Document 2jv8Eb3vVE48yb85g9pJ4q16R
TO: G. D. Bevis
Monthly Report SUBJECT: October, 1978
FROM: LOCATED AT: DATE :
J. C. Pa I insky Leominster, Ma. November 30, 1978
HIGHLIGHTS 1. ADT has completed all work related to fire alarm system except a curb box reset indicating device. 2. Northeast Sprinkler replaced the cooling tower valve. 3. Special physical monitoring of vinyl chloride has been reinstituted now that the manpower distributed to the EPA project has returned to their normal duties. 4. The trackmobile is repaired and is now being used. Training is 75$ comp Iete. 5. EPA punch list work continues. 6. The Bendix area monitoring system was down for short periods in October. 7. CIS initiated the "start-up" of a new chromatograph in the incinerator area in September, but some problems have been encountered. 8. Hnu status is two of three work and one is out for repair. Two Century O.V.A. units were repaired in October. 9. Four material safety data sheets were submitted to J. R. Latham.
10. The Safety Engineer attended the VCSA meeting in Atlanta; a report was issued.
tl. One of four EPA Compliance Technicians was hired in October. The rest will be available by December I, 1978.
12. Institution of a "leak detection" team and leak follow-up has lowered background levels, but not personnel exposure.
VINYL CHLORIDE CONTROL I. Monitoring Summaries (Personnel)
A. Monthly Monitoring Tests 1. Personnel on Regulated Roster 2. Personnel Tested 3. Personnel Tests 4. 1nva1id Tests 5. Repeat Tests 6. Area Tests 7. Contractor Tests 8. Total Tests
Monthly Averages By General Job Categories 1 . PVC Operators 2. PVC Helpers 3. Dryer Bui 1ding 4. PVC Supv. and Engineers 5. Po1yco 6. Shipping 7. Maintenance 8. Development 9. Oper. and Admin. 10. Total Site
October 189 128 128 ' 7 6 36 0 177
7.0 4.0 0.6 12.4 0.7 0.2 3.5 0. 1 0. 1 3.6
BOR 013609
/
G. D. Bevis Monthly Report - October, November 30, 1978 Page - 2
1973
VINYL CHLORIDE CONTROL (con't) I I. Area Monitoring
A. MAC Room Status I, Bendix Monitoring System a. System #1, monitoring 16 points recorded alarms I isted below: High LeveI AI arms Low Level Alarms % of Time System \ in Alarm b. System jf2, monitoring 16 points recorded a I arms Iisted below: High Level Alarms Low Level Alarms % of Time System #2 in Alarm c. System #3, monitoring 9 points recorded a I arms Iisted below: High Level Alarms Low Level Alarms % of Time System #3 in Alarm d. Total number of alarms for month e. Total alarm duration in minutes f. % of time all points in alarm
2. Bendix Monitoring Equipment Downtime a. System #1 b. System H2 c. System #3 d. Total e. % Time Down
3. Hnu Unit Status a. One unit is out for repair.
4. Monitoring Equipment Expenses a. October - $363.00
5. Air Intake Monitoring a. No. of tests b. Range ppm
6. Special Monitoring a. No. of tests b. Range ppm
October
|I 3 399
12.3
80 298
1.2
IS 62
I .4 970 102,338
5.7 Mi nutes
0 0 0 0 0
0 0
0 0
NOISE CONTROL I. Monitoring Summaries
A. Monthly Monitoring Tests 1 . Personnel Tested
B. Monthly Average Plantwide (8 hr. TWA) 1 . No. 1 nva1id Tests 2. No. Tests 3. Average dBA 4. Range dBA
0
0 0 0 0
BOR 013610
G. D. Bevis Monthly Report - October, November 30, 1978 Page - 3
1978
NOISE CONTROL (con't) I I, Area Monitoring
A. Monthly Monitoring Tests 1. Areas Tested 2. Area Tests
B. Monthly Average by Work Area (8 hr, TWA)
No. Tests
Avq. dBA
1. Bldg. #I-M
0
0
2. Bldg. #70
0
Noise testing will resume in November.
October 0 0
Range dBA 0 0
FUTURE ACTIVITIES I. Projects
A. Vinyl Chloride Exposure 1. Special area testing will continue. 2. Continued education on when and where to use respiratory equipment and enforcement will continue.
B. Noise Surveys I. Both dosimeter and area monitoring will resume on a limited basis in December.
C. Housekeepinq I. -A formal program has been delayed due to EPA involvement.
D. Vinyl Acetate & TCE I. A gas chromatograph will be installed during November to monitor VAc and TCE levels in F-209 and F-210 recovered monomer.
SUMMARY
I. Portions of the data contained in this report is extracted from reports by R. Slocumb, C. Snyder, and K. Landry to J. C. Pal insky and were only summarized for convenience.
