Document 2qMon93k49qQj5659By9xrdb
PPG INDUSTRIES, INC. INDUSTRIAL CHEMICAL DIVISION LAKE CHARLES, LOUISIANA
No. 91-1145 SffltHBiT H-3
LR- 2412
NOVEMBER 1b, 1983
FAST, S. W.
The Reliability Study and Loss Prevention Review of the Distillation and Storage Areas of the VCM-I Unit (P-757) CONFIDENTIAL
Pi stribution
G. C. Strickler - Abstract Only
1. R. P. Lynch/J. E. Fike
2. J. A. Hart/E. J. Tullier
3- F.
copies)
B. J.MBAMr/R. E. Sanders
5. B. M. WHite
6. Author
7- C. R. West - G.O.
8. Technical Files (Title Page Only)
Key Words Reliability Study Vinyl Chloride Loss Prevention Review Ethylene Dichloride Distillation Vinyl Chloride Storage
Process Safety
SL 012541
Abstract Introduction Discussion Results Conclusions and Recommendations Appendix Table I
1 2 2 6 6 g 10
SL 012542
LR-2412/1
ABSTRACT A Level III Reliability Study and Loss Prevention Review were made on the dis tillation and storage areas of the VCM-I unit. This study and review completes the examination of the VCM-I unit. Using cause-consequence sheet analysis the reliability study did not reveal any undefined potential hazards in terms of fire, explosion, and toxic gas releases. A Loss Prevention Review of the unit was completed and revealed several situa tions that could contribute to hazards. The Loss Prevention Jobs list was also reviewed to update the status of the individual items. Several recommendations were made based on the Loss Prevention Review including such items as installing temperature alarms, additional SRV protection, installa tion and replacement of fireproofing, and repair of cable trays. These items are detailed in the conclusions and recommendations section of this report. An Operations Review Subcommittee meeting will be held soon after this report is issued to determine a course of action for the items from the Loss Prevention Review.
CONFIDENTIAL: Subject to Protective Order of 14th Judicial District Court
No. 91-1145
SL 012543
INTRODUCTION
CONFIDENTIAL:
Subject to Protective Order of 14th Judicial District Court
No. 91-1145
LR-2412/2
A Level III Reliability Study and Loss Prevention Review of the distillation and storage areas of the VCM-I unit were made. These studies complete the examina tion of the VCM-I unit. These studies are a part of the project (P--757) to make Level III Reliability Studies of all the units in Plant B thereby ensuring that there are no unacceptable risks.
DISCUSSION
The Reliability Study started with preparation of cause-consequence sheets cover ing all of the equipment in the VCM-I distillation and storage areas. The equip ment starts downstream of the secondary quench condenser and continues through the distillation train and on to the product storage vessels.
The cause-consequence sheets are a way of systematically examining all of the equipment in terms of process changes (causes) and the results (consequences) of the changes. The Hazard and Operability Study III Guide diagram, developed by ICI, was used to provide a checklist of causes such as high flow, high pressure, low temperature, etc. used to predict consequences.
The cause-consequence sheet analysis did not reveal any previously undefined poten
tial hazards in terms of fire, explosion, and toxic gas releases. Several situations were recognized that would cause operational upsets or result in product quality problems.
In conjunction with the Reliability Study, a Loss Prevention Review was conducted to identify the qualitative conditions that can contribute to hazards. The review was conducted with Carey Brazitis, VCM-I Area Foreman; Jim Wood; Don Rigler; and Wayne Fast. The Loss Prevention Manual was used as a guide for assuring satisfac tory equipment design, personnel safety, and general plant layout.
A Loss Prevention Job (LPJ) list review was also made to update the status of the listed jobs and delete completed jobs.
An Operations Review Subcommittee meeting will be scheduled after this report is issued in order to determine the best course of action for implementing the listed items. The resulting questions and answers from the Loss Prevention Review are 1isted below.
1. Will a reaction result in solids formation which could cause a hazard or a production loss?
The intrusion of water into the distillation system can cause a rapid forma tion of ferric chloride. The ferric chloride will collect on the top trays of the stripper and the product still resulting in an increased pressure drop and reduced flow. This situation can happen over a period of a few hours but is not viewed as a hazard.
2. What problems can be caused by freezing of the process material?
The possibility of freezing EDC in the -40F lean oil cooler or the absorber vent condenser was recognized. An item to install a low temperature alarm
SL 012544
CONFIDENTIAL:
' Subject to Protective Order
of 14th Judicial District Court
LR-2412/3
No. 91-1145
on the lean oil cooler outlet is on the Loss Prevention Job (LPJ 257) list. Freezing of the EDC would result in a loss of lean oil flow to the absorber and contamination of the HC1 vent with organics.
