Document 2jMk0MnjJRNmEjQbQa3aMMK75

Central Engineering Department PROGRESS REPORT CEA NO. AR NO. DATE 1800 1800 . December 26, 196 8 PRODUCT Arocldrs TITLE Increase Liquid firoclor Capacity DISTRIBUTION CED SECTION MANAGER CED PROJECT MANAGER R. M. Kountz R. S. YateS DIVISION Organic \ PL \ X DIVISION REPRESENTATIVE. H. F. Ray 0. R. Bailey J. M. Depp M. Dmytryszyn R. E. Emling F. W. Enoch J. R. Fair F. J. Holzapfel R. W. Kaltenrieder F. P. LaBelle Russell L. Miller C. L. Parish L. H. Todd (2) ------ w. J. Burkett R. R. Cook/R. C. Herman R. E. Howard Organic Division / S^'B^gen W/'A. Kuhn fi. L. Minckler <D. A. Olson W. R. Richard R. J. Stratmeyer Krummrich Plant D. W. Jackson J. R. McClain J. W. Molloy SCOPE ' The addition of 40 M lbs./year of Aroclor 1242 capacity in new continuous facilities is planned. This will permit increased production of other Aroclors in the existing batch system. Additional storage tanks for raw materials and finished goods and an extension of an existing tract to supply new tank car loading capacity are included. DSW 200492 CONFIDENTIAL INFORMATION THIS DOCUMENT IS THE PROPERTY OF MONSANTO COMPANT AND THE RECIPIENT IS RESPONSIBLE FOR ITS SAFEKEEPING AND DIS POSITION. IT CONTAINS CONFIDENTIAL INFORMATION WHICH MUST NOT BE REPRODUCED. REVEALED TO UNAUTHORIZED PERSONS OR SENT OUTSIDE THE COMPANY WITHOUT PROPER AUTHORIZATION. /A \m CE- 14 STLCOPCB4058556 \ 2 ProductAroclors________________________________________ Location W. G. Krummrich Plant TitleIncrease Aroclor Capacity_________________________________________________ ' Data Tabulated As-Of Nnvpmher TO. 196R _ CEANo. __ AR Ho. 1800 Appropriation Current Estimate Date of Estimate Expended & Committed Spent This Month Scheduled Completion On Schedule? MS 1 . S00 MS 1,380____________________ Process Design, % Complete December 18, 1968 Mechanical Design, % Complete MS 1.380 Construction, % Complete MS _____ 4^5_______________________ % Expended & Committed October 15.__1968*_________ 1 Design Manpower Jn Operation 1 Construction Manpower Last Month This Mo. 100 100 100 100 99 100 99 i on 2.7 9 . 1 44 ___li * Represents seven weeks advancement in schedule. All systems have now been charged with chemicals including the No. 4 Absorber which is being checked out on Aroclor 1260. The second Power Factor Meter has also been placed in operation. Construction activity is now confined to completing punch list items and these should be finished by December 27. Quality continues at levels above batch treated material and the Porocel Column System is giving a higher clarity Aroclor than pre viously produced. (The project is in the process of being closed with an underrun of $120,000 and this issue terminates monthly progress reports for this project. ' vo OSW 200493 STLCOPCB4058557