Document 2j8ZwZoR6dKrdm11e79KaOa2R
This letter is in response to your letter to Mr. Don R. Goodwin of April 16, 1973, regarding incineration costs at vinyl chloride monomer plants. Since your letter addresses a subject that falls within my area of responsibility, Mr. Goodwin has requested that I respond to you.
I have attached a copy of the specifications that our'contractor used to develop his estimate of incineration, co&ts-for ;a 700 mill ion lb/yr. vinyl, chloride monomer plant as well as one copy of the. final incinerator capital cost estimate of $921,750. In addition, we have attempted to reconcile the differences between our estimate and Shell's estimate by trying to put both estimates on a comparable basis. While it has not been possible to precisely reconcile all cost differences, it does appear that the major area where differences exist is in the "other cost" section - engineering, field changes, and start-up costs specifically. While differences in the areas of purchased equipment and installation also exist, it would appear that these differences might partially be explained by the inclusion of an acid recovery system in the Shell estimate. The'EPA estimate included neutralization of the acid, not recovery.
Whereas we cannot dispute the fact that Shell has actually expended the amount in question - $1,768,000 - we still believe that this amount would not necessarily be duplicated at some other installation. In particular, we believe the amounts expended for engineering, field changes, and start-up costs appear to be extraordinary.
Another area in which differences exist is in the escalation of the original capital expenditure to a value representative of the EPA model plant. The Shell methodology is to take the original value of $1,768,000, multiply it by a factor of 1.67 to account for inflation.
see
3-0646
l 2- add $260,000 for an acid mist eliminator^-find then multiply the sum by a factor of 1.4 to account for the increased gas volume that must be treated. This methodology results in a total capital cost estimate of $4,500,000. EPA, on the other hand, believes that an inflation factor of 1.29 is more appropriate based upon the values of the CE Index in January 1973, and January 1975. Also, EPA does not believe that an acid mist eliminator of the size included in the Shell estimate would be required. EPA has included a mist eliminator in its original equipment estimate as is noted on the attached reconciliatory sheet. Finally, we believe that a volume scaling factor of 1.15 is the appropriate factor to use. This factor is based upon scaling the original gas volume at the burner exit of 60,000 SCFM to 73,000 SCFM at the 0.7 power. The EPA methodology, then, gives a value of $2,600,000 as opposed to the Shell estimate of $4,500,000. We realize that even this value, however, is considerably in excess of the EPA capital estimate of $922,000. Whereas we believe that part of the discrepancy is due to factors mentioned before acid recovery cost, engineering, field changes, and start-up costs - we feel that more analysis in this area is needed. I hope that we will be able to discuss these matters with you and other Shell employees in order to obtain mutually agreeable cost estimates for control of emissions at vinyl/chloride'monomer' plants'.
5inc^raly yours
\Jk \ JQi
John R. O'Connor, Chief Standards and Cost Analysis Branch Strategies and Air Standards Division
Enclosure
see
;-0647
The thermal incineration systems specified for VCM control' under this task consist of a thermal incinerator and a caustic scrubber system to remove from the incinerator exhaust gases the HC1 made in the incinerator. Cost information for these systems was developed from a conceptual design basis of an 1800F incin eration temperature and a 2 second residence time to achieve. 99% removal of VCM. This is felt to be a conservative basis but it is not based upon operating data.
The installed cost data presented herein is of necessity based on a model situation and must be adjusted by the reader to meet his particular situation. To help in this adjustment, various cost bases'used in this study are.listed below:
1) 5% caustic solution 'is .'available within . 50 feet of unit * battery limits.
2) Cost of caustic is 35$/8 which includes delivery, unloading and surcharge from existing facilities.
3) An adequate supply of natural gas auxiliary fuel is available at $2.00/MM Btu.
4) Caustic scrubber effluent will be processed in existing treatment facilities. Existing chemical sewer tie-in is within 25 feet.
5) The equipment will be placed on a concrete pad sized
for equipment only. Soil bearing pressure is 2000 .psf.
Backfill, piling, etc., is not included.
* ,*
* * *
-:' .
' - see
3-0648
2-" -
6) Area classification will be Class I, Group D, Division. II. Motors wxlM be TEFC. Arcing controls will be NEMA 7, nonarcing controls will be NEMAt. 4^, control cabinets will be pressurized and purged NEMA 4. Existing electrical power supply 440,220 and 110 volts is adequate.
7) Incinerator will be designed for the 2 seconds residence time at 1800F. Fuel consumption will be based on anti cipated operating temperature of 1600F but system will be capable of 1800F operating temperature. Air will be added in excess of that required for fuel combustion to assure a 1% 02 concentration in incinerator outlet gases, for VCM balanced operation.
8) -Scrubber presaturator'will be designed for.0.3 sec.resi dence time. Material of construction will be suitable for service. Process water will be used for cooling. Fire water is available for backup emergency cooling.
9) The scrubber'will be designed for 95%+ HC1 removal efficiency. Caustic scrubber effluent will go directly ' to chemical sewer on scrubber sump level control.
