Document 2jMk0MnjJRNmEjQbQa3aMMK75
Central Engineering Department
PROGRESS REPORT
CEA NO.
AR NO.
DATE
1800
1800
. December 26, 196 8
PRODUCT
Arocldrs
TITLE
Increase Liquid firoclor Capacity
DISTRIBUTION
CED SECTION MANAGER CED PROJECT MANAGER
R. M. Kountz R. S. YateS
DIVISION
Organic
\ PL \
X
DIVISION REPRESENTATIVE.
H. F. Ray
0. R. Bailey J. M. Depp M. Dmytryszyn R. E. Emling F. W. Enoch J. R. Fair F. J. Holzapfel R. W. Kaltenrieder F. P. LaBelle Russell L. Miller C. L. Parish L. H. Todd
(2)
------
w. J. Burkett R. R. Cook/R. C. Herman R. E. Howard
Organic Division
/
S^'B^gen W/'A. Kuhn fi. L. Minckler <D. A. Olson W. R. Richard R. J. Stratmeyer
Krummrich Plant
D. W. Jackson J. R. McClain J. W. Molloy
SCOPE '
The addition of 40 M lbs./year of Aroclor 1242 capacity in new continuous facilities is planned. This will permit increased production of other Aroclors in the existing batch system. Additional storage tanks for raw materials and finished goods and an extension of an existing tract to supply new tank car loading capacity are included.
DSW 200492
CONFIDENTIAL
INFORMATION
THIS DOCUMENT IS THE PROPERTY OF MONSANTO COMPANT AND THE RECIPIENT IS RESPONSIBLE FOR ITS SAFEKEEPING AND DIS POSITION. IT CONTAINS CONFIDENTIAL INFORMATION WHICH MUST NOT BE REPRODUCED. REVEALED TO UNAUTHORIZED PERSONS OR SENT OUTSIDE THE COMPANY WITHOUT PROPER AUTHORIZATION.
/A \m
CE- 14
STLCOPCB4058556
\
2
ProductAroclors________________________________________
Location W. G. Krummrich Plant
TitleIncrease Aroclor Capacity_________________________________________________
'
Data Tabulated As-Of
Nnvpmher TO. 196R
_ CEANo.
__ AR Ho.
1800
Appropriation Current Estimate Date of Estimate Expended & Committed Spent This Month Scheduled Completion On Schedule?
MS 1 . S00
MS 1,380____________________ Process Design, % Complete
December 18, 1968
Mechanical Design, % Complete
MS 1.380
Construction, % Complete
MS _____ 4^5_______________________ % Expended & Committed
October 15.__1968*_________ 1 Design Manpower
Jn Operation
1 Construction Manpower
Last Month This Mo.
100 100 100 100
99 100 99 i on 2.7 9 . 1 44 ___li
* Represents seven weeks advancement in schedule.
All systems have now been charged with chemicals including the No. 4 Absorber which is being checked out on Aroclor 1260. The second Power Factor Meter has also been placed in operation.
Construction activity is now confined to completing punch list items and these should be finished by December 27.
Quality continues at levels above batch treated material and the Porocel Column System is giving a higher clarity Aroclor than pre viously produced.
(The project is in the process of being closed with an underrun of $120,000 and this issue terminates monthly progress reports for this
project.
'