Document 2Rbgzm92MRdDNDB1J8Z7z43rr
CEA 1430 & 1800 Date: August 28, 1967
TABLE OF CONTENTS
1.1 Title
1.2 Summa ry
1.3 Process Technology
1.31 1.32 1.33 1.34 1.35
Process Description Raw Materials Products and By-Products Waste Streams Personnel, Property andPublic Hazard
1.4 Manufacturing Facilities
1.41 1.42 1.43
1.44 1.45
1.46
Description Design Capacity Flexibility Requirements
Future Expansion Physical Appearance
Storage and ShippingRequirements
1.5 Utilities and Services
1.51 Utility and service Requirements 1.52 Utility and Service Facilities
Page Ho.
1
1
2
2 3 5 7 8
9
9 13 16 17 18 19
20
20 20
APPENDICES A. Equipment Flow Sheet B. Suggested Equipment Layout C. Equipment List D. Scope of Work, Anniston Storage Tank Farm E. Scope of Work, Anniston Drumming and Flaking F. Scope of Work, WGK, New 40M Pound Plant 0. Scope of Work, WGK, Storage Tank Farm H. Preliminary schedule I. Project Loss Prevention Report
(9 pages) (2 pages) (13 pages) (9 pages) (6 pages) (11 pages) (7 pages) (2 pages) (5 pages)
MONS 036254
CEA 1430 & 1800
Date: August 28, By: R. S. Yates Page 1
1967
1.1 TITLE
Aroclors - Increase Aroclor Capacity - Organic Division
At Anniston Plant - CEA 1430
At WGK Plant
- CEA 1800
1.2 SUMMARY
`
The objectives of this project are to,
a) Provide adequate finished goods storage facilities at Anniston and WGK to assure a minimum inventory of the various Aroclors and Aroclor blends so that bulk shipments can be made on demand.
b) Provide at Anniston for blending and drumming of
the several Aroclors with other components without interferring with primary production facilities.
c) Minimize potential for cross contamination of products.
d) Provide loading facilities for tank trucks and
tank cars and unloading facilities for raw mater ials in tank cars.
e) Provide additional raw material storage at WGK for biphenyl and at Anniston for TCB and TTCB.
f) Provide at Anniston new expanded facilities for flaking and bagging biphenyl and solid Aroclors.
g) Provide new facilities at WGK to increase plant capacity from 29.5M lbs./year to 69.5M lbs./year.
h) Provide an overall production capacity for liquid Aroclors of up to 30% more than indicated in the latest Sales forecasts.
i) Provide for an orderly expansion of the WGK and Anniston Aroclor facilities.
Addition of these facilities will result in capacity increases over the present standard'1' capacity as follows:
MONS 036255
CEA 1430 & 1800
Date: August 28, 1967 page 2
At WGK,
Liquid 40.0M lbs./year
At Anniston, Liquid 5.7M lbs./year
Solid 1.0M lbs./year
(1) Note - Standard capacities at present are:
At WGK,
Liquid 29.5M lbs./year
At Anniston, Liquid 48.OH lbs./year
. Solid 10.02M lbs./year
The installation at Anniston will include finished storage and blending tanks, two flakers for solid
Aroclors and biphenyl, a drumming station, tank car spur and loading facilities and bagging station for solid Aroclors and biphenyl.
The installation at WGK will include a new continuous chlorination line, blow tank, intermediate storage, distillation equipment, continuous clay treatment facilities, finished storage tanks, and a biphenyl storage tank with additional rail spur and unloading docks.
Desired completion dates:
Tank farm at WGK Tank farm at Anniston Flaking facilities at Anniston New production facilities at WGK
July 1, 1968 August 1, 1968 September 1, 1968 December 1, 1968
1.3 PROCESS TECHNOLOGY
'
1.31 Process Description
Aroclors are the reaction products formed by the chlorination of biphenyl and/or terphenyls using an iron catalyst. The by-product HCl gas produced is absorbed in water to produce muriatic acid.
Crude Aroclors are produced in chlorinator reaction vessels, air blown and distilled. Liquid Aroclors are earth treated, filtered and loaded for shipment. Solid Aroclors are drummed, flaked or flaked and milled and packaged for shipment.
Distillation residues are discarded as waste or sold as Montars.
A numerical system of nomenclature is used for iden tifying the various Aroclors.
MONS 036256
1.32
itwu te XOUU Date: August 20, 1967 Page 3
Product yields are calculated on both chlorine and biphenyl and are different for each plant and for each Aroclor produced. They are recorded in the respective plant cost standards.
Process documents:
"Standard Operating Instructions for Aroclors Anniston Plant" - April 1966 - M. J. Williams
"Standard Manufacturing Process for Aroclors Anniston Plant" -September 1966 - M. J. Williams
"Process Description for the Manufacture of Aroclors - Department 246 - WGK Plant" - October 1966 D. E. Harris
"Process Description for the Manufacture of Pyranols and Inerteens - Department A246 - WGK Plant" October 1966 - D. E. Harris
"Standard Manufacturing Process for Pydraul A-200 Department B-246 - WGK Plant" - October 1966 D. E. Harris
"Operating Instructions - Aroclor and Pyranols Departments 246 and A246 - WGK Plant" - August 1966 - V. Brawley
"Final Report on the Continuous Chlorination of Biphenyl" - June 4, 1957 - R. A. Simone
"Tentative Process for Continuous Chlorination of Biphenyl" - March 23, 1956 - R. A. Simone
"Final Report on the Continuous Chlorination of Aroclors - Plant Demonstration" - May 7, 1958 R. A. Simone
Raw Materials
1.321 Specifications
Reference is made to the respective standard process manuals for raw material specifications. Raw materials at Anniston, for this project, are the Aroclors and additives used in blends and mixes and at the flakers. Raw materials at WGK are the materials used for the manufac ture of Aroclors. A list of materials follows:
MOWS 036257
CEA 1430 & 1800
Dates August 28, 1967 Page 4
Plant
WGK (246)
Material Code
Date
Material
82601 33500 38800
19409 43099
81059
12/8/64
1/7/66
7/21/66 1/21/66 2/18/65 6/29/66
Diphenyl Ferric Chloride, Anhydride Lime, Hydrated Attapulgus Earth 200/UP Nitrogen Gas Chlorine, Liquid
Anniston (27)
82612 81102 82641 82613 82613 82614 82614 82615 36100 60200 58500
61_320
64010
6/17/66 1/10/64 7/5/64 6/28/64 7/15/64
2/7/62 7/15/64 3/2/66 5/26/66
6/3/65 8/29/63
12/2- 3/63
12/18/64
Aroclor 1242 Electrical Grade Aroclor 1248 Electrical Grade
Aroclor 1248 Non-Electrical Grade Aroclor 1254 Electrical Grade Aroclor 1254 Non-Electrical Grade
Aroclor 1260 Electrical Grade Aroclor 1260 Non-Electrical Grade Aroclor 1262
Glycidyl Phenyl Ether (1) Trichlorobenzene (1) Tetrachlorobenzene (1) Epoxide 201
Toluene Xylene
(1) WGK Specification
1.322 Sources
WGK
Biphenyl
Received from the Anniston Plant in 20,000 gallon unlined steel, steam
heated tank cars. Transferred to an existing 25,000 gallon storage tank.
Chlorine
Received direct from WGK's Department 232 in a 4" transfer line. This line is being replaced by a 6" transfer line in the third quarter of 1967.
Ferric Chloride
Received from the warehouse in 2 lb. glass containers.
Lime, Hydrated
Received from the warehouse in 100 lb. bags.
HONS 036258
1.33
CEA 1430 & 1800 Date: August 28, 1967 Page 5
. Attapulqus Earth
Received from the warehouse in 50 lb. bags.
nitrogen Gas
Supplied by a bulk station located in the tank farm area.
Anniston
Aroclors are transferred by pipeline direct from department to storage and from storage tanks to mix tanks, to drumming station and to flakers.
Glvcidyl Phenyl Ether
Received from the warehouse in 55 gallon drums.
Trichlorobenzene
Received from Hooker Chemical Company in 8,000 gallon steel tank cars.
Tetrachlorobenzene
Received from Hooker Chemical in 8,000 gallon tank cars.
Epoxide 221
Received from warehouse in 55 gallon drums.
Toluene
Received from warehouse in 55 gallon drums.
Xvlene
Received from warehouse in 55 gallon drums.
Products and By-Products
1.331 Quality Considerations
Marketing stresses that quality protection is the most effective means of protecting our present sales position of electrical grade Aroclors. Plant studies have shown that the use of aluminum tanks and aluminum transfer piping systems coupled with inert blanking of in-process and finished goods storage tanks will give us maximum protection.
HONS 036259
L.J&M 1**JU 6, J.OUU
Date: August 28, 1967 Page 6
1 1.3.32 Specifications
Reference is made to the respective standard
1
process manuals for finished goods specifi cations. Finished products at Anniston, for
this project, are the completed blends from
l'1
mix tanks and solids from the flakers. At WGK, finished products, are the liquid
I ' Aroclors and Montars. A list of products follows:
1
Product
Product
Code
Code
1 Anniston Date
WGK
Date
Product
82611
10/28/63 8115
4/7/64 Aroclor 1232
1
82612 82612
6/17/66 7/15/64
81101 81101
6/17/66 Aroclor 1242 Electrical Grade 7/15/64 Aroclor 1242 Non-Electrical Grade
81102
1/10/64 81102 1/10/64 Aroclor 1248 Electrical Grade
82641
7/15/64 81102 7/15/64 Aroclor 1248 Non-Electrical Grade
1
82613
6/28/65 81103 6/28/65 Aroclor 1254 Electrical Grade
ti
82613
7/15/64 81103 7/15/64 Aroclor 1254 Non-Electrical Grade
82614
5/25/66 81105 5/25/66 Aroclor 1260 Electrical Grade
1
82614
6/15/64 81105 6/15/64 Aroclor 1260 Non-Electrical Grade
82_6_1S ---
3/2/66 7/15/64
7/15/64
81107 82868
82868
3/2/66 Aroclor 1262 Non-Electrical Grade 7/15/64 Montars 1, 2
7/15/64 Montars 314
1 a
82622 82621
3/11/66 3/15/66
Aroclor 5460 Aroclor 5442
82620
3/11/66
Aroclor 5060
3
82619
3/11/66
Aroclor 4465
82618
3/11/66
Aroclor 2565
82616
3/11/66
Aroclor 1268
1
82601
7/8/65
82649
4/18/66
Biphenyl Inerteen PPO
82658
4/18/66
A13B3B
1
82681 82659
5/3/67 3/11/66
Inerteen 54201 KA Aroclor 1260 - 10% Toluene
82661
3/15/66
Aroclor 1262 - 1094 Toluene
82685
3/9/66
Therminol FRO
1
82664
4/17/58
Aroclor 1254 - 1094 Toluene
1.333 Packaging and Shipping
1 i
Liquid Aroclors
At both Anniston and WGK, liquid Aroclors are shipped in the following manner:
Tank Trucks 1
Size - 4,000 gallon
Materials of Construction - All electrical grade Aroclors are loaded into SS trailers. Non-electrical grade Aroclors may be shipped in steel trailer tanks.
