Document zQJqE1BQwEjyzK37r3nazojM6
T. H, Huffman
To:
From:
Dote:
Subject:
D. C. Skokna April 22, 1991
ABERDEEN MONTHLY PROGRESS REPORT MARCH, 1991
Safety
There were two first aid and one recordable (RWC) injuries reported in March. The recordable injury (RWC) involved an operator who suffered a corneal abrasion to his left eye. At month's end, the plant's employees have worked 4,287 days (5,726,980 manhours) since the last lost time injury.
FY1991 Kev Statistical Information
March
Y.T.D.
PVC Production, MM Lbs. Reactor Stream Factor, % Resin Quality, % Prime VCM Efficiency, Lbs./Lb. Flexible Compound Production, MM Lbs. Flexible Compound Quality, % Prime Rigid Compound Production, MM Lbs. Rigid Compound Quality, % Prime Plasticizer Production, MM Lbs. Plasticizer Quality, % Prime Energy Use, (EUI, %) Fixed Cost Variance, $M Variable Cost Efficiency Variance, $M
Operations
39.4
86.0
97.6 1.0290
3.2 97.2
5.6 99.7
1.7 87.8 < 13.7> 53.9
< 2.6>
240.5 87.8 98.4
1.0243 25.6 96.7 28.6 99.6 9.6 85.0
< 8.0>
149.9 < 75.3>
Three rotary dryers were successfully converted to the new VCSM
system; the remaining dryers will be converted in April, Dump header modifications in the New Module significantly reduced 5385 hard particles from sixteen to one.
In the compound units, costs and inventory control continued as high priority.
Costs
Fixed costs were $53.9M favorable primarily due to below budget benefits clearances and MM&C expenditures.
Variable costs were essentially at budget for all units.
VAB.0001189749
T. H. Huffman
4/22/91
Aberdeen Monthly Progress Report - March, 1991 Page 2
QMP
All plant natural teams met during March. The Laboratory MD" shift made their management presentation. Their project will improve efficiency and improve the appearance of the lab to our customers.
D. C. Skokna Plant Superintendent rah
..................in nwmmmmmm
VAB.0001189750
Houston
J. D. Burns
X
R. T. Ferrell
X
T. H. Huffman i
C. J. Matson
D. F. Harman
H. R. Flammer
R. R. Smith
B. J. Bean
R. H. Gerlach
R. D. Gamblln
Austin
R. L. Foe
X
H. J. Hall
Oklahoma Cltv
H. D. Garrison
LCVCM Plant
P. D. Carrico
LOOP Plant LCLAB Plant
J. Friend
J. W. Ware
X
Baltimore Hammond
L. R. Bauer J. Pavao
X X
Blane
C. R. Miller
Premiere
P, L. Foote
Aberdeen RWS/DCS (File Copy), TJA, JBA, JEB, JME, SCH, DAB, DAM, RBN, JEN, JDO, BLT
X X X X X X X X
X X X X
X X
VAB.0001189751
SAFETY - B. L. Trego
March
Fiscal Y-T,P, 199;
Fiscal Y.T.D. 1990
First Aid OSHA Recordable
Total Injuries
297
X _6 __3
3 15 10
Number of Restricted Workday Cases
0
3
2
Number of Lost Workday Cases
0
0
0
Injuries bv Department
Vinyl Operations Compound Operations Maintenance Laboratory Receiving/Warehouse Office
Totals
120
142
076
00 1
00
X _2
0
3 15 10
Injuries bv Type,
Cuts and Abrasions Eye Injuries Burns Bruises Strains/Sprains Stings Other
Totals
032
111
02 2
131 030
002
X _2
3 15 10
Non-Occunational Injuries
Lost Workday Cases Days Lost
16
32 110
3 84
Safety Record
Last lost time injury - 7/5/79
Days since -
4,287
Employee hours since - 5,726,980
On March 31, 1991, the employees of the Aberdeen plant completed 4287 days with no lost time injury.
Topics for the plant safety meetings during the month were:
Injury
Reporting, Power Failure Procedures, 3-M Air Hat Cleaning, Hearing Pro
tection, Respiratory Protection, Hazardous Waste Disposal, and Lab Lead
Handling Safety.
VAB.0001189752
SAj^n - Continued
Respirator fit testing is being done by the plant nurse. This is being accomplished through the use of the new Portacount fit tester.
Routine dosimetry results for the month were:
Chemical
<_________________________
Number
VCM Lead Total Particulates
72 100.0 4 100.0 2 100.0
Monthly Inlurv Summary
> PEL HuBk Egrcepp
00 00 00
FA RWC FA
Adm. Services Vinyl Compound
PVC resin, both eyes. Corneal abrasion, left eye. Contusion, left hand.
*
VAB.0001189753
OPAUTY MumaMf rancKgg . T. J. Arbelter
All of the plant's natural teams met during the month March.
The Laboratory D-Shift Natural Team made a presentation to manage ment on March 1. The team's goal was to reduce inefficiency and congestion in the lab and make the lab more aesthetically pleasing to visitors (i.e., customers).
