Document 0JnbXZMy5jdL5zYdBKkpQ5nnM
SOLV/EDC & CMP PLANT NOTIFICATION OF PROCESS CHANGE CHECKLIST
Type: LEVEL 1 (minor) LEVEL 2 (moderate) 3 LEVEL 3 (major)
Originator: James Cook________________
Date of Origination: 05/30/97__________ Plant: Methanes
Actual Date of Change:
Area:
Methanes Loadrack
Equipment: Waste Pot
Permanent El Yes Temporary Yes From: To:
Description and Location of Change (Scope): Change from 4" Spec J to a 4" Spec LI 05 ball valve.
Loadrack Waste Pot
_________
___________________________________ ____________________
Technical Basis for Change: Carton Steel valve Is not holding up in this service. Potential for wet process is high and corrosion is affecting the vavle.
No performance or flow issues associated with this vavle.
Impact on: Safety SLoss Prevention nEnvironment Health Quality Production other: Leaks due to corrosion
Type of Change:
Alarm Shutdown Point instrument
Process Computer Control Addition/Removal of Equip. Piping Modification
Equip./Material Modification Chemical Job Procedure No.
Process Set Point Change H Piping Spec. Other:
1 Pre-modification Checklist: Applicable
OApplicable Applicable Applicable Applicable Applicable Applicable Applicable Applicable Applicable Applicable Applicable Applicable Applicable Applicable ElApplicable Applicable Applicable Applicable Applicable ElApplicable ElApplicable ^Applicable Applicable Applicable Applicable (^Applicable Applicable Applicable Applicable Applicable
Written job scope and sketch of proposed change; POD# Project economics; attached. Consult piping and equipment specifications; Spec. # Comply with Engineering Practices. Consult Technology Center or comply with Tech. Ctr. guidelines. Equipment access/congestion considered. Consult Environmental function Environmental project checklist complete. Chemicals listed in the (TSCA) inventory before use. Perform Reactive Chemicals testing or review. Consult Safety function for compliance with S&LP and Block requirements Consult Process Safety for impact on PHA(F&EI, CEI, & Fire protection). State Fire Marshall notified. Consult Industrial Hygiene function Consult maintenance/Reliability Eng. Consult Instrument function. Consult Electrical function. Consult Analyzer function. Consult/Inform Computer/Programming Support. Consult Area Engineer. Consult Operations. Consult Area Technologist Consult Inventory Management Consult Process Engineering. Evaluate and modify relief system. Work Order written. (List them) Consult Construction/Small Projects Consult Site Logistics Consult Quality (Customer Notification ?) Other (Name them)
_____________ J
Follow-up Signature
Date
Yes Yes Yes Yes O Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes D Yes Yes
_ _ _ _ _
_ _ _ _ _ _ _
=0=1?
ME27
HO7
Page 1 of 4 RR 4/96
DOW CONFIDENTIAL INFORMATION
MOCChecklist.doc
DO A 026592 CONFIDENTIAL
APPROVALS: Originator:
D.: 5 - 30 - 97 Date: >' L~ 97
Date: 6-
_________
f ..Post-modification Checklist: (BEFORE START-UP) Applicable
Applicable Perform prestartup audit: major equipment addition/mod. Lvl
3;attach.
Applicable PSM files updated(such as piping circuits).
Applicable Project list updated.
Applicable Documented in Operating Discipline Library
Completed Job Procedures reviewed by:
Operations Safety Envir.
Emergency Procedures
Training Aids (IPT, etc.)
Controlled copies of Critical Oper. Procedures updated
Safety/Environmental (cleaning, vessel entry, red tag)
Update plant Roundsheets, forms
Applicable Plant equipment files updated.
E3Applicable P&ID's, process flow sheets, and plot plans updated.
Applicable
Personnel trained on the change. Method:
Applicable Critical instrument checklist updated.
Applicable Updated HAZCOM Manual & equip. List.
Applicable Pressure vessels, PVRV's, & PRD registered.
Applicable Instrument loops checked and documented.
Applicable Field switches, equipment, & MCC starters checked & labeled.
Applicable Log sheets/controlled forms updated.
Applicable GPI flow diagram & history/EDAS updated.
Applicable GEMTS, PPM, & MSMS updated.
Applicable Mod V program change checklist completed.
Applicable Equipment RTO Checklist completed.
Applicable Follow-up action plan completed prier-Jo Final Approval(attached).
APPROVAL: Final Approver:
O il
Follow-up
Yes
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes ^ Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
Signature
-7Dale
s-zb-r?
6Date: hfc)
\
Page 2 of 4 RR 4/96
DOW CONFIDENTIAL INFORMATION
MOCChecklist.doc
D & 036593 confidential
Methanes MOC Training Signoff Sheet MOC TITLE: Mark the box next to the appropriate individual that the communication/training is intended to reach.
DATE:
X Taylor, D. X Haney, J. >< Kelley, K.
A Storm, C. Hunt, L.C.
X Rolke, R.W. Stallcup, J.S.
White, W.S.
Young, Barry. KtUa-VtV- J P
434501
L-kfct
091506
uNlil
239424 249497
> (
TzdocZ
fliCm
b/Hfo Ul\i(W
088600
097946 Ttt
240558
434499
433620 4 3 V4S1 c*L_J T-------4-4-v?r
Breaux, R. Beieler, B. Bickham, C.J. Cook, F. Cavalier, N. Grant, W.C. Gravouilla, D.C. Jackson, R. Metrejean, D.J. Harrison, W.
433793 281334 432411 431977 241889 432637 434255 433457 241773 096480
X Michel, A.
X Cook, J.
X Dugas, D. Brown, M.S. Rizzo,G. Johnson, J. Donatto, B. Carrier, B.P. Witt, J. Vavasseur, T. Landry, C.P.
432203 433658 432407 433928 432580 432541 434031 085908 241996 434160 434292
4-V-97
b/dki
Bishop, C.E. Bourg, J. Davis, C. Ekey, J. Jack, O.J. Looney, R. Wolfe, D. Millender, R,
432026 094487 433015 202669 094373 276854 246186 432751
X Clebert, J. Mathis, J.
432385 432997
(pkhn
Simonson, F. X Armond, N.L.
432477 098664
, sj /
L
21 Doucet, K
432056
\
PI 02ps3
Page 4 of 4 RR 4/96
DOW CONFIDENTIAL INFORMA TION
MOCChecklist.doc
DO A 026594 CONFIDENTIAL