HONS 036260
CEA 1430 & 1800 Date: August 28, 1967 ' Page 7
Tank Cars Si2e - 4,000 or 8,000 gallon
Materials of Construction - All electrical grade Aroclors are loaded into solid aluminum cars or in tin, zinc or aluminum spray-lined cars. Non-electrical grade Aroclors may be shipped in steel cars.
Drums and cars Size - 5, 30 or 55 gallon
Materials of Construction - Lacquer-lined containers.
Solid Aroclors
At Anniston, solid Aroclors are packaged in 5 and 40 gallon galvanized steel drums as a solid and in 41 gallon fibre drums as flakes. Biphenyl and Aroclor 5460 are packaged in bags as follows (major part of the production):
Aroclor 5460
Net weight - 100 lbs., St. Regis No. PCBG-32A.
Size - 10" X 6" X 34" with a 5" valve.
Type - Sewn Valve (SV).
Biphenyl
Net weight - 50 lbs., St. Regis No. PCBG-145A.
Size - 16-3/4" X 5" X 33" with 5-1/2" valve.
Type - Sewn Valve (SV).
HB-40
At Anniston, HB-40 is packaged in 5 and 55 gallon steel drums.
1.34 Waste Streams WGK 1,250 lbs./day of HC1 gas absorbed in a 50 GPM water stream (0.21%) will be discharged from the continuous blow tank into the plant sewer. Other process losses are of a minor nature.
HONS 036261
CEA 1430 & 1800
Date: August 28, 1967 . Page 8
Anniston
No change is expected in waste discharges as a result of this project. A dust collector will be installed to control Aroclor dusts from the milling operation . of Aroclor 1268.
1.3S Personnel, Property and Public Hazards
Chlorine Gas
'
Causes eye, skin and mucous membrane irritation. In strong concentrations canister gas masks, Scott Air Paks, or oxygen breathing apparatus are required.
Biphenyl
Solid at normal temperatures. Fumes are toxic over a prolonged period of exposure. The flash point is 235 F.
HC1 Gas
Fumes are very toxic and hazardous to teeth, skin, eyes and mucous membranes. In strong concentrations, rubber protective equipment and approved pack or cannister gas masks are required.
Ferric Chloride
Solid at normal temperatures. Material is not toxic but presents an eye hazard.
Xylene
Fumes are very toxic. Limiting explosion concentra tion is 1.27 to 7.0?6 by volume in air. The flash point is 40F.
Trichlorobenzene
Solid at normal temperatures. Fumes are medium toxic. Fire point is above 210F.
Crude Aroclors
During processing,Aroclors are generally hot, 100c
or above, and can cause serious thermal burns. Con tinuous or repeated skin contact must be avoided. Vapors at room temperatures should not be breathed
in a confined space. At elevated temperatures, fumes are quite toxic. Continuous or repeated skin contact with Aroclor must be avoided by the use of gloves and protective garments.
MONS 036262
1.4MANUFACTURING FACILITIES 1.41 Description 1.411 General
CEA 1430 & 1800
Dates August 28, 1967 Page 9
The following information is included in the Appendix of this report:
Equipment Fli>w Sheets Suggested Equipment Layout Equipment Lists Scopes of Work
Preliminary Schedule Project Loss prevention Report
1.412 For Anniston
New storage and blending tanks to be added:
Aroclor 1242 " 1248 " 1254 " 1260 " 1262 " 1221/1232
Inerteen PPO and A13B
TCB TTCB
54.000 gallon
18.000
"
54.000
"
18.000
"
18,000
"
18,000
30.000
12.000 12,000
"
" "
(2 (2
(1 (1
27,000 gallon) 27,000 gallon)
12.000 gallon) 18.000 gallon)
An existing 2,000 gallon mixing tank will be relocated.
One covered loading dock for tank cars.
One covered loading dock for tank cars and trailers.
A new railroad spur.
Four existing 12,000 gallon storage tanks with submerged pumps will be dismantled and scrapped.
New drumming facilities to be added include a high speed drumming scale and a conveyor system
to bring empty drums to the scale and take filled drums away from the scale.
New flaking and bagging facilities to be added:
Storage for Aroclor 5460, 1268 and biphenyl
Flaker for solid Aroclors
MQNS 036263
CEA 1430 & 1800 Date: August 28, 1967 Page 10
Flaker for biphenyl
Mill for Aroclor 1268
High speed bagging machines for Aroclor 5460 flakes and biphenyl flakes
Conveyor system to take filled bags away from bagging machines
Fume control system for Aroclor 1268
The existing Aroclor and biphenyl flakers will be dismantled together with the present Aroclor feed tank.
A suitable building (120' X 601) to house the drumming and flaking operations.
Pipelines from Department 27 to tank farm as follows:
One line for Aroclor 1242 from existing 12,000 gallon day tank
One line for Aroclor 1248 and 1221
One line for Aroclor 1254 from existing 12,000 gallon day tank
One line for Aroclor 1260
One line for Aroclor 1262
Pipelines from tank farm to mix tanks:
One line for Aroclor 1242
One line for Aroclor 1254
One line for Aroclor 1260
One line for Aroclor 1248 and 1262
Pipelines from tank farm to loading spots and drum filling:
One line for A13B One line for KA and PP0
One line for Xylene and Toluene blends (drum filling only)
HONS 036264
CEA. 1430 & 1800 Date: August 28, 1967 Page 11
. One line for HB-40 (drum filling only)
One line for Aroclor 1242
One line for Aroclor 1254
One line for Aroclor 1221, 1232, 1248, 1262
One line for Aroclor 1260
Pumps will be provided as follows:
One for Aroclor 1242 transfer at tank farm
One for Aroclor 1254 transfer at tank farm
One for Aroclor 1248/1221, 1232/1262 trans fer at tank farm
One for Aroclor 1260 transfer at tank farm
One for Mix tank and PPO tank transfer
One for Xylene Mix tank transfer
One for TCB, TTCB tank car unloading
One for TCB, TTCB transfer to Mix tank
Three to transfer Aroclors from Building 27 to storage
1.413 For W. G. Krummrich
Mew storage tanks to be added:
Aroclor 1242 Aroclor 1248 Aroclor 1254
Aroclor 1260 Biphenyl
44,000 gallon 22,000 gallon 22,000 gallon
22,000 gallon 100,000 gallon
(2 -
22,000 gallon)
A new railroad spur
Two unloading docks for biphenyl cars
Three existing 15,000 gallon storage tanks with submerged pumps will be dismantled.
Pipelines from day tanks to tank farm as follows:
M0NS 036265
CEA 1430 & 1800 Dates August 28, 1967 Page 12
One line for Aroclor 1242
One line for Aroclor 1248
One line for Aroclor 1254
One line for Aroclor 1260
Pipelines from tank farm to loading spots and drum filling:
One line for Aroclor 1242
One line for Aroclor 1248
One line for Aroclor 1254
One line for Aroclor 1260
Pumps will be added as follows:
One for Aroclor 1248 transfer
One for Aroclor 1254 transfer
One for Aroclor 1260 transfer
One for Aroclor 1242 transfer
Facilities to produce 40M lbs./year of Aroclor 1242:
A continuous chlorinator chain consisting of biphenyl mix and continuous feed tank, four chlorination tanks, four mass circulating pumps and four external air coolers.
A continuous blow tank and intermediate storage tank.
Two semi-continuous distillation systems consisting of still pot, external circulat ing system with therminol heating, entrain ment separator, vapor condenser, receiver and vacuum steam ejector.
Two continuous porocel treatment systems consisting of feed tank, absorber, cleanup filter and product receivers. One train will have two absorbers to provide flexi bility.
MONS 03626b
1.42
CEA 1430 & 1800
Date: August 28, 1967 Page 13
A complete therminol heating, storage and circulating system.
Additions to the existing control room to provide space for a foreman and motor con trol center.
Design Capacity
1.421 Anniston
Finished Product Storage
Recommended
Product
(gal.)
Provided Future Need (gal.) (gal.) (1970)
1221 1232 1242 1248 1254 1260 1262
TOTAL
13, 0507 14,000/ 97,500 20,800 51,500 20,900
5.550
223,300
18,000
66,000(2) 18,000.,. 66,000 'z' 18,000 18,000
204,000
27,000 27,000
Increased flexibility in the storage area will allow a apacity increase of 5.7H lbs./year (from 48M to 53.7m).
Estimated tank car shipments for 1971: Estimated tank trailer shipments for 1971:
Estimated drum shipments for 1971: Estimated can shipments for 1971:
372 (3) 66 (3)
25,610 (3) 2, 030 (3)
(1) Letter from HJD to RSY 5/18/67. (2) Includes 12,000 gallon of day storage. (3) Anniston Job No. 370-720 (1) by R. H. Taylor
Mixing and Drumming Area
A new 12,000 gallon mix tank, a relocated 2,000 gallon mix tank and an 18,000 gallon mix tank to provide for:
Estimated tank car shipments for 1971:
Estimated tank truck shipments for 1971: Estimated drum shipments for 1971: Estimated can shipments for 1971:
55 (3)
1 (3) 5,764 (3) 1,312 (3)
A new drumming station with associated conveyors to handle 150 drume/day. (Basis: 8 hrs./day,
260 days/year, .7594 OST)
M0NS 036267
CEA 1430 & 1800 Date: August 20, 1967 Page 14
Flaking and. Bagging
Aroclor flaking capacity (Aroclor 5460) 41,500
lbs./day (Basis: 8 hrs./day, 365 days/year,
75% OST)
_____ _
Aroclor bagging capacity
2 bags/min.
Biphenyl flaking capacity 18,300 lbs./day (Basis: 8 hrs./day, 365 days/year, 75% OST)
Biphenyl bagging capacity 2 bags/min.
Flaking and bagging design will allow these operations to be carried out on a one-shift basis, seven days a week. Exception is Aroclor 1268 which will be flaked and packaged on a three-shift basis, seven days a week (3% of production).
Raw Material Storage
Raw Material
Provided (gal.)
TTCB TCB
12,000 12,000
1.422 WGK
Finished Product Storage
Recommended ^ Provided Future Need
Product
(gal.)