The team accomplished their goal by relocating test equipment, work tables and file cabinets, and by building a new resin work table from "scavenged" laboratory table tops (a new table costs $3,000!). The team also purchased a computer desk in order to locate the resin computer adjacent to the resin work desk.
Quantitatively, the team estimates the relocation of items in the lab will save ten technician minutes per shift. Qualitatively, the
n believes the improved work environment in our lab will have a very positive impact upon the men and women working there. Pro viding a clean, efficient work-place inspires people to be more efficient themselves.
The Aberdeen Plant's Q-Scorecard performance as of March 31 is:
Item
Natural Team Activity Quality Goals Cost Control Safety Waste Minimization Work Unit Enhancement Linkage
Wt.
20% 10% 15% 20% 15% 10% 10%
7 7.57 8.29 8.93 9.5 5.06 1.92
Points
1.4 .76
1.24 1.79 1.43
.51
7.32
The scores reported above are support card scores for each activity).
the average of all departmental line item (except natural team
,.T
VAB.0001189754
D. G. Skokna
Variable Costs
Product
Product Mix
PVC Flexible Compound Rigid Compound Plasticizer
Total
$ 86.2 34.3
213.6 < 0,1>
$334.0
<$17.0> 2.2 8.0
____4x2 <$ 2.6>
$274.2 < 138.3> < 206.1> < 70.9> <$141.1>
$343.3 < 101.8>
15.5 < 66.8>
$190.2
Variable Costs: All units were essentially at budget.
Price Variances:
- VCM Natural Gas m Pigments, Colors m Phthalic Anhydride Plasticizers Alfol* 610 m Resin to Flexible Compound Resin to Rigid Compound m Other Price Variances
Total
$267.9 16.1
< 15.4>
< 21.1>
< 24.5> < 45.4> < 53.5> < 164.1>
<$141.1>
Fixed Cost Variances
Payroll and Benefits MM&C Miscellaneous TI&D Clearances
Total
$ 23.1 43.7
< 16.6> 7.8
< >tl>
$ 53.9
Payroll and Benefits - A favorable $59.3H benefits clearance was partially offset by an unfavorable payroll variance of $36.2M.
MM&C - The favorable variance was a result of our continuing cost minimi zation efforts.
VAB.0001189755
COST YAMAHA - Continued Miscellaneous
m Moving, Home Assistance - <$14.1M> Outside Professional Services - $14.7M m Unclassified - <$31.9M> (This was due to the annual physicals) m Operating Supplies - $18.OM
VAB.0001189756
Vltffl - J. D. Olson, D. E. Knittig
Safety
The Vinyl Department had one restricted work case injury during March. A vinyl operator scratched his eye on the corner of a box. An investigation was completed and the team presented recommended safety procedures.
The monthly safety meetings were conducted by each shift supervisor instead of the one standard meeting by safety. These meetings focused on individual shift safety concerns.
General
1. Dump header revisions in the New Module were completed. The revisions reduced hard particles in the 5385 from an average of about 16 to 1.
2. Dryers #1, #4, and #5 were converted to the new VCSM system this month. All dryers will be converted by the end of April.
3. The resin raw materials in the 744 account were valued at $370.5M. An early shipment of Alcotex that arrived prior to month-end caused a majority of the increase in this account.
A test of a new rinse nozzle in D-745 was started during the month. The nozzle is designed to keep the reactor "ultra" clean and reduce hydroblast cycles. Preliminary results are encouraging with contamination numbers averaging about seven total contaminants.
March
- Production, MM Lbs. - Daily Rate, K Lbs./C.D. - Capacity Utilization Factor, % - Total Reactor Charges - Charges/C.D. - Reactor Stream Factor, % - Rotary Dryer Stream Factor (#4-#8), - Fluid Bed Dryer Stream Factor, % - Resin Quality, % Prime
%
39.4 1270.9
101.2 939.0
30.3 86.0 89.4 92.6 97.6
240.5 1321.4
105.2 5612.0
30.8 87.8 92.6 96.3 98.4
m Operational downtime (recovery scheduling conflicts, charge/rinse water conflicts, Q.C. data delays, dump conflicts and inventory control).
Hours 395.0
wmmmmmmmmmmammmmmmrnemm
mmm
mm****
VAB
VINYL - Continued
Reactor Downtime
a Maintenance downtime (X-ray VC line on D300 and D400, D500 seal change, gearbox maintenance on 0742 and 0743, dryer conversion to VCSM, power failure, D743 condenser drilling, New Module dump header revisions, installation of check valve in Old Module water line, 0745 rinse nozzle installation.)
Drver Downtime
Operational downtime (centrifuge plugs, dryer cleaning, flameouts).
m Maintenance downtime (centrifuge maintenance, dryer conversions to VCSM).
m Reactor limited production.
Hours 644.0
% of Total Downtime 17.3 79.2 3.5
Key Maintenance Work - J. B. Autrey, S. A. Truitt
The reactor seal on D500 was changed. The seal was not getting enough flow for flushing; the throttle bushing did not have the required clearance for proper flow. The old seal was rebuilt as a spare.