JCP/kxs
Q.a tfjLiL,
C. Pal insky U
Safety Engineer
BOR 013611
00
^-4
oft
1
n
BOR 0 1 3 6 1 2
DIVISION
MANAGER'S i JGRESS REPORT EMPLOYEE INJUR^AND ILLNESSES
RECORD TYPE
STATISTIC CONTROL (DIVISION USE ONLY I
Chemical
Thermoplastics
PLANT or BRANCH
Leominster
month_
7
ORIGINAL REVISION
DIVISION CODE
L i i X)ESIS LOCATION CODE
October
1978
___ YEAR g to it
12 A THIS MONTH
THIS YEAR TO DA TE L ._A_J LAST YEAR TO DATE
DATE 1 I
EMPLOYEE NAME
10/10 Jerry Loper 10/3 Ralph Gagne
10/3 Rene E. Maillet
man hours
55.404 55,404 56.010
OCCUPATION
Mechanic Operator Helper
FIRST AID CASES
21 -
16 16
25
TOTAL RECORDABLE
incidents
23 24
-
24
3
3
2_
TOTAL RECORDABLE INCIDENT RATE
10.8 10.8
7.1
RECORDABLE INCIDENTS
TOTAL LOST
WORKDAYS
number of LOST WORKDAY
CASES
27 _ 29 30-32
00
00
26 1
INCLUDE ONLY LOST WORKDAYS AND LOST WORKDAY CASES UNDER COLUMN 9A OF THE LOG. L-100
LOST WORKDAY CASE
RATE
0.0 0.0
CURRENT YEAR GOAL
0.92
DEPARTMENT
BRIE F DESCRIPTION OF ACCIDENT
Laceration and bruise of Maintenance knuckle right hand.
Production
Chemical bum of head, shoulder, eye, and nose.
Shipping
Surgical removal of foreign bodv left eve.
CAUSE OF ACCIDENT
LOST
WORKDAY fatality
CASE l/l
()
Sledgehansner
Plugged charge line. Failure to follow rules.
Wind blowing foreign matt sr.
-
COMMEN TS ON ANY SAEETY TRAINING. JOB ANAL YSES & . COMM/ TTEE ACTIVf TIES
MAIL TO DIVISION SAFE TY OFFICE NO LA TEIYTHA
cc: J. Heller / M, W, Kline ( H. R, Jepsen / N, M, Blackman
TOTAL RECORDABLE INCIDENT RATE
NO. OP RECORDABLE INCIDENTS X 200.000 MANHOURS WORKEO
FORM L-680 (9 '77)
Y OF THE MONTH COVERING THE PRIOR MONTH RESULTS.
MANAGER
October 51, 1978
DATE
LOST WORKDAY
NO, OF LOST WORKDAY CASES X 200.000
CASE RATE
"
MANHOURS WORKED
MANAGER'S PROGRESS REPORT
VEHICLE ACCIDENTS
RECORD TYPE
-STATISTIC CONTROL (DIVISION USE ONLY)
OHIO IN AL REVISION
LJ
DIVISION CODE LSIS LOCATION COOL
dr
DIVISION.
Chemical
nm IPLANTor 'H>c
>p
ssI k
branch Leominster_____ month
October
year ^78
10
11
12
A THIS MONTH YEAR TO DATE
B LAST YEAR TO DATE
NUMBER OF -VEHICLES
33
28 28
____ 35______
vehicle
MLCS -
90,834 90,834
NUMBt H OF CHARGEABLE
ACCIDENTS
40 41
4J
0 0
chargeable
FREQUENCY RATE
" 0.0
o.n
i
!0
NUMBE R OF PREVENTABLE --ACCIDENTS___ 44 - AS
0
88,793
0
0.9
0
CURRENT YEAR
GOAL 1.6
PREVENTABLE FREQUENCY "AH_______
0.0 0.0 0.0
date
EMPLOYEE NAME
VEHICLE ACCIDENTS
OCCUPATION
DESCRIPTION OF ACCIDENT
PREVENTABLE (P)
DOT
NON-
REPORTABLE
PREVENTABLE (NP)
( /)
None
<
-
__1____ .
MAIL TO DIVISION SAFETY OFFICE NO LATER THAN THt 2nd WORKING DAY OF 1 HE MONTH COVERING THE PRIOR MONTH RESULTS.
DRIVER TRAINING
THIS MONTH
NUMBE R Of SMITH SYSTEM INSTRUCTORS
-
NUMHL R OF- SMI HI SVSTEM DRIVE RS
.
NUMfir R or DDC INST RUCTORS
-
NUMBE R OF DDC
drivers
"
YEAR-TO-DATE
COMMENTS ON DEFENSIVE DRIVER TRAINING (e.g., DDC, SMITH SYSTEM, etc.)
~C MANAGER
October 51, 1978
HATE
CHARGEABLE VEHICLE FREQUENCY RATE *
NO. OF CHARGEABLE ACCIOLN IS X 1.000.000
vrmci r mu es
PREVENTABLE VEHICLE FREQUENCY RATE = NO OF PREVENTABLE ACCIDENTS X 1.000.000 VEHICLE MILL S
BOR 013613