Document 2RnzKwobZeQx5gy7r7L4mM22p
R. E. Howard - General Offices
August 4, 1967 Approval for Engineering and
Equipment Purchase CEA 1430 - Aroclor Expansion
^H. C. Carder J' Holzapfel
J. Creacs
In our review of the Aroclor expansion on July 28 you requested that CED proceed with definitive engineering and with the pur chase of long delivery and high priority equipment in advance of submitting the appropriation request.
Specifically, we recommend that the solid Aroclor flaker
($30,000), 5 aluminum tanks for Krummrich ($50,000) and 11
aluminum tanks for Anniston ($100,000) be placed on order. By
combining all the aluminvmi tankage we should be able to nego
tiate a better price. Cancellation charges for the equipment
3 months after commitment are estimated to be $80-90,000.
Engineering charges which will accrue by that time will bring
the total up to the General Manager's level of approval author
ity.
.
We, therefore, request that General Manager's approval for $100,000 be granted to authorize definitive engineering and equipment purchase. The General Manager's signature on this memo will be CEO's approval to proceed. Please return one signed copy to me.
vo Approved General Manager
R. E. Howard
0015803
TOWOLDMONOQ43958