Document 2JN6R23DooGDVRDmb4y7z0dKp

Anniston, Alabama February 21, 1964 OUT-OF-SIGHT - OUT-OF-*1TM" - nnn/vR. Plan for; Elimination ol^h1 orinator Wrappings increasing Ghlorlnator Capacity - 12/10/62 R. G. Moody . V. Molloy I request that the Aroclor Standards be modified to reflect the 600 lb/day loss of Biphenyl into the trapping system. This loss, based on a 30-day month, amounts to $1,000/month. This is a minimum figure. This loss is reflected as benzene usage and is a real cost to the department. The loss is due to Inadequate scrubbing equipment in the chlorlnators and should not penalize our obscure actual Biphenyl operations. This move will allow Biphenyl to meet 1964 raw material objectives. These trappings can be separated in a low velocity chiller, stored in existing Biphenyl feed tanks, and be returned for the manufacture of 1248 with a minimum expenditure. B. 0. Severson /md PCB-ARCH-EXT0377242