Document 2jBxzj6wx8vGL6qr6LNnN4mJg
-0072 - T
NEMOSftHDUM
H. J. Borgen
TROW
G. Libero
SUBJECT
Shipyard Period EXXON NEW ORLEANS 5/25/77 - 6/18/77
DATE
July 8, 1977
FILE NO.
Vessel arrived at Newport News Shipyard on 5/25/77 to commence shipyard repairs, dry docking, USCG Inspection for Certification, ABS Special Survey and West Coast Modifi cations. Vessel sailed 6/18/77.
Repairs and all other worlc was performed as per shipyard specs (enclosure #1) with the following comments:
Item Numbers
1-5 All OK 6 Vessel in drydock 1 haul day and 8 lay days as per enclosure #2.
7-8 All OK
9 Hull rusted and pitted undemater. Heavy sand sweep and two coats of coal tar epoxy applied in addition to other paint schedule.
10 Six out of ^Eight capac anodes found not working on drydock, all repaired, anode in #6P disconnected due to change of service of 6P into fuel oil tank, anode to be relocated next drydocking into segregated ballast tank.
11 All sea valves examined and repaired as necessary.
12 All clapper valves examined and repaired as necessary.
13-14 Renewed outer Waukesha seal ring assembly and after liner. Final readings:
Top - 110.5 mm.
Bottom - 109.6 mm.
15-16 Anchors ranged and. gauged - all OK, see enclosure for readings.
17 Renewedrudder pintlebushing withsolid
18-20 All OK 21 Cancel
22-32 All OK 33 Tested #1-8 mooring winch brakes,all held at least 55,000 lbs.
34-36 37 See enclosure forpump casing audio gauge readings.
38-50 All OK
51 Cancel
EXX-MOR-008269
Shipyard Period EXXON NEW ORLEANS 5/25/77 - 6/18/77 Page two
52-56 All OK 57 See enclosed life raft inspection certificates. 59-70 All OK 71 Cancel 72 Hydrostatically tested boiler and main steam lines for USCG. 73 OK 74 See enclosed copy of all main unit clearance readings 75-81 All OK 82-84 Cancel 85-92 All OK 93 Cancel 94-101 All OK 102-103 Cancel 104-123 All OK 124-150 All West Coast Modifications completed as per specs and tested -
See enclosed copy of 835 pertaining to some items. 151 Repaired all areas of fwd deep tanks to TJSCG and ABS satisfaction. 152 Repaired all areas of #6P and 6S deep tanks to ABS and USCG satisfaction. 153 #7R and S ballast tanks repaired to USCG and ABS satisfaction1. 154-157 All OK 158 Cancel 159-164 All OK 165 Cancel 166-172 All OK 173 3P, 3S, and 3C--all repairs performed to ABSand USCG satisfaction, made
modifications to webs, web brackets, and after bulkhead horizontal stringers as per Mr. Boban of Exxon International recommendations. See signed off 835' 174-175 All OK 176 2PA, 2SA, and 2C--all repairs performed to ABS and USCG satisfaction. Made modifications to webs, web brackets and after bulkhead horizontal stringers as per Mr. Bonban of Exxon International recommendations.
EXX-MOR-008270
Shipyard Period. EXXON NEW ORLEANS 5/25/77 - 6/18/77 Page three
177-179 180
181
All OK
Made repairs in 1C to USCG and ABS satisfaction--see enclosed signed off 835.
Repaired all tank cracks to USCG and ABS satisfaction.
182-183 184
All OK
Modified fwd. end of 6P tank for F. 0., all work tested to ABS and USCG satisfaction.
185-207 173-A
All OK
Cropped out and installed six spigot patches in 3P and 3S tanks at "J" strake in way of fatigued areas and leaking areas, see enclosed audio gauge reading, also see enclosed "signed off" 835 pertaining to that area.
Reference item 173-A. Shell plate in 3P and 3S
Tested shell plate at connection of web to shell plate using magnetic particle test at the following locations in "j" strake:
3P and 3S - Webs 78, 79, 80, 81, at longitudinals L-15, L-17 and L-17
Installed welded spigot plug, approx. 8" in diameter, at the following locations:
3P - Frame 81, L-16 Frame 79, L-16 and L-17 Frame 78, L-16 and L-17
3S - Frame 79, L-16
214-218 All OK
219
220-248 220-248
Controller for new stbd crane not acceptable by USCG - see enclosed 835 and letter. Mike Bennett informed. All All OK
Additional Notes
1) USCG inspection for certification completed, see enclosed new 835, see enclosed signed off 835*s, Safety Construction Certificate renewed Temporary certificate issued, record card endorsed.
2) ABS Special Survey completed with no outstanding requirements,see enclosed list of survey items completed.
3) Provide Mike Bennett with copy of 835 pertaining to West Coast Modifications and discussed same with him.
EXX-MOR-008271
Shipyard Period EXXON NEW ORLEANS 5/25/77 - 6/18/77 Page four
4) Prepared a list of spare parts and their disposition, see enclosure (20), copy to Larry Hanft.
List of Enclosures 1) Shipyard specs 2) Anchor Chain Audio Gauge Readings 3) Generator Residue Analyses Report 4) Fwd Chain Locker Audio Gauge Readings 5) Cargo Pump Casing Audio Gauge Readings 6) Megger Readings 7) Audio Gauge Reading - Web 54 ~ 6P 8) Generator Rotor Balance 9) Liferaft Certificates 10) CO2 Certificates 11) Audio Gauge Readings "J" Strake at 3P and 3S 12) Foam Sample Results 13) Main Unit and Machinery Readings 14) "Signed off" USCG 835's 15) Newly issued USCG 835's with attached letter 16) ABS Special Survey Summary 17) ABS - Hull Audio Gauge Readings 18) Drydock. Block Plan 19) Forced Draft Fan Balance Data 20) Disposition of Spare Parts
GL:jf cc: L. A. Hanft
E. J. Worrel
EXX-MOR-008272