Document nkOG1gNg4Z69X3dyNaVQKD9xm
_
>
COMPANY CONFIDENTIAL
Monsanto
Anniston Plant
TECHNICAL SERVICES DEPARTMENT
MONTHLY REPORT
Anniston
C. K. Eastman A. G. Hill L . C. Lahman J. C. Landwehr G. W. Miller W* B. Papageorge W. F. Taffee H. L. Williams
Month
Summary August, 1969
Cost Improvement Results
Est. Act. $57,877
Target $66,285
% of Target 87.3%
General Offices
YTD
$361,080
$372,285
97.0%
H. S. Bergen ;H. C. Carder D. Danna (5) P. B. Hodges D B. Hosmer (2) W. A. Kuhn W. R. Robirds
J. E. Smith J. A. Stephens R. J. Stratmeyer H. S. Trail
. C[ >
OTHER LOCATIONS
Organic Division
Sandvik belt arrived late August for testing with Solid Aroclor Montars handling in September.
A designed experiment was run on the Biphenyl tubular unit to better describe the process variables and their rel-ationship.
Process Analysis
Correlations (99.9%) confidence) have been found between PNCB usage and reactor pressure, temperature and caustic concentration when these variables are combined into a cal** culated parameter,A. T, which is the difference between the reactor temperature and the boiling point of the reactor mass. From these correlations several combinations of variables will be defined and tested to restore standard PNCB usage for a potential $10,000 per month savings over present levels.
Agricultural Division -
A. H. Forsten Alvin, Texas
Parathion MIP was completed and reviewed with Director of Manufacturing, Crop Protection Group, on August 29.
D. W. Jackson WGK
T. M. Patrick So. 2nd St.
Change out of No. 3 chlorinator was completed on August 16, and a 2 hour reduction in batch cycle time has been dem onstrated. Productivity gains of $3250 resulted in August.
DSW 551266
N --306 REV. t 1 / 1/ 1 968
COMPANY CONFIDENTIAL INFORMATION
``This document contains confidential information which is the property of Monsanto Company. Only those portions of the document relevant to a duly authorized individual's need to know may be exerpted for him. The report must not be sent outside the Company without written
approval and the recipient is accountable for its safe keeping, exerpting or otherwise disclosing of its contents and for its proper disposal."
STLCOPCB4089683
i .Company confidential
2 Utilities
Initial results of Biphenyl Cooling Tower Treatment are good and August savings are estimated to be $600. Design and Drafting A project to improve the emergency power supply for Parathion (AFE 3305 - $41.9M) was approved on 7-30-69. All long delivery items have arrived and installation should be completed by September. Pat McGinley of CED contributed to a large degree to the rapid development of this project. Pollution Control The HC1 neutralization pit was cleaned out in mid-August. Preliminary tests indicate that treatment of sewered acid has improved considerably. Quality The Plant Quality Score was 93.7, up 6.1 from July with a YTD score of 88.4 against a 1969 target of 95.0 minimum. P^S color Aroclor 5460 solubility, HB-40 specific gravity show unfavorable trends.
. C. Landwehr kd
qSW 551267
STLCOPCB4089684
> ORGANIC DIVISION
1969 TSD COST IMPROVEMENT
ANNUAL JAN FEB MAR APR MAY ' JUN JUL AUG SEP OCT NOV DEC
Sol.Aro. Level TAR
Ind.& -Still SpG EST
AFE 3015
ACT
Solid Aro.
TAR
Lower 5060 Soft. Point
EST.' ACT
2250 2250 2250 2250 2250 2250 .2250. 2250 2250
--
--
"
---
'
?600 1500
2600 54 90
2600 4 89 O'
2600 215C
2600 4 67c
2600 800C
2600 4230
r?/.6yoior 2600
1500 5490 4890 2150 467 C 800C 4^30
-
--
Sol.Aro.-Still Coolant temp.
