580 730 4150
Recycle Wash Water AFE 2960
TAR EST' ACT
290 290 290 290 290 290
00
0
00
0
0 0 0 00
Parathion Recovery TAR
EST
AFE 2655
ACT
580015800 5800
00
0
00
Reduce Acetone Losses
TAR EST ACT
430014300 4300 0 0 1050 00
Formulations AFE 2897
TAR EST ACT
1600 1600 1600 1600 1600 1600
S
3000 6600 10,0a 4570 2000 3950 1000
43OO 10,400 928^ 4570 1205 2675 9501
lyiChange Cooling Item AFE 5067
TAR EST ACT
125 125 125 125 125 125 125 125 125 120 130 155 272 333 310 218 240 220 120 180 171 272 333 310 220 300
Well
to Jets
TAR EST ACT
500 500 500
0 00 00
Ag. Division by Month
TAR 750 750 50019145 9145 91^5 14675 1463 5 1 A.685 14575 1448 5 14485
1205EST T$15 3,12 0 6,780 10,155 4842 4033 13,711 8873 4920 7235
ACT 0 0 4,420 10,530 9459 484; >6488 L3435 8825 5535
Ag. Division YTD
TAR
EST ACT
750 1500 P00d 11143 P0P90 P9425 441 00 58785 7347C 3 8 045 10253] 117015 12,61p MS 25,815 37J70 41,936 45,949 6^114 59,712 74584 32434
0 0 12,615 17,035 27,615 57.07441,936 48,4% 30839 59,664 75199
Ag. Division
TAR
untargeted-R.M.
EST
Charges ootimizatii rACT
0 1700 3690 287C 1700 3690 2870
530 530
Organic Div.
TAR
Untargeted - HC1 EST
Catch Tank& Coale: eACT
0
5000 0
00 0 6250 596C 4690 1330C 700C 6500 2000 935C 6817 4920 L5355 6500 7080
Ag Div.-Untargeted TAR
EST
irj ^12 change out ACT
Organic Division
TAR
Untargeted -Optimiz e EST
l->^ ^ /-4- v T7--
-- TMkTT^ * /''im
3250
4180
4180 ------ -
4055 4055
555
l1 DSW 551198
2740
STLCOPCB4089615
Company Confidential 3.
AROCLOR
C. R. Mcllwain, E. E. Bowles, (V. R. Haupt)
Evaluate QuaterphenylPolyphenyl Effects on Solid Aroclor Yields
1969 Savings - $63,200
NFC
$14,000
TSD Objective B-8(a)__________
The #9 chlorinator - #4 still system will be used primarily for Aroclor 1268 in 1970. Data on specific gravity of 1168 and 1268 will be obtained on the next production run to calibrate the nuclear specific gravity quality instrumentation to these materials.
This type of instrumentation has been incorporated in the Solid Aroclor expansion project CEA 2080 and will be calibrated during the start-up.
Porocel Columns CEP 2132;Technical Assistance_________________________________
TSD Job No. 930
This CED project will be closed during the month of January 1970. Several small items will be completed by plant forces.
Production is still experiencing problems with the power factor instrument. Tests thus far have not found the source. Further testing is continuing.
BIPHENYL-SANTOWAX
W. G. Niemeyer, D. A. Self, (V. R. Haupt)
Biphenyl-Santowax MIPPlanning TSD Objective B-7(a)
The Manufacturing Improvement Plan for Biphenyl-Santowax is 50% complete. MIP will be completed in January 1970.
Eliminate Safety Hazards at No. 1 Benzene Feed TankSafety;TSD Job No. 976
AFE No. 3373 was issued on December 3, 1969, to eliminate the safety hazards at No. 1 Benzene Feed Tank.
Customer Assistance to Constellation Finishes, Dalton, GeorgiaSales SupportTSD Job No. 904
Provided cost information on conversion from flaked biphenyl to molten bulk biphenyl storage. TSD supplied this service to meet competition from Geneva Chemicals.
DSW 551199 STLCOPCB4089616
Company Confidential 4.
BIPHENYL-SANTOWAX - continued
.
Santowax R - Solid Aroclor
Yield Test Run
________________Yield SavingsTSD Job No, 984
A test run was planned to determine how high and low quaterphenyl content of Santowax R affects Solid Aroclor yield. At least 10 Solid Aroclor still batches will be run on both high and low quaterphenyl Santowax,R raw : material. The Solid Aroclor still yield will be measured directly by stick ing the still receiver. This type.of test run will require cooperation of both Aroclor and Santowax production personnel. TSD will monitor the test and collect test data.
