INTER-COMPANY AND OFFICE CORRESPONDENCE
rot P. Godin/
W. Rines1^
D. Tarr P. Tessier
SUBJECT:
VCM ALARM REDUCTION PLAN
From:
S. Graham
located at: Leominster, Ma.
ate:
December 6. 1981
{
VCM ALARM REDUCTION PLAN
The purpose of this plan is to work more effectively on problem areas of Fugitive VCM emissions. The method to be used will be the assignment of designated target areas to specific people within the department. It should be noted that even if you are not specifically assigned an area your normal contribution in this area is still expected. An assigned area'will be investigated, and a written report will be produced that will lay out necessary steps that need to be taken to resolve or reduce the
problem.
The number of alarm printouts of greater than 5ppm's or that have a duration of 30 minutes or more will be used to monitor progress.
Below are listed the target areas, assignments, and comments about them;
1) Manhole covers - Assigned Personnel; Steve Graham, Don Tarr, Phil Tessier, Wayne Rines, and Paul Godin. This is the number one pro blem for all the above listed personnel. Possible solutions are;
A. Gasket change - Contacted Malcolm McKenzie through Reggie Doherty. He is an area representative for our gasket manufacturer. A model gasket will be made that will have a lower lip for support and alignment. He will call me with a price quote and the gasket should be ready in mid January.
B. Air Pressure - A minimum of 85 psi is needed for proper air gun effeciency. 90psi would be more desirable.
C. Air Guns - Air guns must be effectively maintained and ad equate spares provided to ensure enough properly working guns.
0. Lugs and Washers - Must be in gocd working order and in adequate supply for manhole covers.
E. Poor Covers - Need to be identified and resurfaced.
F. Operators - Will need retraining where indicated.
2) Undetermined - In order to limit the number ni undetermined alarms
it appears necessary to monitor stack 300. Sample results from the
stack show high readings con-.*1.He with use
imversal ]et ind
times of manhole cover leaks. The proper control of the two sources
would allow readings of belov. loppm's at stack
BOR 000145
\ICM ALARM REDUCTION PLAN 12/6/83 PAGE 2
At present since stack 300 has not been monitored on a regular basis the readings are higher than if some control efforts would be put on it. A high level of emissions at stack 300 will result in various alarms that have otherwise been listed as undetermined. (Assigned Personnel: Steve Graham).
3) Transfer System - The two most frequent transfer associated leaks are sampling of batches and cleaning of transfer baskets. Bldg. #1 exhaustor system needs upgrading. Improvement of sampling technique is also possible. A work order has been submitted to upgrade Bldg. #1 lower exhaustor system. (Assigned Personnel: Wayne Rines).
4) Slurry Columns - The bump and flush of the slurry strippers often give numerous alarms. This area needs investigation. (Assigned Personnel: Don Tarr).
5) Chem. Add Valves - Either upgrade valves or the use of some sort of screw in plug will be investigated. (Assigned Personnel: Steve Graham).
6) Unloading Stations - Swivel joints and tank car connections are sources of leaks. Investigate method to reduce these areas. (Assigned Personnel: Paul Godin)
SPG/cmb
cc: D. L. Young S. Graham
itepnen p. branam E.P.A. Coordinator