(gal.) (qal.) (1970)
1242 1248 1254 1260
TOTAL
132,000 25.200 34,400 20.200
211,800
84.000 ji?? 42.000 3 42.000 22.000
190,000
66,000 66,000
Estimated tank car shipments for 1971: Estimated tank trailer shipments for 1971:
Estimated drum shipments for 1971: Estimated can shipments for 1971:
112 306
12, 200 7651 2 3 4
(1) Letter from HJD to RSY 5/18/67. (2) Includes 40M gallons on hand storage (3) Includes 20M gallons on hand storage.
Extra storage required for operating
flexibility. (4) Include 20M gallons on hand storage.
MONS 036268
CEA 1430 & 1800
Date: August 28, 1967 Page 15
Raw Material Storage
Raw Material Biphenyl
Provided (gal.) 125,000^
(5) Includes 25M gallons on hand storage.
Provides capacity for 4 - 20,000 gallon cars and six days' supply at increased rate.
New unloading track and docks provide four days turnaround time at increased rate.
New Manufacturing Facilities
Continuous chlorination:
Basis: Producing Aroclor 1142 OST: 7,950 hrs./year Rate: 43? lbs./year
Semicontinuous distillation and earth treatment:
Basis: Producing Aroclor 1242
OST:
7,950 hrs./year
Rate: 40? lbs./year
For the overall product group, after these additions are completed, Anniston and WGK plant capacity will be as follows, ? lbs./ year:
Present New Increase in Capacity Capacity Capacity
Anniston WGK
48.0 29.5
TOTAL CAPACITY 77.5
53.7 69.5
123.2
5.7 40.0
45.7
Based on 1971 requirements for both plants (July 1967 Sales Forecast), excess capacity at that time will be:
New Capacity Required in' 1971
Excess Capacity
123.2M lbs./year 99.2? lbs./year
24.0? lbs./year
Excess Capacity
24.2%
MONS 036269
CEA 1430 & 1800 Date: August 28, 1967 Page 16
1.43 Flexibility Requirements
1.431 Anniston
Increased storage capacity and blending facilities will allow for better utilization of present still capacity. This will be accomplished by longer runs on the same product and result in increased pro auction capacity.
1.432 WGK
'
Based on the sales forecast of July 1967 for the Aroclor product group, batch units will produce Aroclors 1248, 1254 and 1260. The maximum capacity of these units is as follows for each Aroclor:
I Aroclor 1248
8,750 hrs. X 7,200 lb./ba. X 5 chlor X 92% OST 34.4 M lbs. 8.5 hrs./ba.
Aroclor 1254
8.750 hrs. X 8,040 lb./ba. X 5 chlor X 92% OST - 30.8 M lbs. 10.5 hrs./ba.
Aroclor 1260
8.750 hrs. X 9,100 lb./ba. X 5 chlor X 92% OST 29.2 M lbs. 12.5 hrs./ba.
Por the year 1971, the maximum batch capacity will be: For Aroclor 1248: 34.4 M lbs. X 21%(1) = 7.25 M lbs.. For Aroclor 1254: 30.8 M lbs. X 35%(1,= 10.80 M lbs. For Aroclor 1260: 29.2 M lbs. X 43%^* 12.60 M lbs.
Total Batch Capacity on this basis 30.65 M lbs.
(1) From the July 1967 Sales Forecast for 1971.
I
MONS 036270
1.44
..
.
CEA 1430 & 1800
Date: August 28, 1967 Page 17
Requirements for 1971 are 20.3m lbs., leaving an excess capacity of 51% at WGK.
For 1971, the continuous system capacity utili zation will be 25.6M lbs., leaving an excess capacity of 56% at WGK.
Flexibility will be designed into the WGK dis tillation systems to allow for the following operations:
Still No. 1 (existing) Aroclor 1260, 1262
Still No. 2 (existing) Boil down still to separate Montars (residues) from all products, Aroclors 1242, 1248, 1254, 1260 and 1262.
Still No. 3 (New)
Aroclor 1242 or 1254
Still No. 4 (New)
Aroclor 1242 or 1254
Future Expansion
1.441 Anniston
At the completion of this expansion, space will be available to the north of Building 27 for the addition of a complete new solid Aroclor line. Space is avail
able in the tank farm area for additional tankage.
Flaking and drumming capacity can be increased by adding additional personnel and operating on a 2 or 3 shift basis.
1.442 WGK
One of the objectives of this expansion is to provide 25-30% excess production capacity for Aroclors. As we use up the excess capacity provided in this project we must consider the next step in department expansion. If we assume the product split will increase propor tionally according to the latest sales forecasts,we can postulate an operation diagrammed as follows:
M0NS 036271
CEA 1430 & 1800 Date: August 28, 1967 Page 18
1.45
The layout of the new chlorination-distillation facili ties at WGK will allow space for the addition of
another chlorination unit, intermediate storage tanks and two additional distillation chains. Aroclor 1248 and 1262, because of the smaller requirements, would continue to be made in the batch units.
On this basis, we can postulate a productive capacity as follows for liquid Aroclors, M lbs./year:
Anniston
WGK batch units Cont. 1242 unit Cont. 1254 unit Cont. 1260 unit
53.7 29.5 40.0 15.0
15.0
TOTAL CAPACITY
153.2
Physical Appearance 1.451 Anniston
MONS 036272
Tanks of different heights will be grouped together to provide standardization.
In the flaking and drumming area, provision will be made for moving finished products directly into a new warehouse facility (when built).
1.46
CEA 1430 & 1800 Date: August 28, 1967 Page 19
1.452 WGK
Tanks will be grouped together as an exten sion of the present tank farm.
The new facilities will be a separate structure to the south of the existing unit.
Storage and Shipping Requirements
1.461 Anniston
Facilities provided are noted in greater detail in other parts of this report. Provision is being made for:
Raw material storage of TTCB and TCB.
Finished product storage for all liquid Aroclors.
Loading docks for tank car and tank trailer loading of products.
Moving filled bags of solid Aroclors and biphenyl to palette loading station, then to warehouse storage.
Moving drums and cans to palette loading station, then to warehouse storage.
Storage in the drumming area of the new manufacturing facility for empty drums and containers.
1.462 WGK
Provision is being made for:
Raw material storage of biphenyl.
Finished product storage for all liquid Aroclors.
Unloading docks for tank cars.
Making an existing unloading dock a loading dock for tank cars of Aroclors. Ho extensions or additions are being made to the present blending and drumming facilities. WGK technical service is modifying an existing storage tank to a blend tank and revamping piping in the drumming area.
MQNS 036273
CEA 1430 & 1800 . Dates August 28, 1967
Page 20
JjUTILITIES AND SERVICES
1.51 Utility and Service Requirements
1.511 Anniston Additions
Steam - 100 psig-For Storage Tanks
2,000 lbs ./hr
-For Process
500 lbs./hr
Purchased Water- For Process (Cleanup) 150 GPM
Compressed Air - For Storage Tanks
20 GPM
Plant Water Nitrogen
- For Process (Flakers) - For Storage Tanks
300 GPM 50 SCFM
Electric
- Connected
300 HP
- Operating
200 HP
WGK Additions
Steam - 80 psig - For Storage Tanks - For Process
5,000 lbs./hr 3,000 lbs./hr
200 psig-For Process
Natural Gas
- For Process
Purchased Water- For Process
Compressed Air - For Process
600 lbs./hr 1,800 SCFH
150 GPM 100 SCFM
- For Instruments
75 SCPM
Electric
- Connected
315 HP
- Operating
250 HP
Plant water - None Required
Nitrogen
- None Required
1.52 Utility and Service Facilities
1.521
Anniston
A new spur track from main track at north of plant to 5th Street, 1700 ft. long.
M0NS 036224
CEA 1430 & 1800 Dates August 28, 1967 Page 21
A new 300 KVA pole line transformer to supply tank farm and warehouse requirements.
A new sewerage lift station to replace existing field which is in the proposed manufacturing area. The lift station will tie into an exist ing city sewerage line.
Relocating a 24" IPS VC acid sewer.
Installation of a steel frame prefab-type building, 120' long X 60' wide to house the flaking, drumming and bagging facilities. This building will be designed so that it can be attached to a new warehouse building which will be 120' wide X 240' long.
A 15' wide X 80' long tank truck loading sta tion.
Relocation of existing plant parking facilities 70' wide X 120' long.
1.522 WGK
Extension of existing track 10A for 110 feet and installation of a turnover to tie existing track 10A into track 10.
Replace existing gas meter with a larger capa city meter.
Install new pump at department city water break tank with associated piping.
Install new 600 amp breaker in Sub #17. Install fans in Sub #17 transformer. Transfer feeder 8-1 from Sub #8 to Sub #17. Install an overhead feeder from Sub #17 to Building CF. Install feeder cables from breaker 8-1 to Department 246.
M0NS 036275
CEA 1430 Date: August 28. 1967 By: H. D. Gabelman
SCOPE OF WORK Aroclor Expansion at Anniston Storage Tank Farm and Mixing Station
Appendix "D'
MOWS 036276
Appendix D CEA 1430
Date: August 28, 1967
By: H. D. Gabelman
Page 1
General:
The facilities included in this project are intended to:
1. Assure storage capacity for minimum inventories of the various Aroclors and blends so that bulk shipments can be made on demand.
.2 Provide for blending of several Aroclors with other components without holding up primary production facilities.
3. Minimize the potential for cross contamination of products.
4. Provide loading facilities for tank cars, tank trucks and unload ing facilities for raw materials in tank cars.
Major Equipment includes
2 - 27,000gallon Aluminum Storage Tanks for 1242.
2 - 27,000gallon Aluminum Storage Tanks for 1254.
1 - 18,000gallon Aluminum Storage Tank for 1248.
1 - 18,000gallon Aluminum Storage Tank for 1221/1232.
1 - 18,000gallon Aluminum Storage Tank for 1260.
1 - 18,000gallon Aluminum Storage Tank for 1262.
1 - 12,000gallon Steel Storage Tank for TCB.
1 - 12,000gallon Steel Storage Tank for TTCB.
1 - 11,500gallon Aluminum Day Tank for 1242 (Existing).
1 - 11,500gallon Aluminum Day Tank for 1254 (Existing).
1 - 12,000gallon Aluminum Blend Tank for A13B.
1 - 18,000gallon Aluminum Storage Tank for KA-PPO.
7kI
1 - Existing and relocated 2,000 gallon Aluminum Blend Tank for Toluene and Xylene Blends.
All storage tanks to have plate coil heaters and to be insulated on
lower half.