HCl L. 0. Chambers, K. G. Hale, (A. G. McCarty)
Production of Staley Grade New Earnings - $288M Acid - AFE 3076Potential Savings $71,000B-^10 (c)
TSD Objective
Carbon treatment studies were delayed until an adequate analytical procedure can be developed. Attempts at using a Jacksonville University instrument (Beckman DBG) failed. The instrument had poor resolution and would not separate the contaminants absorbed at different wave lengths.
Initial results of a Perkin Elmer - Model 124 Scanning UV instrument demon strated in the plant looks good. The PR&D group will continue evaluation for purchase of the instrument (estimated cost $3-4M).
HCl MIP~ Planning B-l(b)
TSD Objective
All review comments returned. Final plan will be issued in January 1970.
Muriatic Acid Reduced High ChlorineQuality TSD Job No. 950
Rotameter hae been delivered to permit maintenance to complete installation to air blow #7 storage tank to reduce free chlorine. This is an interim measure until process data can be collected to identify cause of intermittent high chlorine.
PNP L, 0. Chambers, K. G. Hale, (A. G. McCarty)
PNP Dust
Safety
Flammability;(SSPP Audit)TSD Job No. 814
Final report has been written and is now being circulated in plant for comments prior to typing.
i 1i
DSW 551200 STLCOPCB4089617
Company Confidential 5.
PNP - continued
PNP-Sulfuric Acid.
Safety
Unloading Pump(S&PP Audit)TSD Job No. 979
Project premise for pump unloading was not approved by Production because of potential problems with pump as compared to present trouble - free air unloading. Alternate means of minimizing safety hazards (flange guards) will be initiated by Production. TSD report is out for comments, and will be issued by mid-January.
PNP - DebottleneckCapacityTSD Job No. 482
The actual present capacity is being evaluated in. the different process steps. Alternates for expanding to 2.0M and 2.4M #PNP/month are being developed. Summary of alternates, expected capital required, and present capacities is targeted by mid-January.
NIRAN
D. W. Dudley, T. W. Lawrence, (A. G. McCarty)
Demonstrate Parathion Recovery
TSD Objective __________B-5 (a)
Parathion recovery test facilities completely installed. Initial tests will begin in early January and are expected to last approximately two months.
Acetone Recovery'
Savings $25,200
TSD Objective
__________________ 20% Reduced CODB-5 (i)
Acetone.recovery project is operating near design conditions. No pump out. problems have occurred through 677 batches. Acetone yield for December was 6.18 lb./cwt compared to a 7.25 lb./cwt standard. After a piping modi fication in early December, acetone usage fell to 5.88 lb./cwt, close to the target of 5.18 lb./cwt. Optimization of ejector performance and repair ing vacuum leaks allow 100 mm Hg abs. will further improve acetone usage toward the targeted 5.18 lb./cwt.
Potential savings $50,000
Improve Chlorinator
per 0.5 hour reduction in
TSD Objective
Cooling System ___________chlorination timeB-5 (g)
A Tentative Process Amendment has been approved in th e plant and is await ing Division approval. A project premise, based on the use of Freon 21 in place of Freon 11, and an experimental expense AFE have been approved. Mechan ical design is in progress for temporary cylinder racks and piping. A spare vacuum pump, for use during the test, is available in the plant. Field tests are targeted to begin in late February and to last through May.
DSW 551201 STLCOPCB4089618
I)
Company Confidential 6.
NIRAN - continued
Chlorinator Off-Gas System ModificationSafetyTSD Job No. 980
Investigation is continuing on means to completely elJminate violent de compositions and subsequent damage to equipment in the chlorinator off gas systems. Evaluation of an entrainment separator to preclude unstable material from catch-pots and piping showed this concept to be of question able value. Efforts are now being directed toward preventing the mixing of steam and water from the jets and direct contact after-condensers with the unstable material accumulated in the catch pots. Alternates have been developed and will be discussed with Manufacturing in January.
Replace Nitrogen with
Potential Savings
HCl for Chlorination Sparge$20,000TSD Job No. 603
A Tentative Process Amendment has been prepared and is circulating for approval in the plant. Plans are to test the concept in the early part of the upcoming methyl run.