Reactor 743 and condensers on D742 and D744 were brought down for hydroblasting to control contamination.
m The safety discs on D745 were changed on the annual schedule. While the reactor was down, it was hydrobiasted.
m The input shaft seal on D742 gearbox was leaking oil and was
replaced.
i The gearbox on 0744 failed and had to be replaced. The gear box on D741 was pulled and set under D744. The spare was installed under D741 because it required a different founda tion plate than what is under D744. A new gearbox is on order as a spare.
The exhauster shaft on dryer #6 was replaced when a crack was discovered on the shaft.
No major valves were changed in the vinyl unit this month.
COMPOUND - J.E. Nickerson, M. R. Kane
Safety
The Compound Department had no OSHA recordable Injuries in March. The topic of the monthly safety meeting was "Housekeeping".
General
Control of costs and inventories continued to be a high priority during March. Lines were operated only on an as needed basis and operators from
shutdown lines were utilized to cover vacations and other absences to reduce
overtime costs.
Repairs to the Line I Banbury motor and a Line V Orbitran (control system) failure were responsible for some abnormal maintenance downtime.
Conoound Production
Operating Psvs
Line I Line III Line V
Total % Prime Capacity Utilization Factor
22 27.5
6.5
Downtime
Line I
- Banbury Motor Maintenance - Product Changes - Miscellaneous Maintenance - Dicer Offline - Mill Maintenance - Quality Problems & Control - Waiting on Raw Materials
Line III
- Quality Problems & Control - Product Changes - Miscellaneous Maintenance - Mill Maintenance
Month Av./Dav
1075 1856
237 3168 97.2 40.4
49 67 36
Hours
Plscal Y
9492 14618
1469 25579
96.7 55.9
156 97 61 50 15
11
4
127 73 52 25
A
VAB.0001189759
COMPOUND - Continued
LineV
- Orbitran Failure - Miscellaneous Maintenance - Waiting on Raw Materials - Quality Problems & Control - Product Changes
Operating Daws
Rigid Compound
29
% Prime
Capacity Utilization Factor
5553 99.7 93.5
83 7 7 3 2
191
28583 99.6 80.9
Downtime
Hours
- Miscellaneous Maintenance - Quality Problems & Control - Product Changes - Waitine on Raw Materials
102
69 54 14
Operating __ Da
Month Avg./DaT Fiscal T.T.D.
Plasticizer
31
% Prime
Capacity Utilization Factor
1653 80.6 87.8
9604 84.9 85.0
Kev Maintenance Work - J. B. Autrey, S. A. Truitt
The drive end shaft on the Line III ribbon blender was reworked. The shaft was worn from bearing failure.
The Line I Banbury motor was removed and checked to determine the cause of an overload situation. The motor was cleaned, bearing replaced and load tested. No problems were found with the motor, gearbox or Banbury. The cause of overload is believed to be related to product formulation and the Banbury operation sequence.
The gearbox on Line III "B" blender was rebuilt and placed back into service. The rebuild was required due to worn gears. The motor was also repaired; it had bad windings and bearings.
Line V Orbitran had the CPU board, 1.0. buffer board and the eight-bit 1.0. board replaced.
VAB.0001189760
R. E. Folic, S. G. illlasn, M. R. Kane
PROJECTS IH PEVELOFHEHT - GEHERAL Vlnvl Area HA2QPS
A Hazards and Operabilities Study (HAZOPS) of the old reactor module was begun in early April. An initial two weeks of team meetings are scheduled in April. It is expected that four to six weeks will be required to complete the Old Module. Additional time will be scheduled later in the year.
A project is being initiated to determine the capabilities of the existing vinyl area cooling towers. The project will determine the effect on cooling requirements o-f increases in production due to the cleanwall and VCSM projects and other production increases pro jected over the next two to three years.
Reactor 745 Sorav Nozzle
A new rotating spray nozzle is being tested in reactor 745 for washing the shell between batches. This nozzle replaced the old stationary, low impact nozzle. After one month in operation, the nozzle has performed well. The potential benefits are reduced resin contamination and reduction in reactor downtime to hydroblast the walls. Plans are to install one in D700 if this one continues to perform well.
vcsm
Conversion of all the rotary dryers was completed in early April. All dryers started up without any major complications. The fluid bed dryer will be converted in mid-April. Operator training on the reactor operations phase will be conducted in May. The project continues to progress as scheduled.
foM Two ftectftjp
We are working with Conoco to determine the feasibility of reclaim ing scrap resin from old pond #2. A preliminary design was com pleted by the plant to evaluate reclamation of this resin. This information was used for comparison to contractor bids.