AFE 3015
TAR EST. ACT
160 170 160 I70 160 170 160 170 160
-
Sol .Aro. -Chlortcr TAR
Batch End
EST:
AFE 5015
ACT
390 390 390 390 390 390 390 390 390
---" -
~"
"*
Sol .Aro. Yield TAR
SW/R Composition EST
AFE 5016
ACT
2750 2750 2750 2750 2750 2750 2750 2750 - -' --
Solid Aro. Montar 5 Flake AFE 2949
TAR EST
ACT
1080 1080 1080 1080 1080 1080 1080 1080 ---"
Sol.Aro. Blend 4465
TAR EST ACT
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 1690 1920 1630 1490 710 1180 990 220 1690 1920 1630 14 9 C 710 118C 990
Sol.Aro.-Verti- TAR
cal Still Cond. EST'
AFE 2524
ACT
70 80 70 80 70 70 90 90 9 0 90 - 70 90 90 90 90 -
-
-
Sol.Aro.Cl2 T/C Dock AFE 2542
TAR EST ACT
940 940 950 0-0--
Sol.Aro.-New Cl= TAR
Unload - No Delay EST'
CED 1851
ACT
950 940 950 940 950 940 950 900 2330 2050 2320 900 P33O 2050
Solid Aro.-Flake TAR
& Drum
EST.
CED 1450
ACT
Liq.Aro.
TAR
ooo
3000 3000 5000 5000 5000 5000 5000 5000 5000 5000 5000 5000 0 0 1000 2000 2000 2000 3OOC- 3000 0 0 1000 2000 200C 3000 300C
3000 - - - - - - - - - -
48-5J M #/yr. AFE 2545
EST. ACT
0 550C 0 550C -
--, - - - -' --
Liq.Aro.'No.2 TAR
3000 3000
Still Entrain Sep. EST.'
AFE 5095
ACT
Liq.Aro. -Montar TAR
Disposal
EST.
AFE 2952
ACT
1080 1080 1080 1080 1080 1080 1080 1080 1080 1080
0 00 0 00
00 00
0
.Warehouse Reduce Manpower CEA 1452
TAR EST' ACT
2000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
2000 2000 P00C 3000
OOO
3OOO 300C 300C
2000 200C 20cg 3000 300c 3000 3000
Liq.Aro.New
TAR
Burners $3 Still EST
ACT
1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 0 0 1500 3000 900 0 0 0 1500 3000 900
Biphenyl Relocate TAR
No. 1 Preheat EST
CEA 1892
ACT
500 500 500 500 500 500 500 500 500 500 500 500
1500 0 1560 1870 0
0 "TpUD 0
150C 0 6 10 137 0 0
0 150C
HB-40 2nd Autoclave AFE 3102
TAR
EST ACT
3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3OOO" 3000
2230 2580 0 >490 24 2C 0
600 9000 6000
42U0"
600 10;4CJC 8600 /4 jU
- --
1 EfM Ol5Q
STLCOPCB4089685
) ORGANIC DIVISION
1969 TSD COST IMPROVEMENT
(
ANNUAL JAN FEB MAR APR MAY JUN JUL AUG , SEP OCT NOV DEC
Bi0 Improve Tower Treat. AFE 4155
TAR
EST ACT
450 450 450 450 450 450 450 450
0u
0o 534
00
0
Improve Pit. Power Factor
TAR EST ACT
900 900 900 900 900 900 900 900 0 500 900 yuu 0 500 83O
Central Air
TAR
1000 1000 1000 1000
System
EST
ACT
Optimize Rx Time PNP
TAR EST ACT
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
0 34 20 0
0 0 2940 L26U
0 3420 0
0 0 2940
Reduce Mole Ratio NaOH/PNCB PNP
TAR EST ACT
4000 4000 4000 4000 4000 4000 4000 4000 4000
0
00
00
0
00
0
New Wash Water Pump - PNP AFE 2998
TAR EST ACT
50 50 50 50 50 50 50 50 25 50 50 50 50 50 5U 25 5 0 50 50 50 50
Automatic pH
TAR
500 500 500
Control
EST
PNP ACT
.