PROCESS AND QUALITY ANALYSIS
J. L. Murphree, (W. B. Dunlap)
Process Surveillance
The first Process Capability Report was completed, revealing restrictive specifications in 19 out of 44 quality specifications. A process correlation study was begun in Aroclors to determine critical operating variables.
PNP - Identification of
Potential Savings
Critical Variables$60,000TSD Job No. 839
TSD Objective C-3
Experimental operation of the PNP reactor was carried out through December at one optimization setting indicated by process analysis study of summer 1969. PNCB usage, calculated from batch weights, dropped from 117.6 to 115.3. A cost improvement target of $46,000 has been set for this job in 1970.
Niran Still Control .Potential Savings $79,000TSD Job No. 964
Installation of control instruments is underway. Target dates have been advanced for installation (1/15/70) and completion of the still control study (8/1/70). A review of the study was held with Production personnel.
ENGINEERING DESIGN AND SERVICES
Mechanical/Electrical/Instrument Design & Drafting
J. C. Price, G. W. Richey, R. V. Carlisle, J. K. Rennie, (W. F. Taffee)
J. A. Veazey B. D. Morgan R. L. Brewer
The rebuilding of the existing 175 KW Niran Generator was completed and the unit was returned on 12/22/69. Installation is about 50% complete with
DSW 551202
STLCOPCB4089619
r>
ENGINEERING DESIGN AND SERVICES - continued
Company Confidential 7.
Start-up scheduled for spring turnaround.
Three projects covering the purchase and installation of additional Emergency Radios (AFE's 3389, 3390, 3391 - $0.8M each) were forwarded and approvedso as to extend emergency radio coverage to P2S,., Bip^enyl and Shipping.
Two projects were scoped and estimated. Replace Sight Glasses (AFE 3362 $2.5M), OMP Dismantling (AFE 3359 - $27M).
Significant department effort was expended in compilation and review of material necessary for inclusion in the Anniston "L" Manual. Specific areas reviewed included: Electrical, Material Handling, Piping and Protective Linings.
All long delivery items are on order and installations are tentatively scheduled for spring turnaround (Niran) on the following projects: Modify Agitator Interlocks (AFE 3118 - $9.7M), Automatic Alcohol Feed to Thio Acid Reactors (AFE 3161 - $3.9M).
Drafting
In progress:
Eliminate Safety Hazards #1 Benzene Tank (AFE 3373 - $9.0M), Update Plant Single-Line Diagram.
Review drawings were completed for the following projects: Formulation Revision - Niran (AFE 2754 - $22.8M).
Construction drawings were completed for the following projects: Niran Soda Ash Deluge System (AFE 3149 - $1.4M), Aroclor - Eliminate Head-Knocker (AFE 3364 - $1.1M), Niran Agitator Interlocks (AFE 3118 - $9.7M), Niran Automatic Still Control Test (AFE 3347 - $2.2M).
UTILITIES ENGINEERING
J. C. Price, (W. F. Taffee)
Completed first draft of progress report on Utilities Cost.Improvement Results for 1969 and Plans for 1970. This report was discussed with W. E. Chandler and is being revised and will be published in January. Utilities Cost Improvement Actual Savings for 1969 will reach $1Q.8M ($202M/year). Furnished CED with operating data for Aroclor PNP cooling tower .for use in design of HB-40 Expansion.
DSW 551203 STLCOPCB4089620
Company Confidential 8.
PLANT IMPROVEMENT
G. C. Goodwin, (W. F. Taffee)
A project to Install Solids Incinerator at Plant Dump (AFE 3094 - $20M) was approved during December. Transmittal of design package is scheduled for mid-February with equipment delivery expected in February.
Construction of Corrosion-Proof Channel to Protect City Water Main (AFE 3088 - $8.7M) was completed and put into service during December.
Design packages for Renovating Niran Control Room (AFE 3369 - $19.5M) and Automatic Fail-Safe Valves on Storage Tanks - Niran (AFE 3326 - $9.0M) were deferred by the Agricultural Division due to limited capital money.
The final design package for Grating Over Niran Process Trench (AFE 3367 $3.1M) was transmitted during the month.