VAB.0001189761
NSINEERINS - ^ FOLK, 3.C. HILLHAN, M.S. KANE
ABERDEEN CHEMICAL PLANT APPROVED CAPITAL PROJECTS
AFE NUMBER
A519 A649 A909 D511 D629 D749 D849 D859 DB99 F699 F779 6659 QB39 D570 0580 D600 F650 F660 6560 6610 6630 H500 H510 H620 H501 H521
*
PROJECT DESCRIPTION
STATUS
PLANT ELECTRICAL UP6RADE VINYL CONTROL SYSTEM MODERNIZATION INERTS REMOVAL MODIFICATIONS VCH UNL0ABIN6 MODIFICATIONS COMPOUND REBLEND TRANSFER SYSTEM LEAS HANDLING AND EXPOSURE REDUCTION CQHPQUND LINE 3 SEMI-BULK LEAD HANDLING COMPOUND SILO BRIDGE BREAKING RAILCAR CLEANING RACK LON MOLECULAR HEIGHT RESIN EXPANSION DRYERS NO.4 & 5 CONTAMINATION REDUCTION NEN DRYER BA6HQUSES PLANT MATER RECYCLE OLD NODULE RECOVERY SYSTEM ACCE55 RECOVERY VACUUM PUMP PRE5SURE RELIEF PLASTICIZER LOADING AND UNLOADIN6 REVISIONS
5303 RESIDUAL VCM REDUCTION DECALCIFIED MATER
TC SPILL CONTAINMENT
TC COMPLIANCE PROJECT
REACTOR SLURRY STRIPPING OPTIMIZATION PLANT MATER SYSTEM HEST INCINERATOR REPLACEMENT EAST INCINERATOR REPLACEMENT MISCELLANEOUS CAPITAL PROJECTS < $15M REPLACEMENT INHERENT VISCOSITY ANALYZER BOILER FEEDMATER TANK REPLACEMENT
SOME ADDITIONAL CHANGES MADE, NILL CLOSE TO FIELD CHARGES IN HAY. DRYER CONVERSION ON SCHEDULE. HEN NODULE CONVERSION PLANNED FOR JUNE. HILL BE OPERATIONAL IN APRIL AND CLOSED TO FIELD CHAR6ES IN MAY. DESIGN IS SCHEDULED TO BEGIN IN JUNE. CLOSED TO FIELD CHARGES. PROCESS ENGINEERING IS MONITORING MODIFICATIONS. SYSTEM HAS BEEN TESTED MITK FILLER, MODIFICATIONS IN PR06RESS. NEN PARTS ARE IN, PROJECT NILL BE COMPLETED BY MAY. CONSTRUCTION IS IN PROGRESS. COMPLETION PLANNED IN APRIL. THE PROJECT HILL BE CLOSED TO FIELD CHARGES IN MAY. EN6INBSM6 IS IN PROGRESS ON MODIFICATION, PLANNED COMPLETION IN NAY. NEN MODIFIED SCREMS DUE IN MAY. THE PROJECT MILL BE CLOSED TO FIELD CHAR6ES IN APRIL. DESIGN IS COMPLETE. INSTALLATION IS PLANNED FOR 7/91. DESIGN IS COMPLETE. INSTALLATION IS PLANNED FOR 7/91. INSTALLATION IS IN PR06RESS. COMPLETION PLANNED IN MAY. PROJECT IS COMPLETE, NHL BE CLOSES TO FIELD CHARGES IN HAY. OLD NOQUIE COMPLETION PUNNED IN MAY, NEN MODULE COMPLETION IN JUNE. PROJECT NILL BE CLOSED TO FIELD CHAR6E5 IN MAY. PROJECT IS COMPLETE, MILL BE CLOSED TO FIELD CHARGES IN MAY. NAITIN6 ON ACCOUNTING CORRECTION, MILL BE CLOSED TO FIELD CHARGES IN ENGINEERING IN PROGRESS. PORTIONS OUT FOR BID. PLANNED COMPLETION EARLY-92 INCINERATOR DELIVERY PLANNED FOR 4/91. PROJECTCOMPLETION PLANNED FDR 7/91 INCINERATOR DELIVERY PLANNED FOR 4/91. PROJECTCOMPLETION PLANNED FOR 9/91 ENGINEERING IS IK PR06RESS ON 8 PROJECTS. 7 PROJECTS COMPLETED. CLOSED TO FIELD CHARGES. DESIGN IS IN PROGRESS.
VAB.0001189762
ENVIRONMENTAL - K. G. Akins
Water
All wastewater discharge parameters were met for the month of March.
The State responded to our letter of dissatisfaction on the new permit limits. They cited several reasons for no changes to the permit limits; the main one being that the City of Aberdeen was recently regulated at those same limits. The City of Aberdeen also discharges to James Creek. We expect to receive our new permit in mid-April.
A test run of "superbugs" was completed in our wastewater treatment system. Results were somewhat clouded due to the mild winter this year. However, based on BOD data taken during the test run, "superbugs" will help decrease BOD during the winter.
Superfund
The draft remedial investigation was received. Comments were gathered from the plant and corporate environmental and sent to Conoco. A meeting to review the final report was set up for mid-April.
A meeting was held with Conoco, Royal, Vista and Sun Polymers to discuss
removal of pond #2. The most favorable option was for Sun Polymers to dry
the material in Aberdeen.
The only obstacle now is getting State
approval. A meeting has been set up with the State for mid-April to dis
cuss this project.
The State has not yet confirmed that they will accept the lower risk factor. However, they have sent a letter to EPA in Washington asking for guidance on this matter.
gaste
No hazardous waste shipments occurred during the month.
Use of the general plant trash compactors has resulted in savings of approximately $900/month.
ENERGY CONSERVATION - J. R. Ganc
March. 1991
Data
A. Unadjusted EUI
<14.6%>
B. Adjusted EUI
<13.7%>
C. BTU/Lb. Product
2843.1
D. Total Energy Consumption MMM BTU 141.5
II. Boiler Operation
Fiscal Y.T.D.