HC1 Filter Pump
TAR 450 440 440 EST 350 530 340 ACT 330 3 30 340
New Blow Tank HCl
TAR EST ACT
200 200 200 200 200 200
200 200 200 2dJ 5u0 200 200 200 200 200 200 200
L
150,000 Gal.-HCl Storage Tank AFE 2468
TAR EST ACT
1760 1760 1780 1760 1760 1780 1760 1760 1780
-
u -
0 2640 3290 0 283O
Produce Staley Grade Acid AFE 4076
TAR EST ACT
780 780 790 780 780 790 --
-
Clo Pit. Shutdown TAR
8880 8880 8880 8880 8880 8880 8880
CF.A 1851
EST ACT
8380 223'Cj
6/f6e5e5
12335 12355
[L9900
Hg Recover from TAR ??50 250 250 250
Residua
EST ' 3910 ACT 3910
0 0
00 00
Hg Wash Tank
AFE 2802 Biphenyl . Productivity
TAR EST
ACT TAR ~EST
ACT
3-50 350 250 250
o0 00
0u 00
5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600
0 9UuU i.S.CU. 0 0 0 3b7t0:; ; 57T? j
1800. 5900 13,530 0
0
0 307 8C
Total Organic By Month M $
TAR
EST ACT
23-5. 26.Si 29.3 37.5 42.4 51.1 51.6 51.6 51.6 52.7 Ll,5 50.//
16.5! 27.1 3O.2 11.5 36.3 39.565 107.4 ppm
24.3 [27.3 11.4 25 .75 45.9 110.2;
Total Organic
TAR 23:i 50.1 79.4 116.9 159 .2 210.3 261.9 7J3;5 560 417.8 47 1.7 521.9
YTD M $
EST ACT
| 46.9 16.51 40.3
78.3 68.1
79.6 115.9 79.5 >105.2
144.4 151.1
a2S58i..s5q11 315.131
* $2^955 adjustment included for May & June.
* $27,780 adjustment included for months .
January thru June.
DSW 551269
STLCOPCB4089686
AG DIVISION 1969 TSD COST IMPROVEMENT
'1*
4
ANNUAL JAN
Cooling Tower
TAR
Repiping AFE 2598 Optimize N2 &
EST ACT TAR
Cl2 Levels
EST
ACT
Increase Waste
TAR
Acid Sales
EST.
ACT
Chlorinator R.I.
TAR
EST'
AFE 2244
ACT
EVOP Condensation Rx.
TAR EST ACT
750 0 0
Cl2 Unloading
TAR
EST
CEA 1851
. ACT
Recycle Wash
TAR
Water
EST
AFE 2960
ACT
Parathion Recovery TAR
EST
AFE 2655
ACT
Reduce Acetone
TAR
Losses
EST
ACT -
Formulations
' TAR "
EST
AFE 2897
ACT
Change Cooling
HsO Item iyi
TAR EST
AFE 5067
ACT
Well H20 to Jets
TAR
EST
ACT
Ag. Division
TAR 750
by Month
EST
ACT 0
Ag. Division YTD
TAR
EST ACT
750 0
Ag. Division
TAR
untargeted-R.M.
EST
Charges optimizati' rACT
Organic Div.
TAR
Untargated - KC1 EST
Catch Tank& Coalei eA'CT
FEB
750 0 0
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
420 420 410 410 420 420 410 420 420
0 00
00
0 00
0
6600 67 00 6700 6600 6700 67 00
0 00 0 00
00 0
400 500 500 400 500 300 400 300 300
00
0
00
0 0 0 0
250 250 250 250; 250 250 00
0
500 500 750 750
12,615 12,615
5000 5000 5000 2000 2000 2000 00 0
290 290 290 290 290 29 0 00 0
5800!58001 5800
_
i 4300:4300 4300
1600 1600 `1600 1600 1600 1600 3000 6600 10,Get 4570 2000 4300 10,400 9233 4570
125 120 .120
125 125 125 125
130 155 272 333 180 171 272
125
i ii 125! 125
500 500
125 500
750 50C 9145 9145 91 *5 1 4675 14,<R5 14685 14575 1 443 5 14435
12pl5 372 c 6,730 10,155 4842 4033 0 1215 >,420 10,580 9459 4841
1500 90 QC 11145 90990 9C/.95 441 no. 53785 7447 C 38045 10253: 117015
12,65
2;,815 37/7041,9^ 45,949
0 12,615
27,615 57,07441,936 *
0
17 OC
0
5000 0
00 0 6250 596C 4690 9p5C 6817
os*^170 STLCOPCB4089687
>
AROCLOR
'
'
....................................................................
Company confidential 3*
E E. Bowles, C. R. Mcllwain, P. D. Kinnear (V. R. Haupt)
Aroclor Safety Audit
Safety
TSD Objective A-1
Completed preliminary review of all Aroclor Safety Audit items, either project premises or maintenance repair orders have been issued initiating the completion of these items.
Aroclor MIP________________________________ B - 1
TSD Objective
Preliminary groundwork for the 1970 Aroclor MIP has been started. Pro duct outlook based on the new sales forecast is such that capacity will not be an important factor in this year's MIP. The major items of in terest will be operating efficiencies as related to decreasing the unit cost of Aroclors, Department commitment for date of issue of approved plan is November 15th.