3- Are the columns in the VCM-I unit adequately protected by safety relief devices?
The SRVs on the columns are sized for a fire exposure rating but are in adequate in the event of maximum steam boilup. A project (LPJ 206) to in stall larger SRVs is on hold at this time. This project will be altered if the new quench heat recovery project is installed. The installation of the larger SRVs to handle the maximum boilup case could create another potential hazard in the possible release of large volumes of organic vapors during slight overpressure conditions.
k. Is additional fire protection needed in the form of water sprays, fireproof
coatings, flammable vapor detectors, etc.?
Flammable vapor detectors are strategically located throughout the unit. The pressure vessels are all surrounded by deluge system nozzles. The Albiclad fireproof coatings on structural steel members of the furnace and process areas need to be replaced with Chartek or the new PPG coating. The Albiclad has sloughed off and the portion remaining no longer has the ability to intumesce and is useless as fire protection.
The support structures of the dryers, dryer filters, and neutralizers as well as the main columns and beams in the process unit need new fireproofing.
5. Are critical bearing temperatures monitored?
C/5
The bearings on the Elliott air compressors are not monitored for tempera ture although high oil temperature is alarmed and low oil pressure provides a shutdown. The motor bearing and motor winding temperatures on the York drive motors are alarmed.
6. Can high speed centrifugal units coast to a stop in the event of a power failure without damage to the equipment from lack of lubrication?
cn
The Elliott air compressors and York freon compressors are equipped with auxiliary oil pumps. These auxiliary oil pumps on the York freon compressors are connected to emergency power.
7. Is the rotating equipment critical enough that vibration monitoring alarms and/or shutdown systems should be employed?
The York freon compressors have vibration monitors that read out in the con trol room and also have warning lights.
8. On positive displacement compressors is protection provided against over pressure by restricted or blocked discharge?
The.freon recovery compressor does not have an SRV on the discharge but has a high discharge pressure shutdown. The compressor should be fitted with a safety relief valve.
9. Do all desiccant dryers have backup filters to prevent carryover of desiccant?
Subject to Protective Or der of 14th Judicial District Court
No. 91-1145
LR-2M2/4
The lower intercooler dryer filters have been removed and the upper inter cooler and quench liquor dryers have only one filter each left from an original dual system. The dryers are used infrequently but the lower inter cooler dryer should be equipped with at least one filter.
If a filter is not equipped with a safety relief device, will an unacceptable condition result if the filter overpressures?
A filter would be subjected to overpressure in the event of a fire with the filter blocked in liquid full. These small vessels have generally been ex cluded from SRV protection throughout the Complex due to their small size.
Do all control loops meet failsafe criteria?
A list of the failure position of all of the control valves in the VCM-I plant is needed to make this determination but a list does not exist.
Are all instrument cable trays and electrical control conduit properly pro tected from mechanical damage and exposure to fire?
The cable trays are protected from mechanical damage although some portions are severely corroded and in need of replacement. The cable trays are routed to minimize exposure to fire but no fireproofing is applied. Plant practice does not include fireproofing cable trays.
Is all critical instrumentation on emergency power?
The level indicating controllers on the refrigeration system, the vaporizer shutdown system, the Areas vinyl chloride analyzer, and control room panelboard are on emergency power. The vapor detector systems should be on emer gency power so that they would operate by something other than the heat activated device (HAD) system.
Do all storage tanks containing flammables have dikes or drain to an impound ing basin?
The heavies still bottoms tank is located off of the process pad area. Any spillage from this tank would flow into the storm sewer and not the process sewer. The vinyl sphere areas near VCM and at the docks, along with the day tanks are in diked areas.
Is all fire fighting equipment strategically located?
All fixed water spray systems are adequately engineered and maintained. There are, however, no explosion proof bunkers around the deluge valves nor are they recommended at this time. The marking of the hand held fire extin guisher locations could be improved.
Is there a common venting system which could lead to cross contamination of all vessels?
The venting of the day tanks is to a common system and sometimes results in
HC1 contamination of tanks. This presents a product quality problem and not a hazard.
s<- 012546
CONFIDENTIAL:
8abi.=t to "af5f.ltVreiCt of 14th Judicial Distr
LR-2M2/5
Is the general area lighting sufficient for both normal and emergency operating conditions?
The emergency lighting in the control room in the event of a total power failure is poor. Additional battery powered lanterns are needed.
Are piping systems adequately protected against excessive pressure build up, including hydraulic expansion from exposure to the sun?
