Document 2qGxoKrwQNXwnrrOm90vb7JX6
Monsanto
S. Yates - General Offices
February 20, 1968
Minutes of Project Meeting No. 8 Held February 15, 1968 CEA 1800 - Aroclor Expansion - WGK
TO 'Messrs. Present
W. G. Adams D. C. Atkins R. Q. Brown W. J. Burkett R. P. Bartholomew J. A. Fontaine J. Arnold R. C. Herman 0. R. Raymond B. W. Steketee R. P. Stevens J. M. Trigg R. B. West
H. B. Dygert T. A. Jackson (2) O. A. Klingler
REVIEW OF PROJECT PROGRESS
1. Schedules, Control and Procurement
A. Area I - Tank Farm
a. Five storage tanks are enroute from R. D. Cole.
b. Field erected storage tank is to be completed by March 18.
c. Power feeder will be complete by Feb. 29. A tem porary outlet will be provided for Nooter welding machines.
d. Loading dock and tie-in drawings will be issued by Feb. 29.
e. Electrical drawings will be issued week of March 4.
f. Instrument drawings will be issued week of March 11,
9- Insulation schedule will be issued week of March 4. B. Area II - Manufacturing Area
a. Steel quotes are due in house on Feb. 26. Expedit ing will follow the procurement of the steel closely to try to get delivery by May 1.
b. The design of the slab will be complete by March 11
so the drawing can be completed for field construc
tion.
0129725
TOWOLDMONOQ45145
I Minutes of Meeting
-2-
February 20, 1968
c. Mr. Arnold is evaluating the potable water system required for safety showers. He is evaluating a loop system discharging into the existing depart ment break tank versus an underground system.
Completion date 2/29/68
d. Valves and special fittings have to be ordered by March 18.
e. Instrument control valves have to be ordered by March 4. Actual requisition was processed on Feb. 14 to take advantage of a price break.
f. Electrical drawings will be issued on June 30.
g. A fourth absorber unit has been purchased and will be installed in the existing manufacturing area. Mr. Yates will have to develop a layout and engineering flow diagram for this absorber. Due to press of other work, developing of a de sign manual for CEA 1668, this phase will not be completed before April 1.
2. Drafting
A. Area I - Tank Farm
Drawing status completion as of 2/15/68 as reported by Mr. Fontaine:
Layout
90%
Piping Plans
48%
piping Isos
100%
Structural Steel
92%
Structural Concrete
64%
B. Area II - Manufacturing Area
Drawing status completion as of 2/15/68 as reported by Mr. Fontaine:
Layout
62%
Piping Plans
0%
piping Isos
12%
Structural Steel Structural Concrete Architectural
86% 76% 100%
0129726
TOWOLDMONOQ45146
Minutes of Meeting
3
February 20, 1968
3. AC&M Design
a. All equipment should be on order by Feb. 23 except as follows:
Therminol Furnace
By March 6
Remaining Pumps
By Feb. 26
b. Safety shower water systems are being evaluated.
c. Mr. Adams reviewed in some detail the procedure which has been established for drawing approval and final drawing procurement.
We are trying in this project to be more realistic in entering dates on the requisition form. We are also entering a specific date for final drawing issuance. We are requesting a copy of the fabricator's drawing, with our changes transposed to the drawing, to be sent to us two weeks after we return our approval drawing. This should not delay procurement but give us an additional check of the fabrication drawing.
4. El&U Design
a. Electrical design in the 01 Area is 95% complete and drafting is 90% complete. Feeder installation draw ing has been issued to the field.
b. Electrical design in the 02 Area is 20% complete and drafting is 20% complete.
c. No problems in the instrument design or drafting area.
5. PD&PM Design
All PD sheets have been issued to the AC&M group except for the Blow Tank and the Blow Tank Pump. We are waiting for plant results on a plant test before issuing these sheets.
6. Miscellaneous
Mr. Burkett questioned the cost of galvanisation versus painting for the steel. Mr. Atkins has requested an alternate quotation for our regular epoxy system. Spec. 502
Time of Meeting: 1 hour, 20 minutes.
/"
VO 0129727
TOWOLDMONOQ45147
0129728
TOWOLDMONOQ45148