Existing
dav tanks will be left "as is". The 2,000 gallon blend tank will be
left "as is" except it will be relocated. The 12,000 gallon Aluminum
Blend Tank for A13B will have plate coils, heaters, insulation and an
agitator. The 18,000 gallon Aluminum Blend Tank will have plate coil heaters and insulation.
)
MOMS 036277
Appendix D CEA X430 Page 2
Pumps, All 316 SS except TCB and TTCB which are cast iron.
1242 - Common loading pump for 2 storage tanks to loading spots; existing transfer pump from day tank to storage. See Code 93 paragraph 5 concerning pumps.
1254 - Common loading pump for 2 storage tanks to loading spots; existing transfer pump from day tank to storage. See Code 93 paragraph 5 concerning pumps.
1248/1221 - Existing transfer pump from receiver to storage - common pump. See Code 93 paragraph 5 concerning pumps.
1262 - Existing transfer pump from receiver to storage. See Code 93 paragraph 5 concerning pumps.
1248/1221/1232/1262 - Common loading pump from storage to loading spot.
1260 - Existing transfer pump from receiver to storage - loading pump from storage to loading spot. See Code 93 paragraph 5 concern ing pumps.
TCB and TTCB have one common pump for unloading from tank cars and one common pump for transfer to blend tanks.
Blend tank for A13B and storage tank for KA-PPO will have common trans fer pump from tanks to loading spot or drumming.
Blend tank for Toluene and Xylene blends will have a transfer pump from tank to drumming.
Filters
All 316 SS or 304 SS.
Separate filters (Alsop) are provided for 1242, 1254, 1260 and 1248/ 1262/1221/1232.
A new filter (Sparkler) is provided for A13B/KA-PPO from mix and finished blend storage tanks. An existing Sparkler filter will be relocated for the Toluene and xylene blends.
Piping
Separate transfer lines are provided for:
1242 - Fromday tank to storage to loading docks.
1254 - Fromday tank to storage to loading docks.
1260 - From receiver to storage to loading docks.
MONS 036278
Appendix D CEA 1430 Page 3
1262 - From receiver to storage.to loading docks.
1221/1248 - Common line from receiver to storage to loading docks.
All above lines are 3" aluminum, traced and insulated.
Piping is provided for circulating the contents of each finished goods tank.
Piping from tank cars for TCB and TTCB to storage and from storage to mix tanks will be steel.
Utilities
1. Spur track from main track to 5th Street with 2 covered loading docks for tank cars. One of these will be used for unloading TCB and TTCB.
2. One covered loading dock on 5th Street for loading tank trucks.
3. 6" steam main from Building 27 to tank farm.
4. 2" N, transfer line from existing N, storage tank to tank farm (all^tanks except TCB and TTCB are blanketed.)
5. Electrical:
Existing HB40 transformer will be dismantled and scrapped; HB40 load will be picked up on Aroclor motor control center. Hew load in the tank farm-warehouse area will be supplied from pole line transformer supplied from the existing HB40 overhead feeder.
Roads
An approximate 80' X 15' wide loading area at side of 5th Street will be provided as a loading area for tank trucks.
Structures and Foundations
Two tank car spots and one tank truck loading spot are weather protected by roofing.
All storage tanks will be on ring walls with compacted sand fill except the 2000 gallon blend tank which will be on a concrete pad. Area be tween tanks will be covered with chat.
HONS 036279
1
1
01 - Equipment
1 As per Equipment List and Summary.
Appendix D CEA 1430 Page 4
02 - instruments
1 As per Instrument List and Summary.
1 03 - Setting and Testing Equipment
Tank farm is immediately adjacent to 5th Street and east of Aroclor office. Truck deliveries can be made directly to site.
1
04 - Setting and Testing Instruments
Nothing unusual.
05 - Piling
None allowed for.
06 - Excavation 1 1 For railroad spur track
Tank foundations - 12 0 9-1/4 yd3 each
?
Tank pad for 2000 gallon mix tank Pump foundations - 8 0 1 yd3 each n Filter foundations - 6 0 2/3 yd3 each
2 Tank car loading docks 0 2 yd3 each
1 Tank truck loading dock
Pipe support foundations
as 7,000 yd3 - 111 yd3 * 15 yd3 - 8 yd3 SB 4 yd3 s 4 yd3 - 2 yd3 at 13 yd3
All excavated earth will be spoiled in immediate area.
07 - Foundations
Tanks
12 ring walls 0 3 yd3 each Forms 155 ft2 each Crushed rock and sand fill Pad for mix tank Form
Pipe Support Foundations 6 0 2-1/2 yd3 each Forms 0 100 ft2 each
3 36 yd cone. i860 ft2 95 yd3 15 yd3 cone. 80 ft2
HONS 036280
15 yd3 600 ft2
3 Loading Docks Forms
8 Pump Foundations @ 1 yd3 each Forms 60 ft2
6 Filter Foundations 2/3 yd3 each Forms 20 ft2 each
Appendix D CEA 1430 Page 5
= 6 yd3 cone. as 120 ft2
= 8 yd3 cone. - 480 ft2
= 4 yd3 cone. m 120 ft2
Approximately 6 borings for soil bearing determination will be made.
08 - Supports, Platforms and Structures
1 Pipe bridge over 5th Street
=
Pole supports to loading dock structure
=
Miscellaneous steel at ground level pipe supports
2-20' high ladders with safety cages.
.
3-1/2 ton steal 3 ton steel 2 ton steel
Platforms over tanks in farm Platform Stair Treads Grating Double pipe hand rail Toe plate 3 loading docks (with covers over) Galbestos roofing
5 ton steel 50 1050 ft2
750 ft 700 ft
6 ton steel 600 ft2
10 - Sprinklers and Fire Protection
Nona
M0NS 036281
Appendix D CEA 1430 Page 6
11 - Piping - Process and Service
750' - For 1242 - From Bldg. 27 to storage tanks to loading docks A-ll const. - 3" Sch. 40 - I.P.S. - Aluminum
750' - For 1254 - From Bldg. 27 to storage tanks to loading docks A-ll const. - 3" Sch. 40 - I.P.S. - Aluminum
750' - For 1260 - From Bldg. 27 to storage tanks to loading docks A-ll const. - 3" Sch. 40 - I.P.S. - Aluminum
600' - For 1262 - From Bldg. 27 to storage tanks to loading docks A-ll const. - 3" Sch. 40 - I.P.S. - Aluminum
700' - 1221/1248/1232 - From Bldg. 27 to storage tanks to loading docks
All above 3" aluminum pipe to be single traced with 1/2" copper tubing. Trap condensate each 200' of tracing.
.
300' - 125# steam from Bldg. 27 - F-41 const. - 6" Sch. 40 steel pipe
300' - 125# steam
- F-41 const. - 2" Sch. 40 steel pipe
500' - N, Nitrogen unit east of Chlorine - 2" vinyl covered ` Sch. 40 steel
For TCB and TTCB from loading dock to storage - F-ll const. 350' Sch. 40 3" steel pipe
For TCB and TTCB from storage to mix tanks
- F-ll const. - 100' Sch. 40 3" steel pipe
Toluene to mix tank - A-ll const. Xylene to mix tank - A-ll const.
20' - 3" Sch. 40 I.P.S. Aluminum 20' - 3" Sch. 40 I.P.S. Aluminum
KA-PPO to loading dock A-ll const. 320' - 3" Sch. 40 I.P.S. Aluminum
A13B to loading dock A-ll const. 320* - 3" Sch. 40 i.p.s; Aluminum
12 - Ductwork
None
MONS 036282
Appendix D CEA 1430
Page 7
13 - Electrical
'
Yard lighting for tank farm area - 13 tanks - approx. 60' X 100' area.
Lighting for two tank car loading docks and one tank truck loading dock area.
6 - Street light type Mercury Arc fixtures for loading dock and
tank farm perimeter plus 8-175 watt Mercury Arc lighting fixtures over tank farm area.
8 - 15 HP motors on pumps
2 - 7>j HP motors on agitators
Pushbuttons at each pump and at remote location.
install 300 KVA pole type transformer for warehouse and tank farm load.
14 - Site Preparation
Grade area east of Aroclor office to an elevation of 746't. Area equals approx. 120' north from 5th Street x 60' east of Aroclor office.
Terrace down from 746' elevation to 742' immediately to east of leveled area.
3 Earth moved approximates 300 yd and will be spoiled in immediate area.
15 - Sewers and Drains None required.
16 - Underground Mains
None required.
17 - Yards and Roads
1. Establish tank truck loading spot on 5th Street adjacent to tank farm. Area approx. 1200 ft^ (80' x 15').
Grade off approx. 50 yd3 earth.
Crushed rock ballast for loading spot (8" thick) - 35 yd3
2 1200 ft 2" thick asphalt paving.
2. Tank Farm Area (120' X 60')
M0NS 036283
crushed Rock 70 yd3
Appendix D CEA 1430 Page 8
3. Repair construction damage to.5th Street.
Assume resurfacing of 3000 ftz (30' x 100') 2" asphalt paving.
18 - Railroads
Install approximately 1700' rail spur from main line at north side of plant. Spur to extend along west side of Parkwin to 7th Street.
Then offset to west approximately 130' and extend to 5th Street. This includes switch, bumper, ties, track, ballast and 4 crossings. Excavation for this spur is included in code 06.
19 - Insulation
Tank insulation to be 1-1/2" thick calcium silicate - Std Kll.2 Std 100 with weather barrier.
Tanks as follows:
4-13' 5 - 12' 2 - 11'
diameter G> 60C1 ft2 diameter 40C1 ft2 diameter 30C1 ft2
each each each =
2400 ft2 20Q0 ft2
600 ft2
Pips insulation to be the same spec Std as tanks.
For 1242
1-1/2"
- 100 - 750' - 4" pipe
For 1254 For 1260
1-1/2" 1-1/2"
- 100 - 750' - 4" pipe - 100 - 750' - 4" pipe
For 1262
1-1/2"
- 100 - 600* - 4" pipe
For 1221/1248 For Steam For Steam
1-1/2" 1-1/2" 1-1/2"
- 100 - 700' - 4" pipe - 100 - 300' - 6" pipe - 100 - 300' - 2" pipe
Pump and filter insulation to be same Kll.2 Std 100 insulating system with weather barrier.
6 - Pumps to be traced and insulated. 5 - Filters to be traced and Insulated 9 25 ft2 125 ft2
30 - Painting
All structural steel to be hot dipped galvanized. Touch-up damaged areas with inorganic zinc coatings in field, (carbo Zinc #11)
HONS 036284
l
Appendix d
CEA 1430 Page 9
90 - Dismantling
Remove and scrap 3 X 15,000 gallon and 1 X 11,000 gallon horizontal storage tanks and 1 X 10,000 gallon vertical mix tanks
Item No.
