Chris E Shoop 02/20/2002 05:20 PM
To: cc:
Subject:
Robert F Pinchot/DEV/AE/DuPont@DuPont. Debbie J Mulrooney/AE/DuPont@DuPont Robert I Wevodau/SE/DuPont@DuPont, Ravinder Singh/CL/DuPont@DuPont, George L Clowes_Ji7CL/DuPont@DuPont, Stephen J Gissy/AE/DuPont@DuPont Emission Estimates for 2003 Production
Rob/Debbie,
Here's the file to use for emission estimates based on 2003 production forecasts.
Note that the FEP data did not identify which line was planned for use so I split it 35/35/30 on lines 1,2, & 3. Recent history has shown smaller use of line 3 but I expect that will grow to a higher percentage.
Line 3 has the highest stack.
Note also that this sheet does not show the use of any operation without the use of the deep-bed scrubber. We plan to ask for 3 months of operation in this mode for 2003 and 6 weeks thereafter. We might have no use of this scenario if the deep-bed scrubber is highly reliable.
Thanks, Chris Shoop
2003 Estimates-020220-xls