POLLUTION CONTROL
E. G. Wright, (W. F. Taffee)
Air and H20 Pollution
Community and Governmental
ComplaintsRelationsTSD Objective B-2
No H20 pollution complaints were received during December. Four (4) air pollution complaints were received during the month.
Eimco Filter Unit at Waste Treatment
Production Assistance
TSD Objective F-4 TSD Job No, 808
The Eimco representative visited the plant during December to aid in resolving the problem of cloth "blinding." As a result of his recommendation, the feed slurry was "thickened" and the unit's performance improved a significant amount. Addition of the Betz polyelectrolyte also increased the unit's effi ciency. During January, further tests are scheduled in order to optimize the process. It is tentatively scheduled to release the unit to Production by February 1.
Air Sampling Slurry 'Pollution AbatementTSD Objective C-2
On December 15, 16, 17 a representative from Kem-Tech Laboratories conducted an air survey around the plant perimeter using their mobile laboratory. We should be in receipt of their report during early January.
HCl Neutralization PitPollution AbatementTSD Objective F-4
Since repairs of the Niran H^PO^ pit have still not been completed, it remains . impossible to determine if the HCl pit has "broken through" due to the excess H^PO^ present. As soon as repairs to the Niran pit are completed a test will be run to determine the present effectiveness of the HCl pit.
DSW 551204 STLCOPCB4089621
POLLUTION CONTROL - continued
Company Confidential 9.
Waste Treatment
All wastes were effectively treated during December. Average daily values for Monsanto's effluent are as follows:
PNP COD Parathion BOD
Average daily 1.0
94 .70
6.0
Specifications 5 ppm
200 ppm 1.0 ppm
200 ppm
DSW 551205 STLCOPCB4089622
PLANT LABORATORIES G. W. Hiller
Company Confidential 10.
PROCESS RESEARCH AND DEVELOPMENT J. T. Bell
Of the 110 mandays available to PR&D in December, 67 mandays were expended on projects included in the 1969 PR&D Program. Vacation, supervision, miscellaneous, and special projects (Aroclor 5460 Acetone Insolubles, preparation of special Aroclor samples) account for the remaining time.
Blend Scavenger Refinement (Aroclor)
Improved Aroclor Electrical PropertiesJ. L. Brown
Upon receipt of a special order of Type 4A Molecular Sieve, a work plan will be issued outlining a final study for evaluation of this material as an absorbant for refining electrical properties of Aroclor 1242-Phenyl Glycidyl
Ether blends.
HB-40 Process Studies
Determine Process ________ :Variables______________________
/ W. H. Howard
The study to develop a continuous HB-40 process has been terminated. The inability to overcome equipment difficulties prevented reaching the original project objectives. A report has been prepared for issuance.
Biphenyl Tubular Pilot Studies
Obtain Desired Biphenyl/Terphenyl Ratio
J. L. Brown
The PR&D Polyphenyl Laboratory is now 98% complete. Installation of the control panels and process line will start 1/2/70 with a tentative installation EDC of 4/1/70.
Low Color Aroclor 5460
_____ _______Develop Alternate Process
G. L. Arnett
Laboratory work and corrosion studies have been completed. Support will be given for a plant demonstration.
Parathion Condensation Reaction StudiesIncreased Yields____________________________________ I. Ransaw
The evaluation of different catalysts in the condensation reaction has been delayed by difficulties in obtaining the necessary chemicals. The study of solvent effects has been initiated and as a result the overall program is essentially on schedule as indicated by the work plan.
DSW 551206 STLCOPCB4089623
D
PLANT LABORATORIES
(Cont'd)
.Company Confidential 11
PROCESS RESEARCH AND DEVELOPMENT
(Cont'd)
Aroclor 5460 Acetone InsolublesQua 1 ity G, L. Arnett
The investigation to determine the process controls necessary to prevent the formation of over-chlorinated terphenyls is approximately 90% complete. Additionally, Aroclors 5420, 5425, and 5430 have been prepared in the laboratory for Organic Research.
Muriatic Acid _______
'QualityI. Ransaw
The development of a quantitative method for the analysis of trace organics in Muriatic Acid is concentrated on two techniques: scanning UV and gas chromatography. A UV instrument is to be made available by the vendor by January 19 with a critical evaluation scheduled for completion by that date. The completion of the evaluation of the chromatographic method is tentatively set for March 13, based on an assumption of the return of that instrument from the factory in operating condition by February 15.