Equipment No. ____________ Description
201
22-0077
10' X 26' long horizontal tank
202
22-0089
8' X 30' long horizontal tank
203 22-0076-01 10' X 26' long horizontal tank
204 - 10' X 26' long horizontal tank
205
22-0108
14' X 10' high tank
208 - Taber vertical subm. pump 209 - Taber vertical subm. pump
214 - Taber vertical subm. pump
215 - Taber vertical subm. pump
Remove and scrap existing HB-40 transformer.
93 - Relocations and Modifications Expense
1. Existing feeder cable from existing HB-40 transformer to Aroclor motor control center.
2. 360' of 8' high cyclone fencing.
3. Existing Sparkler filter (18"), from building 27 to new tank farm.
4. Existing 2000 gallon jacketed SS mix tank with agitator, from building 27 to new tank farm.
5. Money for replacing three existing transfer pumps is to be included in this scope. The existing pumps referred to are those noted in the "General" section of this scope under "Pumps" for transferring 1248/1221,1262 and 1260 from exist ing day tanks and/or receivers to new storage facilities.
HONS 036285
CEA 1430 Date: August 28, 1987 By: H. D. Gabelman
SCOPE OF WORK Aroclor Expansion at Anniston
Drumming and Flaking
Appendix "E"
HONS 036286
Appendix E CEA 1430 Page 1
general
Thia scope covers the installation of drumming and flaking facilities in a new prefab structure north of 5th Street and at eastern boundary of block 4 (east of tank farm, see Appendix D). Space and detail de sign will allow for attaching a warehouse to the north of this struc ture. The warehouse is a separate project covered by CEA 1452.
These facilities are intended to
1. Provide for drumming and flaking in an area, removed, but adja cent to the manufacturing area, so as to allow for greater effi ciency in use of manpower, both in the manufacturing area and in packaging and warehousing,
2. Rail and truck loading and unloading facilities at point of packag ing to minimize handling will be provided (see Appendix D).
3. Provide storage space for bags and a limited number of drums both empty and full.
01 - Equipment
See Drumming and Flaking equipment lists.
02 - Instruments
See instrument list.
03 - Set and Test Equipment
04 - Set and Teat Instruments
05 - Piling
None
06 - Excavation
Building foundation Intermediate building foundations
- 80 yd as 40 yd
Pipe Supports 15 2-1/3 yd3 each
City Water - 50' 9 6 ft3/ft - 300 ft3
C.T.W.
- 30' 12 ft3/l - 360 ft3
Fire Water - 120' 6 ft3/l - 720 ft3
- 35 yd' as 11 yd m 14 yd' aa 45 yd'
HONS 036287
Appendix E CEA 1430 Page 2
Backfill (CW, CTW, FW)
Spoil in immediate area Building fill
- 70 yd3 3
- 177 yd
- 1600 yd3
(use for building fill) (needed fill available from ) (R.R. excavation for tank farm)
Excatation and backfill for 500' of 4" pressure sewer - 225 yd3 each
Excavation for sewage ejector - 14' deep - 52 yd3
Excavation and backfill for 4-" connecting sewers - 93 yd3 each
07 - Foundations
Building Foundations and Floor Forms
300 yd3 concrete 5000 ft2
Pipe Supports Forms
- 35 yd3 concrete - 750 ft2
6 Borings for soil bearing analysis.
Drumming! Air Compressor Pad for sewage ejector Concrete fill around ejector
- 2 yd3 concrete - 1.5 yd3
- 2000 psi concrete 7 yd'
08 - Supports, Platforms and Structures
Flaking: - Structural Steel - Grating - Stair Treads - Double Pipe Handrail - Toe Plate - Miscellaneous Steel
Drumming:- Miscellaneous Steel
- 30 ton - 1800 ft2 - 80 - 150 ft. - 90 ft. - 2 ton - 2 ton
All structural steel to be hot dipped galvanized; building steel to be painted (see Code 20).
09 - Building
A 120' clear span structure 60' long with 23' eave height will be
provided. A canopy will be extended over the railroad tracks. The aide next to tracks will be open for loading and unloading
rail cars, one half of south side will be open to serve as a truck loading and unloading dock. East, north and part of south side will be covered with corrugated transite and corrugated vinyl.
Walls
- Corrugated transite
.'
Corrugated vinyl
-
5000 ft 2 2
1200 ft
HONS 036288
Appendix E CEA 1430 Page 3
Roof and Roofing
Corrugated "Galbestos" and Vinyl panels with 8' overhang over rail road tracks and 6' canopy over truck loading area.
Corrugated Galbestos - 7500 ft2
Corrugated Vinyl
= 1000 ft2
Gutters and Downspouts
'
240' - 6" Aluminum guttering 120' - 6" Aluminum downspouts
10 - Sprinklers and Fire Protection
Structure - Provide an automatic dry pipe sprinkler fire protec tion system designed for extra hazard spacing and pipe sizing for approximately 7200 ft^ (1 head each 100 ft^) 72 heads.
11 - Piping
'
Drumming
2" parallel traced and insulated aluminum for 1242, 1254, 1248/1221/1232/1262, 1260, blend A13B, blend KA-PPO all originating at battery limits (connected to lines running to loading docks) - 6 lines 9 120' each 720'.
2" parallel traced and insulated aluminum for Xylene and Toluene blends - 1 line 300*
3" steel insulated line for HB-40
600'
4" steel insulated line for steam
- 200'
2" steel miscellaneous piping (for Jet, air comp, etc.) - 200' assumed
Flaking 3" X 2" jacketed steel line for 1168 & 5460 2" steel traced and insulated for Bi^ 3" steel insulated line for Theminol 4" steel for CTW, S&R - 2 lines 9 150' each 2" steel insulated steam for Bi^ surgetank
2" steel insulated steam for Miscellaneouspiping
- 450' * 500' - 900* 300' - 200'
- 200'
12 - Ductwork
Flaking
12" <j> - 304 SS 18 gauge
100 ft.
MOMS 036289
Appendix E CEA 1430 Page 4
13 - Electrical
Power from pole line transformer into motor control center in building (approx. 50' distance).
Power from motor control center to following motors:
Drumming: 1 - 25 HP Air Compressor Motor
Flaking:
1 - 15 HP 1268 Mill 1 - 10 HP Aroclor Flaker Motor 1 - 5 HP Bi^> Flaker Motor 1 - 3 HP Bag Flattener Motor 2 - 5 HP Fluidizing Air Blower Motors 2 - 5 HP Suction Blower Motors 2 - 3 HP Transfer Pump Motors 3 - 3 HP Conveyor Motors 1 -V4 HP Shaker Motor 2 - l*s HP Ejector Compressor Motors
Lighting for ground level - area 120' x 60' (7200 ft2) 18 - 175 watt mercury arc lights
Lighting for 14' level - area 30' X 60' (1800 ft2) 5-175 watt mercury arc lights
14 - Site Preparation
Qrade truck loading and unloading area at southeast corner of drumming and flaking structure.
40' X 50' area - Move approx. 80 yd2 earth.
15 - Sewers and Drains
300' - 12" v.C. storm sewer (Along east side of structure to Snow creek)
200' - 8" V.C. storm sewer for gutters
M0NS 036290
3 - Floor Drains
200' - 4" V.C. connecting sewers to floor drains.
Provide 30 GPM sewage ejector with tank, controls, etc.
500 lineal feet 4" Cl pressure sewage line from ejector to pipe shop service line.
140 lineal feet of 4" Cl sewer to connect existing sewers to ejector.
1 manhole at ejector, 10' deep with cover. 1 mankni. -*
ShOD.
*------.
16 - Underground Maine
Appendix s CEA 1430. Page 5
50' 2" C.I. City Water Main
60' 12" C.I. Fire Main 60' 6" C.I. Fire Main
60' 4" Steel C.T.W. - Supply'and Return
17 - Yards and Roads 2000 ft2 X 8" thick concrete truck pad 50 yd3 concrete. 2 700 ft asphalt - street repair at sewage ejector.
18 - Railroads
None
19 - insulation
Pipe insulation to be IV thick calcium silicate Kll.2 Std 100 with weather barrier. Quantities as follows:
Drumming:
4" - 200' 3" - 1620' 2" - 200'
Flaking:
3" - 1400' 2" - 400'
20 - Painting
Building steel to have 3 coat vinyl system.
90 - Dismantling
Disconnect and remove 4 septic tanks.
Item No.
Equipment Mo. ____________ Description
631 22-0700
Plaker hold tank with agitator, drive and motor.
690 14-0031
Model VMS 5-56, Flaker, size 24" x 48" with 5HP motor.
Biphenyl Flak. er
HONS 036291
646 17-0027
2DH Micro Pulverizer with 1/3HP motor
Appendix E CEA 1430 Page 6 nalncation 1. Relocate 520' of existing 24" acid sewer. Excavate and in ' stall new V.C. sewer between two existing manholes. 2. Relocate parking lot. extend to north of existing parking lot, 70' X 120', 8400 ft.2 of asphalt paving with parking stalls.
HONS 036292
1
CEA 1800 Date: August 28, 1967
By: R. S. Yates
1
1
1
1 SCOPE OP WORK
1 Aroclor Expansion at w. G. Krummrlch
1 New 40 M lb8./yr. Plant
1
1
1
1
1
1
1
T
1
T
1 Appendix "F"
HONS 036293
1
Appendix F CEA 1800 Page 1
Ooneral The facilities included in this project are
1. Installation of a new continuous chlorination system. 2. Installation of two distillation units with a capacity of
25 M lbs./yr. in each system. 3. Porocel/bauxite treatment for four different Aroclors. 4. Replacement of present off-gas recovery system with a new
system. Haior Equipment Includes
A biphenyl mix (2000 gallon) and feed tank (2000 gallon) to supply continuous chlorinator line. 4 - 1200 gallon (4` Dia. X 20') chlorinator units with attached coolers, pumps and entrainment system. 1 - 2500 gallon continuous blow tank. 1 - 15,000 gallon intermediate storage tank. 2 - Flash distillation systems consisting of still pot, entrainment separator, condenser, receiver, and external therminol heater. Off-gas system consisting of gas cooler-condenser, surge tank (3000 gallon). Therminol cooling system for still condensers. 4 - Fixed bed absorbers (3' Dia. X 15') with associated tankage, filters and pumps. External therminol heating system for supplying therminol to the still pot heaters.
HONS 03629^
Appendix p
CEA 1800 Page 2
01 - Equipment See Equipment List and Summary.