< 8.5%> < 8.0%>
2757.5 830.7
Boiler
March. 91
No. 1 No. 2 No. 3
83.2% 83.7% 82.8%
Boiler #2 operated eighteen days during the month.
83.1% 83.3% 82.8%
VAB.0001189764
WMXK KMOOTCE REPORT
Beall
None
Jimmie Morgan - Maintenance Department - Employee progressed from General Mechanic "B" to General Mechanic "A".
PD-TDIIMWyiWU
Morris H. Williams - Maintenance Department - First Level Supervisor
None fO/ranM TT**VB OF ABSEMCE None
A
Mnpwmm/m
VAB.0001189765
EMPLOYMENT Salaried Hourly Temporary
SUB TOTAL
L.O.A. TOTAL
74 165
2
241
5 246
DEPARTMENTS
#EMPLOYEES
M
I
F
NEg HIRES S alaried/Trans fe r Hourly Temporary
TOTAL
MO 0 0 0
0
YTD 0 0 1
1
%M %F
'L
DEPARTMENT TURNOVER
MO. YTD
ANN. %
J I'fl
9766
T
\
A
cn
UJ
<c
a<rto
<x a.
UJ
<o o
to
UJ <X CO
r aero
co rrt 05
$o+ o+ +<oz>
00 <D O
CM
UJ
CO
*<mn m
<E>
CD
ro
CM
co
U9 Lju
ZZKCLU CO COCO
CO
VAB.0001189767
HP
I I UJ
u?
ii
it
!
$
0>
i i CM
i i in
ro i
i CM
OJ CM
i
cm
r-
J
CO
CM
I
I
i
-o
*r
i
CM
in
i
s
CM
m5
CM ro
00
i ro i
i i i i CM CM
ii
i i ii
y^ i r- i M3
o
tp in i
i nO
i CM i in i r i ev i i
in
i ro i
in i i
i nO
ro
44 CP ro
CM i I +r* i 'O i o i NO
r- 1|1 1 **- 1 00 i in i OO
i i ro i t
i in
in *r i oj i
in
i
In
i i
>o O.
1 i
NO i i
11 iro
CO 1 1
u. i o1
A 1 o- 1 l
1 in 1 in 1
H-l <c
t 1
in4
1 *
1
O'
1
'O
1
>o
*
CO
J 1 <D 1 1 1 o
*- t on I < I
o 00 00
in
<D
UJ -j
co <c UJ
a. UJ
<r a. UJ
hcou
JC CO '!>*
Caen
co ro X
CO ui<ro
co UJ
CO
UJ o UI CO Cd 1 <t 1
sin o- CM \ >o ao ro
o* t
CM
no
CM
*I
I CO
CO 1 1 1 O' 1 p*-- 1 i in i i l 1 4 i CM i O'
CO Ui
1 1
4
1 l
4
1 1
O4'
1 1
1
i
--
1
i
i
l
ro
i in
i t
O' 4
1 l4
2E 1 1 1
1 1 i *r i i i 1 in i ro i 1
1l1Ii i ii l i ii l
o
1 |*-C |4 ICM 1
J*-- i in 1 1 in l in in 1 i in i i in i in 1 in 1 i
UJ i CM 1 1 CM 1 CM i CM 1 i OO i -t 1
i i CM i CM 1 o- 1 in i
y f i r- 1 1 On i i 1 CM i i mQ i ro i f*- t NO 1 in i
UJ i LTt 1
1 O' i
i CM l NO i
O i*
ni
V
i 04 1
1i
i 1 1 O' i i t ro i 1 i i CM 1 NO 1 i
ixiae: i 1 1 i i * i 1 i i 04 1 1 i
i iin
(O' InO |nO nn
1 LiiOUl 1 in t O' 1 ro l
11
1 I
x:
3C
1 1
CM 4
i
00 4
1 1
CO 4
1 1
'O 4
1 1
O
l
1 h-- f-- 1 in i "4* 1 1 CD 1 CM 1
i <T i oo t -o i 'O
in GO
04
O'
1 1 O' 1
\4
1 1^ IOJ |4
i \ CO
00 \
1
1
1 1i
I
i
1 in i in i in i t in \
r*n m in CO
in
! i
1 CM i o1 4i
i
i in i CM i
l I
CM cm
in
cm
ICO 1 05 ce 1 in i i i
* in i ro CM i
ro O' ro ro
-4-* |
in
ro
ro
I* ro i
CM in ro
ro in
t
uj
UJ On o\
11iii
ti
4
1 1
4
1 1
i
i
I
i
i
qr 1 nO 1 i M3 i i i i in
CM
1 *
in 4*--
r i
i i
ro i ro l
i i
i i
i i
HO CM
ro ro
CM
in
CM
In ro
CM
Q
H Sh
UIA 1 i 1 1 i 1 in
i--IOC r 4 i 4 1 4
in
in
in i in in in in
<D in
CM
44
4 cm m4 O'
i M3 t co 1 GO co
in cm ro nO
ro
i O- i 1 ro
ad co
i i
O' r*-*
t r
1 1
GO <4P
cox i i 1 ro
i no
oo i oj i in
i
ro in
CM CSI
in in
s
-O
ro
m oo
in
i
to
UJ
CJ
i UJ i
I UJI 1 A t
1
rsi 2
UJ
o
i i
i
*^"1
a
i i i
l 1 1
Ou
o
I l 1
X UJ o
1
1 1
A Z O
1 1
1
M
CJ
u- \ rn I UJ l o i 35 1 Q 1 o
w i UJ i ad l UJ t l 1 >-- CO
2E i ad i O f
* .*11 l 2d
Ui o <r j <r 1 !-- 1 UJ f QC l o
o i :3 1 1
tAl o1>
n C4M
004 'O ^On
0*4 ^44 444 444
UJ
UJ CO
UJ
4C
<CU4
CO CO CO
y*|U***fe
:fc. l
VAB.0001189768
ADMTNTSTBATIVB SERVICES - D. A. Barclay
Safety There were no reportable safety instances this month.