ANALYTICAL AND QUALITY CONTROL
S. 0. Kemp
Complaint Report
Quality
Number
Material
Customer
Reason
17-A-69 18-A-69 19-A-69
Aroclor 5460 Aroclor 5460 Aroclor 5460
Canada Colors to Swift & Co. Plasti-Kote
Thomas Chemicals
Dark Yellow
Development of a gel in their formulation. Whitish Yellow Powder
YTD Quality Complaints/100 Shipments 0.275
Target 0.20
DSW 551207 STLCOPCB4089624
p .Company Confidential 12 COMMUNITY RELATIONS, PERSONNEL, RECRUITING, AND DEVELOPMENT
Community Relations
1. J. C. Landwehr, A. G. Hill and J. C. Price attended the annual meeting of the Coosa-Alabama River Improvement Association, December 17.
2. E. G. Wright attended AIA Air and Water Resources committee meeting in Birmingham, December 11.
3. W. F. Taffee attended AIA Education committee meeting in Birmingham.
4. W. F. Taffee attended hearing on establishment of Birmingham Air Quality Control Region, December 17.
Personnel
1. David Dixon, Chemical Engineering Co-Op from Georgia Tech, will start his first quarter of work on January 5 and will report to W. B. Dunlap.
2. George Jeffrey, Chemical Engineering Co-Op from Georgia Tech, will start his first quarter of work on January 5 and will report to J. C. Price.
3. Elton Allen, Drafting Co-Op from Alabama A&M, will start his first quarter of work on January 26 and will report to R. L. Brewer.
Development
1. R. L. Brewer and G. C. Goodwin completed a short course on "Reinforced Concrete Design" taught by J. C. Price. Others completing the course from outside the department were J. 0. House and M. D. Blair.
2. G. L. Arnett, G. C. Goodwin, W. H. Howard, B. D. Morgan, and G. W. Richey attended Safety Seminar at Holiday Inn, December 9-10 sponsored by Liberty Mutual.
3. J. T. Bell and J. L. Brown visited St. Louis December 11-12 to discuss plans for the Polyphenyl pilot test program.
4. TSD and Lab personnel attended TSD Safety Seminar on Design Safety, Decem ber 16, 1969 held at Alabama Power Company auditorium.
5. Lamar Murphree completed another Olivetti Underwood computer training course in December. TSD graduates were D. A. Self and J. A. Veazey.
Visitors
1. R. S. Yates visited concerning HB-40 Process, December 9-11.
2. D. B. Hosmer visited December 11-12 to review Organic Division product MIPs and TSD-Lab programs for 1970.
3. W. E. Chandler visited the plant December 4-5 to discuss the 1970 Plant Improvement and Utilities budgets and the 1970 Utilities Cost Improvement Program.
4. V. W. Lepard, Kern-Tech Laboratories - Baton Rouge, La December 16.
visited E. G. Wright
DSW 5512ns STLCOPCB4089625
T>
DSW 551209 STLCOPCB4089626
IN MAINTENANCE
FOR CONSTRUCTION
IN MAINTENA'D COMPLETED
NOT CLOSED
r> r t ** - -t r i`.v>0 l.Lj i O
SUSMITTED
iu*/'' CA
APPROVAL
APPROVED PROJECTS IN TSD
company ooni.iuciii.xai. TSD PROJECT SUHMARY
D3W 551
STLCOPCB4089627
ANALYTICAL SAMPLES
LABORATORY ADMINISTRATION
ANALYTICAL MANPOWER
Manpower/sample
$/Manhours
11.00 10.00
9.00 8.00 7.00
1 ----- V--
--\-----
1
1%
i
1 r^\
v
i
* Y ^rV 1.
11
\\ /A
11 L___ i
wi
% Total Plant Operating Cost
2.0 1.5
maaaKgj
1
1.0 r: j
0.5
. , .
--i--
ii
..
--f - p
-naimf*
Overtime %
7 --j--
5 ==l 1
3 paiffiEfcssa
I J cxasi
1 I1
1967 1963 J
F
M/
f\ r*J 1
1 MA
-- i* 1 1 ..'8 % i.. i f\ j
1w
1 `""Tsaa^
i-i j j
H i
a
----- j-- 1 ---- r"3 1 I ___ J___
, ___i-( - "--"1J----- 1"
nsw 551211
1 1 1 .. 1L
STLCOPCB4089628