Most transfer lines are protected by thermal SRV's but it is possible to block in some lines. The normal procedure is to leave the lines open on one end or the other to equalize the pressure buildup.
Are adequate control measures provided to prevent clouds of flammable vapors from reaching known ignition sources?
The buildings located to the west of the VCM-I plant are of concern in the event of a large spill. The old construction warehouse is now occu pied by the carpenters while some of the other construction buildings are no longer inhabited. Recently a VCM-I unit evacuation alarm was installed in the maintenance building west of the unit but other perimeter buildings do not have any warning devices.
Hydroshields and deluge systems are installed to prevent vapor clouds in the process area from reaching the furnaces.
Are all areas containing flammables properly drained for carrying spilled flammable liquids and water used for fire fighting away from buildings, tanks, and process equipment?
The main process pad drain would not handle the flow of two 1 inch fire hoses during tank washing on the recent outage. The sewer flow capability needs to be evaluated. The 6" drain from the process pad is designed to handle a 225 gpm flow.
Are screens provided in the lines upstream of deluge valves?
Yes, screens are provided on deluge systems to sprinklers but not to the hydroshields. Due to the large orifice size on hydroshields, screens are not needed.
Are adequate safeguards provided to prevent explosions in the incinerator and 36" process area vent headers?
The incinerator vent header has an oxygen analyzer which samples at a point after all the VCM-I plant vents are collected. The analyzer reads from 0 - 10% and is alarmed. Nitrogen purges are added to both the incinerator vent header and the 36" process area vent header to limit air intrusion.
Do all sight glasses have excess flow valves?
The sight glasses do not have ball checks in many cases so the sight glass valves should be closed except during readings. Inaccessibility of the valves is one reason for the difficulty in complying.
SL 012547
CONFIDENTIAL:
ft'O'bysefe
Protective Order
qc 44^ Swdicial District Court Uto* 91-1145
LR-2^12/6
The following items from the LPJ list were discussed and a new status decided.
LPJ 199
Lean Oil Cooler Subject to Design Pressure
LPJ 206
Industrial Engineering needs to provide input on how to correct the problem of operating the lean oil cooler at its design pressure.
Additional SRV for VCH Columns
This project covers the installation of larger SRV's to protect the columns against maximum boilup instead of only fire exposure. Steam
shutoffs were considered as an alternative but SRV sizing standards do not take credit for shutoffs. These larger SRV's will also intro duce a greater hazard of vapor cloud explosion due to the large quan tities of organic vapors released. The installation of the quench heat recovery system will impact on this project and force a redesign of the SRV's. This needs Loss Prevention attention before the project goes any further.
LPJ 173
Fireproof Structural Steel per ORC
LPJ 259 LPJ 166
The replacement and installation of fireproofing is pending a manage ment decision on whether Chartek, the new PPG material, or cementatious coatings should be applied. This decision is pending the outcome of testing of the materials.
Replace Seal Flush Filter with High Rating
A new work order will be written and Loss Prevention will be consulted before this filter purchase is made.
Install Test Taps on Maxon Valves to Determine Leaks
RESULTS
Jim Wood will write the ORC to determine if this project should be pursued.
SL 012548
Since there were no previously undefined potential hazards recognized during the cause-consequence sheet development, no fault tree analysis was done on this study.
Plans for implementing the recommendations of the Loss Prevention Review will be made at the Operations Review Subcommittee meeting to be held after this report is issued.
The Loss Prevention Jobs list items will be acted on as outlined in this report. CONCLUSIONS AND RECOMMENDATIONS
In order to reduce the potential for hazard within the VCM-I distillation and storage areas the following items from the Loss Prevention Review should be implemented. Each item is referrenced to a question number.1
1. Install a low temperature alarm on the lean oil cooler outlet. (0. 2)
CONFIDENTIAL:
>b*<* ^fSistricfCourt 14th JjuucUdicial uisui
LR-2412/7
No. 91-H45
2. Evaluate the installation of the larger SRV's on the distillation columns
in light of the quench liquor heat recovery project. Resolve the question of
SRV sizing for maximum steam boilup in view of the larger SRV release. (Q. 3)
3. Apply fireproofing to the supports of several vessels and to structural
steel with deteriorated fireproofing. (Q. 4)
4. Install an SRV on the discharge of the freon recovery compressor. (Q 8)
5. Install a filter downstream of the lower intercooler dryer. (Q 9)
6. Make a list of the failure mode of all control valves. (Q 11)
7. Repair corroded cable trays. (Q 12)
8. Connect vapor detector systems to emergency power. (Q 13)
9. Improve marking of hand held fire extinguishers. (Q 15)
10. Install additional battery powered lanterns in the control room. (Q, 17)
11. Study the drain capacity of the process pad in light of fire fighting water requirements. (Q 20)
12. Equip sightglass shutoff valves so that they can be shut off except during readings on the routine operator rounds. (Q 23)
The following items from the LPJ list require action.