02 - Instrument Items See Instrument List and Summary.
03 - Setting and Testing Equipment
Area is accessible for truck and train unloading. High lift can be used advantageously. 04 - Setting and Testing Instruments
A control room is available for the instruments and panel.
05 - Piling
For Structural Steel
14 Concrete piles X 3 cu.yds. Size 24" dia. X 25' long
42 cu.yds.
For Blow Tank, Item 422
4 Concrete piles X 3 cu.yds. For inter Storage Tank, Item 424
12 cu.yds.
7 Concrete piles X 3 cu.yds. For Aroclor Surge Tank, Item 586
21 cu.yds.
4 Concrete piles X 3 cu.yds. 00 - Excavation
12 cu.yds.
For Floor of Operating Area 2300 ft2 X 1' deep
85 cu.yds.
For Motor Control Center and Foreman'Office S cu.yds 6* deep X 5' wide X 40'
07 - Foundations
For Structural Steel 14*20" square pads 3' deep
4.2 cu.yds. HONS 036295
Appendix P CEA 1800
Page 3
For Blow Tank 1 . 1' X 3' high X 71 long support 1 - 1*5' X 2' deep X 8' long support
For Inter Storage Tank, Item 424 18" thick X 12' dia.
1.75 cu.yds. 6.4 cu.yds.
For Floors Miscellaneous Supports, etc.
85 cu.yds. 5 cu.yds.
Pipe Supports 6X2 cu.yds. For Motor Control Center & Foreman's Office Support 5' X 1.5' X 80' - 600 ft2 Floor 800 ft2
12 cu.yds. 6 cu.yds.
08 - Supports
Structure Supports
65 tons
Grating
4500 sq.ft.
Handrail
500 ft.
Toe Plate
500 ft.
Stairway (15 ft. elev.) For Motor Control Center & Foreman's Office
4 5 tons
For Item 545 09 - Building Items
5 tons
5 unit heaters with associated piping for operating structure.
For Motor Control Center and Foreman's office
2 personnel doors (3' X 6'8") Windows for office, 3 units 4' X 10'
Sprinklers
None
MONS 036296
1
Appendix F
CEA 1000 Pago 4
U Piping
Note; * With 2 - 1/2" O.D. copper tracers and insulated - 1-1/2" thick insulation.
** with 1 - 1/2" O.D. copper tracer and insulated - 1-1/2" thick insulation.
ttern 403 - Biphenyl Mix
.
* Charge - 50 ft. of 2" IPS C.S. pipe with 2 No. CD3 valves.
* overflow - 50 ft. of 3" IPS C.S. pipe.
* vent - 15 ft. of 3" IPS C.S. pipe with spark arrestor jacketed.
Steam - 30 ft. of 1" IPS C.S. pipe to coil with 2 valves. - 30 ft. of 1" IPS C.S. pipe from coil with 2 valves.
Item 404 - Biphenyl Feed
* charge - 20 ft. of 2" IPS C.S. pipe with 1 No. CD3 valve.
* Overflow - 25 ft. of 2" IPS C.S. pipe.
* To Item 405 - 20 ft. of 3" IPS C.S. pipe with 2 No. CD3 valves.
Items 406, 410. 414 and 418 - Continuous Chlorinators
Chlorine Charge Line
200 ft. of 4" IPS C.S. pipe with 6 DE6 valves.
* Circ. lines
280 ft. of 3" IPS C.S. pipe with 28 CD3 valves.
* Transfer to Item 422
75 ft. Of 3" IPS C.S. pipe with 4 CD3 valves.
Vent Lines
50 ft. of 3" IPS C.S. pipe with 2 CD3 valves.
Trace chlorinators to allow for winter operation - 400 ft. of 1/2" copper tracing per chlorinator.
Item 405 - Biphenyl Feed Pump
* Chlorinator Charge - 80 ft. of 2" IPS C.S. pipe with 4 No. CD3 valves.
* Chlorinator Return - 70 ft. of 2" IPS C.S. pipe with 1 No. CD3 valve.
MONS 036297
Appendix F ' CEA 1800 , Page 5
Tt-gm 422 - Blow Tank
* charge
30 ft. of 4- IPS C.S. pipe with 1 No. CD3 valve.
Vent Blow Line
35 ft. of 6" IPS Saran lined steel_ifie. 30 ft. of 2 IPS C.S. pipe with 4 valves.
** To Item 423 10 ft. of 3" IPS C. S. pipe with 1 No. CD3 valve
Tfcem 424 - Intermediate Storage
** From Item 423 75 ft. of 2" IPS C.S. pipe with 1 No. CD3 valve.
** Overflow
25 ft. of 3" IPS C.S. pipe.
Vent
10 ft. of 3" IPS C.S. pipe.
** To Item 425 10 ft. of 3" IPS C.S. pipe.
Item 425 - Transfer Pump
** To Item 502 & 511 - 50 ft. of 2" IPS C.S. pipe with 2 No. CD3 valves.
** To Existing Chlorinators - 75 ft. of 2" IPS C.S. pipe with 3 No. CD3 valves.
Off-Oas System
Present HC1 header at southwest section of 12 ft. level to be modified and new line run from this header to new off-gas con-
denser, Item 427.
** Piping Required
30 !ft. of 6" IPS C.S. pipe.
** From Chlor. 6-9
100 ft. of 6" IPS C.S. pipe with 2 CD3 valves.
Circ. Water System 75 ft. of 3" IPS C.S. pipe.
Drain From Item 427 To HC1 Recovery
15 ft. of 4" IPS C.S. pipe. 40 ft. of 6" IPS C.S. pipe.
KC1 Transfer
1300 ft. of 8" IPS C.S. pipe from Dept. 246 to Dept. 218.
Steam to Item 429 ** To Item 431
60 ft. of 2" IPS C.S. pipe. 20 ft. of 3" IPS C.S. pipe.
** From Item 431
90 ft. of 2" IPS C.S. pipe.
HONS 036298
Appendix F CEA 1800
Page 6
Aroclor Circulating System To Items 504 & 526
125 ft. of 4" IPS C.S. pipe.
From Items 504 & 526
125 ft. of 4" IPS C.S. pipe
. With 4 valves.
Item 502 - Still Pot Item 511 - Still Pot
.
Montar Drawoff 2-15 ft. of 2" IPS C.S. pipe 30 ft. With 4 valves
To Items 505 & 512 2-15 ft. of 14" IPS C.S. pipe = 30 ft.
'
From Items 505 & 512 2-25 ft. of 10" IPS C.S. pipe - 50 ft.' Above lines insulated with 2" thick insulation.
Item 506 - Still Condenser Item 513 - still condenser
To Item 508 & 515 2-15 ft. of 3" IPS S.S. pipe *= 30 ft.
Item 508 & 515 - Still Receivers
To Items 523 & 524 2 - 30 ft. of 4" IPS C.S. pipe * 60 ft. with 2 valves
** To Items 510 & 517 2 - 15 ft. of 3" IPS SJ3. pipe 30 ft. with 1 valve
Item 523 & 524 - Catch Tanks
Drain Lines
To Ejectors
)
Items 509 & 516 )
2-35 ft. of 2" IPS C.S. pipe " 70 ft. with 2 valves
2-15 ft. of 4" IPS C.S. pipe 30 ft. with 2 valves.
Item 509 & 516 - Ejectors
Steam Lines Drain Line
60 ft. of 1-1/2" IPS C.S. pipe 30 ft. of 3" IPS C.S. pipe
MGNS 036299
Appendix F
CEA 1800 Page 7
Item 518, 519 & 520 - Aroclor Cooling System
From Item 519 to Item 520
30 ft. of 2" IPS C.S. pipe with 2 valves.
From Item 520 to Items 506 & 513 60 ft. of 2" IPS C.S. pipe with 2 valves.
From Items 506 & 513 to Item 518 30 ft. of 2" IPS C.S. pipe
From Item 518 to Item 519
30 ft. of 2" IPS C.S. pipe
Item 503 & 525 - Circulating Pumps
**2-15 ft. of 4" IPS C.S. pipe = 30 ft. with 4 valves **2-10 ft. of 4" IPS C.S. pipe 20 ft. with 2 valves
* 1 - 150 ft. of 2" IPS C.S. pipe for transfer to Still No. 2.
item 530 & 537 - Surge Tanks
From Items 510 & 517 To Items 531 & 538 Hater/Steam Overflow From #2 Still Receiver
2-25 ft. of 2" IPS A1 pipe with 2 valves 2-20 ft. of 2" IPS A1 pipe with 2 valves
100 ft. of 2" IPS C.S. pipe
2-15 ft. of 3" IPS A1 pipe 200 ft. of 2" IPS A1 pipe with 2 valves
Items 532, 539 & 540 - Absorbers
* To Absorbers 100 ft. of 2" IPS A1 pipe with 5 valves * From Absorbers 100 ft. of 2" IPS A1 pipe with 5 valves
Items 541 & 533 - Filters
**75 ft. of 2" IPS A1 pipe with 4 valves
Items 534 & 535 - Surge Tanks
* Vent Lines * To Item 544 * To Item 536 * From Item 544 * From Item 536
Steam Line
2-25 ft. of 3" IPS A1 pipe 20 ft. of 3" IPS A1 pipe 20 ft. of 3" IPS A1 pipe
100 ft. of 3" IPS A1 pipe 125 ft. of 3" IPS A1 pipe 100 ft. of 1-1/2" IPS C.S. pipe
Items 426 & 433 - Scrubbers
HONS 036300
Water Inlet Drain Line
100 ft. of 2" C.S,. pipe with 3 valves 30 ft. of 8" Saran lined steel pipe 30 ft. of 12" Saran lined steel pipe
Appendix F CEA 1800 Page 8
m< scellaneous
Feed line from batch blow tank to Items 502 & 511 ** 125 ft. of 2" C.S. pipe with 4 valves
To Item 434 - 20 ft. of 3" C.S. pipe with 1 valve
) 7 - Ductwork
None required.
p - Electrical
Motors to be installed and wired
5 - 2 HP 1 - 3 HP 7 - 5 HP 1 - 7*j HP 7 - 10 HP 6 - 15 HP 2 - 20 HP 1 - 50 HP
.
Allow for remote pushbuttons and alarms for 15 motors.
Lighting required: Operating area:
16 - 20 ft. X 20 ft. bays
Foreman's office:
225 ft^
5 Motor Control Center: 225 ft
Install 600 ampere breaker in Sub. No. 17.
Install fans in Sub. No. 17 transformer.
Transfer feeder 8-1 from Sub. #8 to #17.
Install overhead feeder cable from Sub. #17 to Bldg. CF, capacity 600 amperes, length 400 ft.