Quality All natural teams met in February.
Processed
Processed Invoices Working Fund Checks Written Cost Savings Through Bid Process Raw Material Purchase Orders Issued MRO/AFE Purchase ORders Issued Spare Parts Purchase Orders Issued
Packaged Finished Goods Ending Inventory
Month
1008 7
$2899 100 199 166
Y.T.D.
6131 69
$20396 535
1232 1170
Feb.. 1991
Compound "A" Grade PLENEX Compound Off-Grade (BC) Compound Off-Grade (H) Millscrap(*) Dry Blend "A" Grade Dry Blend Offgrade Resin Type I Resin Type "BC" Vacuum Dust
Total Packaged Warehouse
4,054,762 64,682
734,449 73,172
132,457 312,968
44,605 636,800
37,600
6,418,636
* Includes PLENEX millscrap and cleanout.
Bulk Finished Goods Ending Inventory
Feb.. 1991
Compound "A" Grade Compound Offgrade Dry Blend "A" Grade Dry Blend Offgrade Resin "A" Grade Resin Offgrade
Total
1,774,593 368,450
1,550,810 1,057,260 5,926,350 ____58Q.250 11,257,713
(Decrease)
4,091,582 74,019
736,079 82,772 69,916
309,147 42,805
574,450 37,500
6,344,493
55,769 9,337 1,630 9,600
<62,541> < 3,821> < 1,800> <62,350>
< 100>
< 918> <55,194>
Mar.. 1991
1,422,788 177,500
2.185.510 873,660
7.809.510 1.189.150 13,658,118
(Decrease)
< 351,805> < 190,950>
634,700 < 183,600>
1,883,160 608.900
2,400,405
tn
to
to
i
to
oi
i
to
g
IIII MI It CO IIII HH II IHI
to
wo
s
J3
u*n
cu i*j
r -> 13C1( rC"**
r **4
'm
IB* tMIMMlMMMOTWiW
VAB.0001189770
H|*
1
1 1 1
I
1
ABERDEEN CHEMICAL PLANT SHIPPING ANALYSIS MARCH 1991
-SHIPMENTS BY PRODUCTS-
PUBLIC
MONTH IPT/ITC
EXCN/TOLL
RESIN-BULK RESIN-PACKAGED
20,271,760 10,514,800
231,500
126,300
363,900 0
FLEXIBLE COMPOUND-BULK
737,410
FLEXIBLE COMPOUNO-PACKAGED 2,091,821
730,300 0
0 0
NEW BUSINESS
9,722
00
RIGID COMPOUND-BULK RIGID COMPOUND-PACKAGED
4,093,190 401,457
345,600 0
0 0
TOLLING - BULK TOLLING - PACKAGED
0 00 0 00
PLASTICIZER TOTAL
130,480
1
27,967,340
84,440 11,001,440
559,650 923,350
YTD
PUBLIC
IPT/ITC
EXCH/TOLL
118,010,754 1,205,683
79,676,270 1,260,900
1,777 ,400 0
4,378,400 15,310,969
6,660,500 711,002
0 0
43,075
00
20,911,890 2,165,691
0 0
3,214,950 521,706
0 0
0 0
1,401 iW AtQ44Q| 33
779, ISO
714,510 3,281 ,760
162,803,012 92,739,838 6,494,720
SHIPMENTS 8Y MOOE BULK:
-Nwcir RESIN FLEXIBLE COMPOUND RIGID COMPOUND PLASTICIZER
t t
i
1 1 1
1 1
RAILCAR
CUSTOMER PICKUP
28 0 6 0
COMMON CARRIER
35 5 4 5
TOTAL
TOTAL MARCH
*YTD* RESIN FLEXIBLE COMPOUND RIGID COMPOUNO PLASTICIZER
TOTAL YTD
PACKAGED
MARCH* RESIN FLEXIBLE COMPOUND RIGID COMPOUND PLASTICIZER
TOTAL MARCH
*YTD* RESIN FLEXIBLE COMPOUND RIGID COMPOUND PLASTICIZER
TOTAL YTD
193 34 49
993 60 138 14
1,205
CUSTOMER PICKUP
2 21
0 0
23
252 0
22 29
303
COMMON
CARRIER
9 54 15
0
78
216 20 65 25
326
TOFC AIR/WPS
00 00 00 00
00
AIR/UPS
2 5 0 0
7
22 69 0 0 129 388 0 0
6 78 0 0 0 100
157 536 0 0
30 61
3 0
94
276
1,461 80
225 68
1.834
TOTAL
13 80 15
0
108
121
578 87
1
787
CC: DAB,TLC,AEV,JRF
VAB.0001189771
1000
03/90 06/90 07/90 06/90 11/90 01/91 03/91 04/90 00/90 00/90 IQ/90 12/90 02/91 PKG'D PRODUCTS INVENTORY
pp WWWWMWNM*
VAB.0001189772
ftc
IAP<mWm - J. M. Edwards, Jr.
