PETRIN CORPORATION P.O. BOX 330 PORT ALLEN, LOUISIANA LOUISIANA CONTRACTOR'S LICENSE NO. 7334
DATE: OCTOBER 2, 1990 TO: HENRY VADNAIS ( GLYCOL-II) FROM: RON LEE RE: T-54.T-56 1&2, T-57, T-53 AND
T-5
THE FOLLOWING IS THE RESULTS OF AN ASBESTOS SURVEY, RECENTLY COMPLETED IN THE GLYCOL-II PLANT.
THIS ESTIMATE DOES NOT INCLUDE SCAFFOLDING OR MATERIAL RENTALS, BUT DOES INCLUDE ALL ASBESTOS RELATED MATERIAL.
T-54 COLUMN : SKIRT, 24" ELBOW EXPOSED ASBESTOS NEEDS TO BE ENCAPSULATED.
MANHOURS MATERIAL LABOR
20 130.00 430.00
TOTAL
560.00
T-56-1 COLUMN: SKIRT, BOTTOM HEAD NEEDS TO BE REPAIRED AND ENCAPSULATED,14" PIPE ON HEAD TO BE ENCAPSULATED.
MANHOURS MATERIAL LABOR
104 774 .00 2 ,236.00
TOTAL
3,010.00
T-56-2 COLUMN: BE ENCAPSULATED.
SKIRT,BOTTOM HEAD AND 8"
MANHOURS MATERIAL LABOR
30 172.00 645.00
ELBOW NEEDS
TO
TOTAL
817.00
T~57 COLUMN: ENCAPSULATED.
SKIRT,BOTTOM HEAD AND 6"
MANHOURS MATERIAL LABOR
30 172.00 645.00
ELBOW NEED TO BE
TOTAL
817.00
DO 074268 CONFIDENTIAL
PETRIN CORPORATION P.O. BOX 330 PORT ALLEN, LOUISIANA LOUISIANA CONTRACTOR'S LICENSE NO. 7334
T-S3 COLUMN: SKIRT,BOTTOM HEAD NEEDS TO BE ENCAPSULATE.
MANHOURS MATERIAL LABOR
20 130.00 430.00
TOTAL
560 .00
T-5 COLUMN: EXPOSED ASBESTOS ON COLUMN AND BOTTOM HEAD NEEDS TO BE ENCAPSULATED:
MANHOURS MATERIAL LABOR
80 602.00 1,720.00
TOTAL
2,322 .00
ALL SKIRT NEEDS TO BE CLEANED OUT WITH HEPA VACUUM.
MANHOURS 32
LABOR
688.00
TOTAL ESTIMATE JOB COST IS: MANHOURS:
316
MATERIAL LABOR
1,980 .00 6,794.00
TOTAL
8,774.00
UPON COMPLETION OF THIS PROJECT,YOUR RESPONSIBILITY FOR COMPLIANCE WITH BOTH DIVISION AND OSHA POLICY REGARDING ASBESTOS REMOVAL WILL BE GREATLY IMPROVED.
IF WE MAY BE OF ANY FURTHER SERVICE,PLEASE FEEL FREE TO
PETRIN CORPORATION, DOW CHEMICAL
00 074269 CONFIDFNTTA
PETRIN CORPORATION P-O. BOX 330 PORT ALLEN,LOUISIANA 70767 LOUISIANA CONTRACTOR'S
LICENSE No. 7334
DATE: TO:
FROM: RE:
AUGUST 9, 1990 JIMMY RILLS Ron Lee Asbestos Project
The following is the results of a asbestos survey, recently completed on the PLANT WIDE 235# STEAM LINES.
This estimate does not include scaffolding or material rental, but does include all asbestos related material.
The following is an approximate estimate of the linear feet of steam line in the division per plot plan areas:
AREA A 9,120 L.F. AREA B 16,540 L.F. AREA C 7,680 L.F. AREA D 12.6S0 L.F.
45,640 L.F.
Upon completion of this removal project, your responsibility for compliance with both division and policy regarding asbestos removal will be greatly improved.
OSH A
If we may be of any further assistance please feel free to contract us at extension 6300.
Ronald C. Lee, Superintendent F'etrin Corporation, Dow Chemical
no 074270 C0NFTDENTIA1
J
PETRIN CORPORATION P.O. BOX 330 PORT ALLEN,LOUISIANA 70767 LOUISIANA CONTRACTOR'S LICENSE No. 7334
DATE: TO:
PROM: RE:
AUGUST 9, 1990 JIMMY RILLS Ron Lee Asbestos Project
The following is the results of a asbestos survey, recently completed on the PLANT WIDE 304 STEAM LINES.
This estimate does not include scaffolding or material rental, but does include all asbestos related material.
The following is an approximate estimate of the linear feet of steam line in the division per plot plan areas:
''! `
AREA A AREA B 1,900 L.F. AREA C 650 L.F. AREA. _D 5,140 L.F,
1 -< . i i ''r , ]
7,690 L.F.
Upon completion of this removal project, your responsibility for compliance with both division and policy regarding asbestos removal will be greatly improved.
OSHA
If we may be of any further assistance please feel free to contract us at extension 6300.
00 074271 CONFIDENTIAL
PETRIN CORPORATION P.O. BOX 330 PORT ALLEN.LOUISIANA 70767 LOUISIANA CONTRACTOR'S LICENSE No. 7334
DATE: TO:
FROM: RE:
AUGUST 9, 1990 JIMMY RILLS Ron Lee Asbestos Project
The following is the results of a asbestos survey, recently completed on the PLANT WIDE 475# STEAM LINES I
This estimate does not include scaffolding or material Cental, but does include all asbestos related material.
The following is an approximate estimate of the linear feet of steam line in the division per plot plan areas:
AREA A 1,830 L.F. AREA B 7,015 L.F AREA C 7.B40 L.F. AREA D__ 4,440_ JL._F
21,125 L.F
Upon completion of this removal project, your responsibility for compliance with both division and policy regarding asbestos removal will be greatly improved.
QSHA
1f we may be of any further assistance please feel free to contract us at extension 6300.
Ronald C. Lee, Superintendent Petrin Corporation, Dow Chemical