Install 400 ft. of feeder cable from breaker 8-1 to Dept. 246,
capacity 600 amperes.
.
1_4 - Site Preparation
None allowed for.
HONS 036301
Appendix F CEA 1800 Page 9
IS - Sewers
Floor drains
- 6 surface drains.
Sewer pipe
- 130 ft. of 4" permanite sewer pipe with two tie-ins to existing 8" sewer which runs directly south of Dept. 246.
Excavation Sewer tie-in
- 2 ft. X 4 ft. X 130 ft. - Two for scrubbers.
40 cu.yds.
Drinking fountains - two required.
16 - Underground Mains
None allowed for.
17 - Yards
Allow for gravel surfacing approximately 2000 ft2 of access areas. 16 - Railroads
None allowed for. 19 - Insulation
Piping Equipment
- Refer to Code 11 ~ As below - Mater:
Item
Area
Vessels
403 404 422 424 429 430 500 501 502 505 508 511 512 515 519
235 ft2 235 ft2 540 ft2 855 ft2 428 ft2 100 ft2
20 ft2 20 ft2 330 ft2 130 ft2 205 ft2 330 ft2 130 ft2 205 ft2 100 ft2
Thickness
1%"
IV IV IV IV IV IV
llj" 2" 2"
IV 2"
2"
IV IV
HONS 036302
Appendix F CEA 1800 Page 10
Item 537 539 540 541 542 543 530 532 533 534 535 585 586 409 413 417 421 504 526 545
20 Pumps
Area 205 ft2 160 ft2 160 ft2
50 ft2 330 ft2 330 ft2 205 ft2 160 ft2
50 ft2 330 ft2 330 ft2 120 ft2 200 ft2
60 ft2 60 ft2 60 ft2 60 ft2 100 ft2 100 ft2 160 ft2
--
'
Thickness
ft" iy 1*5" IV 1*5" 1*5" 1*5" 1*1" 1*1" 1*1" 1*5" 3" 2*i" 1*1" 1*5" 1*5" 1*5" 1*5" 1*1" 1*1" 1*1"
20 - Painting
Coating Std #502, Epoxy system Supports for Items 408, 412, 416, 420, 426, 433, 427, 509, 516, 518, 523 and 524. Items 406, 410, 414, and 418 Uninsulated piping - air, water, gas
.21 - Walls, Masonry, Roofs
Concrete block structure attached to existing control room. Allow for 4 walls 15' X 20' high, total area - 1200 ft .
2 Concrete roof deck with tar paper coating - area 250 ft .
MQNS 036303
Appendix F CEA 1800 Page 11
in - Dismantling
Item No. 172 173
Equipment No. 21-5150
38-5588
Description Mist eliminator, 30" x 13' Brinks unit
Heat exchanger, 16" O.D. X 8' long
Present 6" HC1 line to Dept. 218 will be dismantled
93 - Relocations and Modifications Expense
Move and relocate one power line pole and electric wires now in conflict with the new structure.
Move and relocate the following pipe lines which are south of the existing plant and which will interfere with the new struc ture.
Air line
- 40 ft. of 4" C.S. pipe
Chlorine line
- 40 ft. of 4" C.S. pipe
Instrument air line - 40 ft. of l1!" C.S. pipe
Water line
- 40 ft. of 3" city water line
HONS 036304
CEA 1800 Date: August 28, 1967 By: R. S. Yates
SCOPE OF WORK Aroclor Expansion at W. G. Krummrich
Storage Tank Farm
Appendix "G
HUNS 036305
Appendix a CEA 1800
Dates August 28, 1967 . Byi R. s. Yates
Page 1
", - iTJ 1
.
-'! facilities included in this project are intended to;
j. insure adequate supply of biphenyl.
2. Assure storage capacity for minimum inventories of various Aroclors so that bulk shipments can be made on demand.
I. Minimize the potential for cross contamination.
provide additional unloading facilities for biphenyl. ri. Remove existing underground storage tanks.
Miior Equipment includes
1 - 100,000 gallon Steel Tank for Biphenyl.
2 - 22,000 gallon Aluminum Tanks for Aroclor 1242.
1 - 22,000 gallon Aluminum Tank for Aroclor 1254.
1 - 22,000 gallon Aluminum Tank fpr Aroclor 1260.
1 - 22,000 gallon Aluminum Tank for Aroclor 1248.
All storage tanks to have plate coil heaters and to be insulated over the lower half. Tank for 1260 to be completely insulated.
rumps
All 316 SS.
1342 - Common pump for two storage tanks.
1254 - Pump for two storage tanks.
1260 - Pump for one storage tank.
1248 - Pump for one storage tank. filters
All 316 ss.
S-parate filters for 1242, 1254, 1260.
Vjrate transfer lines from existing transfer pump (Item 144) to each 'Jn^ to truck dock as follows:
HONS 036306
Appendix (j CEA 1800 Page 2
.. ;2 - Fromday tank to storage - to manifold station
...34 - Fromday tank to storage - to manifold station j0 - Fromday tank to storage - to manifold station 3248 - Fromday tank to storage -- to manifold station fcparate circulating lines on each tank.
.Mncs to bo 2" s. 3" IPS aluminum with single 1/2" copper tracer and insulated.
railroad
1. Extend spur track #10A, 125 feet and tie into existing track 10.
01 Equipment
'
See Equipment List and Summary -
0i Instrument items
See Instrument List and Summary
03 Setting and Testing Equipment
Area is accessible for truck and train unloading. High lift can be used advantageously.
01 Setting and Testing Instruments
.
Normal conditions.
0`3 Excavations For 100,000 gallon tank - 25' x 30' high
e
For good soil (301 J? x 15 feet deep) Ring Wall (25'0) Sandf ill
Pump Foundations
400 cu yds 10 cu yds 19 cu yds
3 x 2 cu yds Pipe Supports
6 cu yds
9 : 3 cu yds
27 cu yds
HONS 036307
Appendix G
CEA 1800 Page 3
For 5 storage tanks
For good soil
35' x 35' x 15' - 18,400 ft3 20' x 18' x 15' - 5,400 ft3
23,800
Total Excavation
Spoil Backfill
07 Foundations
880 cu yds
1,369 cu yds 1,300 cu yds
Pumps 4x2' x 31 x 2'
Pipe Supports 9 x 2-1/2 cu yds Loading Dock Miscellaneous
Base for 5 tanks 5 x .78 x 142 x 10/12 - 635 ft3 5 x 3.14 x 14 x 4* x 10/12 * 735 ft,
1T70 ft3
2 cu yds 25 cu yds
5 cu yds 5 cu yds 55 cu yds
Soil tests will be required, fid Supports, Platforms and Structures
Loading Dock - (2 required for biphenyl cars) Tank Platforms Ladder to top of biphenyl storage tank - 30 ft Grating Handrail Toe Plate 0X_ Building Items None 2.i Sprinklers and Fire Protection None required.
2 ton 4 ton
700 sq ft350 lin ft 350 lin ft
HONS 036308
Appendix >3 . CEA 190C
Page 4
jvyina
- em 401 - I*.j.-.henyl Storage Tank
)5 ft cf 4" IPS CS pipe for pump suction with <ne valve.
'0 ft of 2" IPS CS pipe for ciro. line with -. r.o valve.
LOO ft of 2" IPS CS pipe from unloading spot to tank with two
/a.', vv,.
'
20 ft t? 2" IPS CS pipe from pimp dischar.-e to Item _V2, e: t iphenyl storage tank, with t.wc valves.
200 ft of S'* IPS CS pipe from Building CF. to storage tank with two valves for stem supply.
2C0 ft of 1" IPS CS pipe for miscellaneous steam services at stor ig.-. tank.
Pi ic vis Piping -lx 1/2" OD copper tubing tracers with 2-1/21' insulation, 2" thick.
Stem Piping - 2" thick insulation.
Str-raua ranks (Ite.-n 558-562)
5 Cirti. Linus - 2 50 ft of 2" IPS A12 pipe with 5 AL valves.
5 Vent Lures - 51 ft of-3" IPS A12 pope with 5 AL valves.
200 ft of 1-1/2" IPS CS pipe for at earn to plate coils with .16 VilVOii .
Piping -lx 1/2" OD copper tubing tracer with 2~t/2" & 2-1/2" diameter insulation 2" thick. Steam piping - 2" insu lation .
nitrogen Piping
250 ft of 1-1/2" IPS CS pipe with 10 valves from existing nitrogen station.
Instrument Air Piping
200 ft of 1-1/2" IPS galvanized pipe with 16 valves. Tranafer Piping to Storage Tanks
Tie into existing lines at Tanks 9, 10, 11, (items 117, lie, 119).
Piping required: 200 ft of 2" IPS aluminum pipe with 8 valves.
HONS 036309
(Note for 1254, 1242, 1262)
Appendix G . CEA 1800
Page 5
;;ew 1248 line from existing transfer pump (item 144) piping required:
150 ft of 2" IPS aluminum pipe with 2 valves.
pining: 1 x 1/2" OD copper tubing tracer with 2-1/2" diameter insulation 2" thick.
Transfer Piping to Loading Station (Tank Car)
ppr 1242: 225 ft of 3" IPS aluminum pipe with 3 valves and *" - aluminum loading arm for tank cars.
fpr 1254: 225 ft of 3" IPS aluminum pipe with 3 valves and " aluminum loading arm for tank cars.
2j_J_2: 250 ft of 3" IPS aluminum pipe with 3 valves.
For 1248: 250 ft of 3" IPS aluminum pipe with 3 valves.
Piping: 1 x 1/2" OD copper tubing tracer with 3-1/2" diameter
insulation 2" thick.
Transfer Piping to Loading Station (Truck Dock)
For 1242: 100 ft of 3" IPS aluminum pipe with 1 valve.
For 1254: 100 ft of 3" IPS aluminum pipe with 1 valve.
For 1260: 100 ft of 3" IPS aluminum pipe with 1 valve.
For 1248: 100 ft of 3" IPS aluminum pipe with 1 valve.
Piping: 1 x 1/2" OD copper tubing tracer with 3-1/2" diameter insulation 2" thick.
rransfer Piping to Drumming Station
For 1242: 100 ft of 2- IPS aluminum pipe with 2 valves.
For 1254: 100 ft of 2" IPS aluminum pipe with 2 valves.
~or 126C: 100 ft of 2" IPS aluminum pipe with 2 valves.
For_1248; 10C ft of 2" IPS aluminum pipe with 2 valves
1_p 1 nq; 1 X 1/2" OD copper tubing tracer with 2-1/2" di insulation 2" thick.
Work
HONS
036310
i ! ;)__rloctrical
.