A. Safety
There were no safety incidents in the Laboratory during March. The monthly safety meeting topic was "Lead Handling in the Lab" taught by Jim Edwards.
B. Customer CoRttCtt
There were three customer contacts made in March. John Irvine, Rendell Newton, Mark Eramo end Jim Edwards visited KlocknerPentaplast, American Mirrex and FVC Container Corporation.
We met with Odell Sargent and Louie Pritchett at Klockner on 3/26/91. We discussed product quality and specific improvements that are needed in contamination, fiber and gel count. Action steps were also discussed to locate sources of line streamers.
We met with Lynne Webb, Dave Pullin, John Blum and Ronnie Foster at American Mirrex on 3/27/91. Vista's 5305 contamination count was compared to Oxy's equivalent. 5305 has approximately twice the contamination as Oxy's resin per the Syntron method. Mirrex is also concerned about fibers and line streamers.
We met with John D'Avella from PVC Container and Frank Pallante, Bill Gibby and Phillip Friedman from Novatec Plastics on 3/27. They like Vista's 5265 for bottle manufacturing and compare it to Georgia Gulf and Pac West as a good alternative except for color. In 16 to 18 mil bottles, the throat at the top turns slightly grey using 5265. It takes three times the amount of blue toner to com pensate for the grey. R&D in Austin will identify the source of the greying.
C. Customer O.C. Problem Reports and CNR's
03/06 American
Customer complained of two separate incidents of high moisture and yellow discoloration with Vista 5305 and 5265 resin. The 5265 complaint was from material that had set in their silo a long t ime and had collected toisture at the bottom outlet. The 5305 complaint was from a compartment in railcar GACX 73381 traced to a dryer start up. John Olson wrote a letter to Mirrex addressing the wet 5305 issue.
Continued
Continued
3/07
Customer complained of higher than normal contamination in two compartments of 5305 railcar VIPX 45747. During the 3/27 visit, a statistical analysis was presented to Dave Pullin and Lynne Webb showing that although the numbers looked high, they were within specification and within our upper control limit. They agreed but said that our con tamination was twice as high as the competi tion's .
03/08
Customer complained of getting poor service at the loading dock in terms of scheduling a pick-up and expediency. Don Barclay's in vestigation showed several instances of miscommunication which caused the problems. Future pickups should run smoother as a result of the CNR.
A truck of 5385 sent to Textileather for evaluation failed their contamination specification. After further conversation and testing, it was learned that they need very low contamination 5385 (10/50 max). The replacement truck and the truck that followed ran very well for them.
3/27
Customer complained of contamination in
38601 black compound causing excessive
screen pak changes. Samples of the screen
pak showed uncrushed crystals of calcium
carbonate during a preliminary investiga
tion.
Samples were forwarded to R&D
Analytical in Austin for confirmation.
American Mlrrex. News Castle. DE
The "A" compartment hatch was open on 5265 railcar UTCX 46442 as it arrived at the CSX terminal. The latch mechanism had vibrated loose during transit. This compartment was withheld from shipment to Mirrex.
VAB.0001189774
I
^v.
f-ABOBATopy - Continued
D. Product Waivers
Eagle
80273G WHT 110
Eagle
80273G WHT 110
Eagle
80273G WHT 110
Vinyl Building RP-20 WHT 121 Products
Color
1 R/C
Long Stab. & 40 Mesh 1 R/C
High Eq. Torque
1 R/C
Fusion Torque
1 R/C
Western Ag.
E. PVflM
80273G WHT 110
40 Mesh
2 R/C
RVCM of
The following is a summary of residual VCM results on in-
process samples.
None of the reactor daily averages
exceeded 400 ppm RVCM during the month of March, 1991.
Number of Samples Average RVCM, ppm
Reactor Slurries
________Drier
5265
5305
26 0.271
49 0.208
The following is a summary of the residual VCM analysis of shipment samples for the month of March, 1991.
Product
Number of Samples
5265 5305 5385 5395 5415 Debox Dry Blend
48 66 49 28 46 16 24
0.114 0.112 0.379 0.022 0.066 0.280 0.150
Mi
m
I
m WWPf
VAB.0001189775
Continued
Resin
(based on dryer "regulars")
5265
mi
5385
51i
Bulk Density Inherent Viscosity
(vs. 0.715 - 0.744) L Color A Color B Color % on Pan
(vs. 2%, max.) % thru 140 Mesh Mets I.R.