10) Pumps will be spared and material.of constructions will be C.S. for caustic pump and epoxy FRP for scrubber liquor.
11) In the absence of specific available experience, operating labor cost estimates will be projected from general
. incinerator and scrubber knowledge.
5
''
' SCC 3-0649
-512) Process vent Stream conditions supplied to the control o system are suJfferized in cost data tables. 13) Maintenance and repairs will be 'figured at 53 of fixed
capital investment. 14) Stack will discharge at 100' above grade
Q
see
3-0650
4 >
ESTIMATED CAPITAL'COST-DATA * (COSTS IN DOLLARSr
Thermal incinerator for balanced VINYL CHLORIDE MONOMER PLANT (700 MM Ib/yr) (OXYCHLORINATION, "LIGHTENDS," and vinyl finishing COLUMN VENTS)
Effluent Gas Flow ACFM F SCFM
Effluent Contaminant Loading (ppm) VCM
Ib/hr VCM
12,000 70
12,000
1,625 189
Cleaned Gas Flow ACFM F SCFM
Cleaned Gas Contaminant Loading (ppm) VCM
Ib/hr VCM Cleaning Efficiency, % * ..
36,000 175
30,000
2.17 1.89
99
(1) Gas Cleaning Device Cost
(2) Auxiliaries Cost (a) Fan(s) (b) Pump(s) (c) Damper(s) (d) Condition, (Incl. Inst.) Equipment (e) Dust Disposal Equipment
(3) Installation Cost
(a) Engineering
(b) Foundations
& Support
Ductwork & Stack - 100' above
Electrical (Incl. Inst.)
Piping
Insulation
Painting
Supervision
.. * -
Startup
PerformanceTest
Other
(4) Total Cost
*99% for VCM, 95% for HC1
.. "
245,000
73,500 46,500 9,000 9,000 9,000
603,250 71,250 285,000
28,50Q
38,000. 38,000 61,750 23,750
9,500. 9*500 9,500 28,500
921 ,750
SCC
3--'0651
ANNUAL OPERATING COST DATA (COSTS IN S/YEAgJ
THERMAL INCINERATOR FOR BALANCED VINYL CHLORIDE MONOMER PLANT (700 MM lb/yr) (OXYCHLORINATION, LIGHT ENDS, AND VINYL FINISHING COLUMN VENTS)
Operatinq Cost Item
Unit Cost
Operating Factor, Hr/Year
8,000
Operating Labor (if any) Operator
Total Operating Labor
$6/Hr $8/Hr
$ 12,600 8,400
21,000
Maintenance
Labor Materials Total Maintenance & Replacement Parts
$' 46,100
Rep!acement Parts
Total Replacement Parts
Utilities Electric Power Fuel Water (Process) Water (Cooling)
Caustic Soda Total Utilities
$.03/Kwhr $2/MM Btu $.25/Mgal $.05/Mgal $.35/1b
$ 34,200 592,000 8,000
0 309,900
944,100
Total Direct Cost
$1,011,200
Annualized Capital Charges
113,200
Total Annualized Cost
$1,184,400
see
3-0652 >
COMPARISON OF INCINERATOR CAPITAL COSTS - SHELL vs. tr*
.. * . .
. ..___ . . ..
PURCHASED EQUIPMENT
1. Incinerator
2. Blower & Driver
3. FRP Equipment & Duct Work
incl. column
4. Exchanger
5. Pumps
6. Filters
7. Tanks (less lining)
8. Instruments
9. Electrical
10. FRP Piping
11. Valves
12. Structural Steel
13. Column Packing
14. Piping Labels
15. Freight
.
16. Conditioning Equipment0
17. Dampers
Subtotal
CONSTRUCTION CONTRACTS
1. Piling. & Foundations 2. Mechanical & Piping 3. Instrumentation 4. Electrical
Subtotal
OTHER COSTS
.* - Shell
^
(Norco," La.)
Mi
113
U3
67
10 19
1 25 63 15 33 36 62
1 1 6 -- --
495
170 270 ~
76 60
576
- EPA ... Estimate1
'M$
245a 46.5
(Incl. in Item B2)
None 9.0
None --
(Incl. in Item B3) (Incl. in Item B4) (Incl. in Item B2)
None (Incl. in Item B1) (Incl. in Item A1)
None 9 9
318.5
285d 152* (Incl. in Item B4)
38
475
1. Engineering (Contractor) 2. Sales Tax 3. Shell Engineering 4. Field Changes 5. Start-up Costs 6. Supervision 7. Other (Contingencies, etc.)
Subtotal
229 71.3 20 None
102 (Incl. in Item Cl) 195 None
151 19e '
-- 9.5 -- 28.5
697 128.3
GRAND TOTAL
$1 ,768M
$922M
aIpcludes burner and burner controls, combustion chamber, and scrubber (includes mist elim
inator). Cost is FOB vendor*
^Includes oost ..of.qufencher and quencher controls.
^Includes cost of foundations and support and Tabor to install them.-
\
includes cost of: duct work arid stack (100'), piping, insulation-, and
painting materials and labor.
includes cost of: startup and performance test.
.
see
3-0653