Appendix G CEA 1800 Page 6
install 4 x 15 HP motors for pumps.
.so interlocks or alarms required.
install 8 street light type, 400 watt mercury arc ing dock, tank farm perimeter and area lighting.
fixtures
for
load-
Install 8-175 watt mercury arc fixtures over tank farm area. 1 4__ site Preparation
None
5 Sewers and Drains
None
,16__ tnderground Mains None
__ yards, Roads, Fencing
Chat will be placed around storage tank area, depth 12".
ror item 401
2,500 ft2
For 5 Storage Tanks 18 Railroads
1,600 ft2
Spur track #10A will be extended 125 ft and a switch installed at the end to bring the spur back into main track #10. Existing bumper will be removed.
.1.2__ Insulation
PlEina* Insulation is covered in the category #11 - Piping.
i
;tem 401 - Thick, 1-1/2", insul. * with weather barrier.
Spec.
No.
100
(Calc,
silicate)
Side wall - 7fDH " 3.14 x 25' x 30' - 2,360 ft2
Top
- 7Td2 * 3.14 x (25)2 44
,,,,,, , 2 490 ft
2,850 ft2
HONS
tern 558 - Thick, 1-1/2", Insul. with weather barrier.
Spec.
No.
100
(Calc.
Silicate)
036311
Side wall - ftm - 3.14 x 13' x 12' = 490 ft2
Remaining area to be spray covered with asphalt mastic. Spec. no. 700
cork
filled
Side Wall
7
Top 77~P
4
.78
(13)'
Appendix G CEA 1800 Page 7
490 ft, 132 ft* 622 ft2
Item 559 - Same as item 558
Item 560 - Same as item 558
Item 562 - Same as item 558
~6- ~ Thick' 1-1/2", Insul. Spec. No. 100 (Calcium Silicate) with weather barrier.
Side Wall - 77bH = 3.14 X 13 X 24 980 ft
Top area to be spray covered with cork filled asphalt mastic, Spec. #700.
1 Top
132 ft2
20 Painting 1
Spec 502 for all steel items.
1 90 Dismantling
Remove pump 4247 and motor 9905 now on Tank #10,(item 118) .
1 Dismantle 3 X 14,000 gallon underground storage tanks and associated equipment:
1 Item NO. Equipment No.
Description
148 21-0768
10' Dia. X 26' long U.G Hor. Tank
149 19-0585, 66-0853
Pump and Motor
\ 150 21-0769
10* Dia. X 26' long U.G Hor, Tank
151 19-0584, 66-1501
Pump and Motor
\ 152 21-1310
10' Dia. X 26' long U.G Hor. Tank
153 19-0929, 66-0856
Pump and Motor
1 93 Relocation
Replace two existing pipe supports going out to present tank car loading dock.
HONS 036312
r
,4 Monsanto
, ii tnor.om
B Howard - St. Louis
JL*t
i ^uguat 28, 1967
J
>
PROJECT LOSS PREVENTION REPORT 67-65 CEA-1800
Yates (Project Manager)
R. E. Doerr R. E, Howard
J. L. Mathews
H. B. Patrick - WGK S&PP Project File S&PP Location File
J
J COPIES TO THOSE PRESENT J. R. Fullgraf
H. D. Gabelman
I
R. J. Green W. B. Howard
J. MacPherson - Anniston
M. J. Pistek - WGK
H. F. Ray
- WGK
R. P. Stevens
R. S. Yates
4 DATE AND PLACE OF MEETING August 15, 1967, Creve coeur, Missouri.
J CEA-1800 increase Liquid Aroclors' Capacity, WGK Plant, Sauget, Illinois.
J This project is for installing a new aroclor manufacturing plant and a tank farm. The capacity will be 40M ppy. The capital is approximately $1.4M; completion target is approximately January,
] 1969.
The project includes installation of a 100M gallon biphenyl storage tank and extension of trackage for access to this tank. > . Two biphenyl unloading docks will be provided. The drainage
from the 100M gallon biphenyl tank will be away from the process.
PROCESS
1. Biphenyl Storage Tank This storage tank will be air blanjested; it was stated that contact of the biphenyl with air will not result in deleterious effects on the biphenyl. The flash point of biphenyl is 235F. It was thersfors . agreed that low pressure steam (5 psig max.) would be used for heating the large storage tank, the 25,000 gallon tank, and tank cars, in order to avoid heating above the flash point.
HONS 036313
0)
2 Addition of Ferric Chloride to Biphenyl Mix Tanks
The
ferric chloride is added batchwise to the mix tanks by
opening the tanks and dropping in the solid. It was agreed
that, in order to prevent formation of any flammable mix
tures above the biphenyl in these tanks (Nos. 403 and 404),
the temperature of material in the mix tanks will be held
below the flash point.
3. Chlorination System
The chlorination proceeds at a tempera
ture of about 150C; approximately 550 BTU's are evolved per
pound of chlorine added. Heat removal is accomplished by
circulating batch material through an external air cooler
and back into the chlorinator. Safety provisions include
the following:
(a) A high temperature sensing element in the chlorinator mass detects high temperature, shuts off chlorine, and alarms.
(b) Circulating pump shutdown (motor circuit detection) shuts off chlorine feed.
(c) A temperature detector in the circulating line is used
for temperature control in the system. When this ele
ment detects low temperature it alarms and also shuts
off the air cooler fan.
.
(d) A temperature detector in the chlorinator mass (separate from No. a. above) alarms at a high temperature which
is lower tHan the temperature at which the element in a. alarms and shuts off chlorine.
FIRE PROTECTION A new open type structure will be erected adjacent to Building CR.
No automatic sprinkler protection is required for this structure. It should be noted, however, that a spill of biphenyl at a tem perature above its flash point (235F) has resulted in fires.
The existing hydrant protection is considered adequate to extin guish such a fire.
LOSS EXPOSURE
The therminol furnace consists primarily of a
cylindrical combustion chamber containing finned tubes. Although
an explosion in the combustion chamber is possible, the combustion
chamber could in all probability contain the explosion pressure.
There appears to be no major hazard from this source. The stack
might of course be blown off.
' HONS 036314
/a
/J/r
(* )
3
A more likely source of loss exposure would appear to be the burning of a tube in the therminol furnace. A tube could bo replaced within about two days if one is in stock. On a soldout basis the business interruption loss would be approximately $20M. The repair cost was approximated at $3M.
LOSS PREVENTION GUIDE
Attached to R. S. Yates' copy of this
report is a copy of Form G-1425, loss Prevention Review Guido,
which can be used as a safety checklist for this project.
'
LOSS PREVENTION REVIEW BY PLANT The S&PP Branch of CED docs not plan a complete review of design prints for safety provisions. S&PP requests plant personnel, including plant safety personnel, ' to follow the development of design prints and to check the pro
gress of construction with particular emphasis on personnel safety and loss prevention.
SAFETY MANAGER R. J. Green will be Safety Manager for this project. Please contact him for reviews during the design phase of this project.
La)- . H W. B. Howard
MOWS 036315
^Monsanto
i
(,,,B ,Nwt k
W. B. Howard - General Offices
... August 29, 1967
"
J ........ .
PROJECT LOSS PREVENTION REPORT 67-64 CEA-1430
Iro
j
/r .: Mr. R. S. Yates (Project Manager)
COPIES TO THOSE PRESENT
R. E. Doerr
R. E. Howard J. L. Mathews P. K. Ward - Anniston S&PP Project File S&PP Location File
J. R. Fullgraf H. D. Gabelman R. J. Green
J W. B. Howard J. MacPherson - Anniston
M. J. Pistek - WGK
J H. F. Ray - WGK R. P. Stevens R. S. Yates
J
A
A A A
A
DATE AND PLACE OF MEETING Missouri.
August 15, 1967, Creve Coeur,
CEA-1430
Increase Liquid Aroclors Capacity, Anniston
Plant, Anniston, Alabama.
This project is for a new tank farm, mixing area, flaking area^ and drumming area, capital will be approximately $1.6M; completion target is January, 1969. Although no additional capacity is claimed under this project, the operation will be changed from three shift, seven day, to one shift, seven day.
A flaker will be added for solid aroclors and another flaker for biphenyl. Exhaust systems will be provided to remove fumes from the flakers.
A PROCESS 1. Mix Tank
Solutions of aroclors are prepared in toluene
A and xylene in a mix tank. The toluene and xylene used for this purpose are pumped from drums directly into the 2,000 gallon mix tank. This tank is jacketed for steam
, '
and for water. The tank will be nitrogen padded.
A 2. Biphenyl Surge Tank
The flash point of biphenyl is
235F. The biphenyl surge tank in the flaking area will
A
be heated, but only to approximately 80C. The biphenyl will thus be below the flash point.
0 /&/%>{b ty -Z" (?)
MOMS 036316
:ii *
3 3 3
L
3 3 3 ,3 3
,1
3J
J_
3 ] 3 3
Mr. R. S. Yates
-2-
August 29, 1967
3. scale-up of Flaker Size The new flakers will be of
significantly larger size than the present flakers. The
aroclors are expected to perform on the new flakers as
well as, or better than, they do on the present flakers.
The biphenyl gives some problems in flaking with the
present flakers, and some of these problems may continue
with the new flakers. Although there is a scale-up factor
with the new flakers, no significant scale-up problems
are anticipated.
'
FIRE PROTECTION
A 120' x 60' x 1 story metal siding on
steel frame prefabricated type building will be erected north
of Bldg. 27 for flaking and drumming of aroclors.
It is recommended that this building be provided with an
ordinary hazard wet pipe system of automatic sprinklers. The system should be supplied from a feed connected to the fire main in Fifth Street with a post indicator type shut-off valve located at least 25 ft. from the proposed building.
LOSS EXPOSURE The maximum probable loss is anticipated to occur from the scarring of an aroclor flaker roll. Re surfacing of the roll would require about one month. On
this basis the BI loss would be approximately $100M. Equip ment repair costs for the resurfacing would be approximately $4,000.
LOSS PREVENTION GUIDE
Attached to R. S. Yates' copy of
this report is a copy of Form G-1425, Loss prevention Review
Ouide, which can be used as a safety check list for this
project.
LOSS PREVENTION REVIEW BY PLANT The S&PP Branch of CED does not plan a complete review of design prints for safety provisions. S&PP requests plant personnel, including plant safety personnel, to follow the development of design prints and to check the progress of construction with particular emphasis on personnel safety and loss prevention.
SAFETY MANAGER R. J. Green will be Safety Manager for this project, please contact him for reviews during the design phase of this project.
R. J. Green
v
-H A
W. B. Howard
P
T (e)
MQNS 036317