(vs. 95% of control) Hard Particles, (% > 10) Average particle size,
microns
1.19 0.49
--
3,72 3.67 1.89 1.33
--
1.21
-- -- --
151
0.94 0.89 0.56 1.83 8.67 3.67 3.75
--
2.67
-- --
--
158
1.13 0.56
--
2.07
--
1.78 3.00
--
3.02
-- --
58.8
186
1.19 0.64
--
1.89
--
5.00 1.71
--
2.21 3.65
--
0
1.67
5415
1.12 0.70
------ ---- -
3.00
------ ------- -
2.67 3.75 1.25 6.41 4.26 1.96
0
191
Hardness Color Hard Particles Heat Stability Contamination Dispersion Dicing Cross Contamination Mischarge
Total
Adjustments M Lbs. (%)
7.0 90.0
--
7.0
-------------------------
--
<0.21> <2.72>
--
<0.21>
--
--
--
__ZJ2 <0.21> 111.0 <3.35>
fon--ry
Rejections M Lbs. (%)
....
37.5 14.4
--
4.5 10.1 14.5
3.2
_2jJ> 93.7
__
<1.13> <0.43>
-----
<0.14> <0.31> <0.44> <0.10> <0 29> <2.83>
Color 40 Mesh
19.5 3.5
<0.37> <0.07>
I. Miscellaneous
1. All six natural teams met during the month.
2 "D" shift made their presentation to management. Their
project was to re-arrange lab furniture and equipment to enhance testing efficiency and reduce steps (walking).
3 The software program
4. Precision studies were done on the new viscosity testing equipment.
VAB.0001189776
SAMPLE SHIPMENTS MARCH 1991
A
RESIN Ship Date 3/01/91
3/01/91 3/05/91 3/08/91
3/11/91 3/18/91 3/20/91
Product
5265 5385-1 5385-3 5415
5325
5305
5265 5385 5415
5265 5415
5385
*
5385
Amount
Customer
3X1 lb. 3x1 lb. 3 X 1 lb. 3 X 1 lb.
MULANOVICH REPRESENTACIONES (PERU)
4 X 50 lbs. Premier Polymers
50 lbs.
Burton Rubber Company
50 lbs. 50 lbs. 50 lbs.
Uniroyal Chemical
5 lbs. 5 lbs
P* D. I. Inc.
25 lbs. 10 kg
FABRICA ARGENTINA ALPARGATAS
ALPARGATAS S.A.I.C. (Argentina)
COMPOUND Ship Date 3/06/91 3/07/91 3/08/91 3/11/91
3/13/91 3/15/91 3/20/91 3/20/91 3/21/91
Product
35852 NAT 02
462-83A NAT 462-83A NAT
38931 WHT 810(00) 45541 NAT(OO)
419-50-A
58162 NAT 55041 CB 50 54331 CB 50 17462 GRY 545 58162 GRY 545
Amount 1500 lbs.
1400 lbs. 100 lbs.
50 lbs. 50 lbs.
5x5 lbs.
200 lbs. 300 lbs. 1300 lbs. 200 lbs. 200 lbs.
Customer Savannah Wire & Cable Co Automotive Industries Americhem Inc. AFC
Furon Company Associated Plastics Anchor Wire Corp. Tandy Wire & Cable National Door
VAB.0001189777
COMPOUND (Cont.)
Ship Date
Product
3/22/91
18831 WTCL
3/25/91
452-116A WHT
DRYBLEND Ship Date 3/08/91 3/13/91 3/19/91
Product 80273G WHT 110 80273G WHT 110 489-98 WHT 125
PLASTICIZER Ship Date 3/26/91
Product
mm
108P
MI SC. Ship Date 3/08/91
Product Vent Dust
Sample Shipments/March 1991 Pacte 2
Amount 100 lbs. 1400 lbs.
Customer QUIMBOL SA (Bolivia) Sunbeam - Northern
Amount 1190 lbs. 1 lb. 35100 lbs
Customer Available Plastics LAJA LTDA. (Uruguay) Vinyl Building Products
Amount 2 gal.
Customer Blane Polymers
Amount 10 lbs.
Customer Wexford International
VAB.0001189778
ABERDEEN CHEMICAL PLANT
CUMULATIVE RECORDABLE INJURES
QC
Ld
A
Oct Nov Doc Jan Fob Mar Apr May Jun Jul Aug Sep
MONTH
WORST (1985) --BEST (1990)
1991
MONTH
Oct Nov
Dec
Jan
Feb Mar
Apr May Jun Jul Aug
Sep
TOTALS
ABERMH't OSBA RECORDABLE INJURIES
FECAL YEAR
1985
1986
1987
1988
1989
1 3000
02 100
1 00 1 2 20 100 20000
0 1300
00 1 0 1
30023
1 0000
21 113 12110
0001 0
1990
1 1 0 1 0 0
1
0 0 0 1 0
1991
0
3
1 0 1 1
VAB.OOOl189779
ABERDEEN ENERGY CONSUMPTION
B T U /L B
an/rue
VAB.0001189780
MONTHLY
MONTH
--------- 12 MONTH AVERAGE
f
*