LPJ 199
Request Industrial Engineering assistance in determining method to have lean oil cooler operate at a pressure lower than design.
LPJ 206
Study the installation of additional overpressure protection of the VCM-I unit columns.
LPJ 173
Determine the best material to use in replacing and applying fireproofing where needed in the VCM-I unit.
LPJ 259
Design the new seal flush filter to withstand the operating pressure of the furnace feed line.
LPJ 166
Determine if test taps are needed for the Maxon valves.
SL 012549
CONFIDENTIAL: 'Subject to Protective Order
14th Judicial District C - No. 9I-H45
LR-2412/8
Date: 1: ' x <' /'_F'j-a Date: ! 2.// C, / ? Date: 12./ /*/ /t 3
SL 012550
LR-2412/9 CONFIDENTIAL; "Subject to Protective Order Q-5t 14th judicial District Court
.... ** i _ 1 1 A K
APPENDIX
SL 012551
CONFIDENTIAL:
**? frotect.ive Order -.Judicial District Court
*a. 5U-JU45
LR--2412/10
TABLE I
VCM-I
LIST OF DISTILLATION AND STORAGE AREAS EQUIPMENT
STUDIED IN THE RELIABILITY/LOSS PREVENTION REVIEW
Absorber Stripper
Absorber column Lower intercoo]er Lower intercooler surge tank Lower intercooler dryer Lower intercooler dryer fi1ters Lower intercooler pumps (2) Upper intercooler Upper intercooler surge tank
Upper intercooler dryer Upper intercooler dryer fi1ters Upper intercooler pumps (2)
90 lean oi1 cooler +34 ean oi1 cool er -40 ean oi1 cool er Lean oil pumps (2)
Absorber vent condenser HC1 stripper
Stripper reboiler
Stripper feed pumps (2) Quench liquor dryer
Quench liquor dryer filters (2)
(2) (2)
Vinyl Product Still
Product Product Product Product Product Product Product Product
still still still still still still still still
reboi1ers (2) condensers (2) vent condenser feed tank reflux tank feed pumps (2) reflux pumps (2)
Heavies Still S EDC Recycle System
EDC recycle cooler EDC reaction tank Heavies still feed tank Heavies still Heavies still reboiler Heavies still condenser Heavies still reflux tank Heavies still feed Pumps (2) Heavies still reflux pumps (2) Waste recovery tank
SL 012552
2
Heavies Still & EDC Recycle System (Cont'd.)
Heavies Heavies Heavies Heavies
still still still still
bottoms pumps (2) stack seal feed filter bottoms filter
Neutralization
Neutralizers (3) Acid product phase separator (Humidifier) Product phase separator (Dehumidifier) Water addition tank Product cooler Product filters (2) Neutralizer drain tank
HC1 Distribution
Entrainment separator HC1 knockout pot No- 1 HC1 heater No. 2 HC1 heater No. 1 HC1 line No. 2 HC1 line VC HC1 scrubber
Product Storage
VCM Daytanks (8) Product transfer pumps (2) Product transfer filter CertainTeed transfer pump Daytank rework pump Storage spheres No. 1, No. 2 & No. 3 Tank car loading pumps (2) Tank car loading filter Dock storage transfer line Ship and barge loading pumps (2) Ship and barge loading filter Vent compressor Vent compressor K.O. pot Day tank rework neutralizer
York Refrigeration System
York refrigeration compressors (2) Compressor motors (2) Gear speed increasers (2) Compressor oil system pumps (2) Freon recovery compressor
LR-2^12/11
SL 012553
-3-
LR-2412/12
Freon Liquid System
Freon condensers (2) High pressure float chamber Freon surge receiver Fourth stage controls Freon pump-out unit Freon storage tank Purge units
Auxiliary Equipment
VC cooling towers Nos. 2 & 3 Cooling tower fans (4) Cooling tower water pumps (4) Condensate collection tank Condensate Pump Steam desuperheater Steam desuperheater condensate pump Coke K.O. drum Seal flush filter - F.E. suppl Seal flush filter - prod, stil feed supply Dopp kettle seal flush filters (2) Rework pump Instrument air blower Elliott air compressors (2) Regeneration air blower on ins rument air dryers Chlorine vaporizer Aftol addition pump Chlorine surge tank Aftol still aid tank
St 012554