Evaluate Quaterphenyl-
Polyphenyl Effects on
1969 Savings $63,200
Solid Aroclor Yields ____________NFC$14.000B - 8(a)
TSD Objective
Operator training on radiation instruments was conducted during August. Waiting for radioactive source for level alarm to be installed before start-up in early September.
Debottleneck Liquid
Yield & Capacity
Aroclor Stills;IncreaseB - 8(i)
TSD Objective
High Aroclor inventory prevented the field test of Aroclor Tentative Amendment B during the month of August.
Sandvik Belt Cooler for Montar 5 Solidification
Solid Aroclor Expansion TSD Objective Evaluation;B - 8(1)
The stainless steel cooling belt was delivered 3 weeks later than expected. Test runs will begin early in September.
BIPHENYL-SANTOWAX W G. Niemeyer, D. A. Self (V. R . Haupt)
Debottleneck BiphenylSantowax Distillation Area to 87.6 M lbs/yr.
Biphenyl
Capacity Increase
TSD Objective B - 7(a)
Fabrication of spool pieces for installation of by-pass loops around Santowax C flow meters is complete. Installation of by-pass loops will be completed by 9/11/69. A capacity/performance test run will be con ducted on the Santowax distillation column after the meters are re installed and calibrated.
DSW 551271
STLCOPCB4089688
> Company confidential 4.
BIPHENYL-SANTOWAX - (Cont'd.)
Low Biphenyl Santowax
Sales
for FDA 5460SupportB - 7(b)
TSD Objective
During August, we produced Santowax C with approximately 0.157. biphenyl due to running at a low production rate. To make it routinely year round, increased cooling water capacity is required in the distillation area.
Tank Truck Shipments of
Sales
'Molten Biphenyl___________ ____________SupportTSD Job No. 824
TSD has assisted in the conversion of a large biphenyl customer. Chemical Processing of Georgia, from flaked biphenyl in bags to molten biphenyl. Two truck loads were shipped during the last week in August.
Prediction and Control of Dust Explosion Potential in Biphenyl Flaker Packaging System;SafetyTSD Job No, 9^1
Safety review committee has accepted the recommendation to convert the biphenyl bagger from air fluidization to nitrogen fluidization to main tain an inert atmosphere in the hopper. In addition, help will be re quested from S&PP on hopper design changes.
Designed Experiment Run on
Process
TSD Objective
No. 1 Biphenyl Furnace____________ StudyB - 7(e)
A designed experiment was conducted on the No. 1 biphenyl furnace from August 4 through August 1J. Around-the-clock TSD coverage was provided to record temperature data and supervise sampling. Four blocks of data were collected with 12 trials in each block. The variables studies were: 1. converter outlet temperature, 2. converter pressure, 3. promoter concentration, and 4. per cent biphenyl recycled in benzene feed. The primary purpose of the test run was to determine what set of process conditions would produce the desired product split with minimum quaterphenyl production.
Install Secondary High Level Alarm on Biphenyl ColumnSafetyTSD Job No. 817
Complete design package was transmitted to Maintenance for construction on August 25, 1969.
'1
f
DSW 551272
STLCOPCB4089689
- ' '
}I
Company confidential 5.
BIPHENYL-SANTOWAX - (Contd.)
Install Knockout Tank on Santowax Jet Vent
____________ SafetyTSD Job No. 862
Design package will be transmitted to Maintenance by September 12, 1969.
HB-40
J. W. Mattern (V. R. Haupt
HB-40 Control Variable Study
Process Study with $10 M Potential Savings
TSD Objective B - 12(d)
Collection of base line data has been postponed due to frequent shutdown from high inventory and lack of an adequate, safe sampling port for in* coming Santowax R. A plan for catalyst savings is currently being reviewed by Production.
HC1 G. L. Moore, L. 0. Chambers, K. G. Hale (A. G. McCarty)
Production of Staley Grade Acid - AFE ^076 ________
New Earnings $288 M
TSD Objective
Potential Savings $71.000B - 10(c)
Coalescer and catch tank contributed $4700 savings during August. The coalescing element was changed during the month because of considerable deterioration. Alternate designs are being evaluated with the vendor to increase element life.
Issue HC1 MIP ________
TSD Objective Planning__________________ B - 1(b)
Finished draft complete. Plant review scheduled for 9/10/69 with issuance targetted in September.
Reduce High Free Cl2 in Muriatic Acid
QualityTSD Job No. 950
Air blowing of acid storage tank continues to alleviate high free Cl2 problem. Plant tests to determine source of free Cl2 will be scheduled later.
PNP G. L. Moore, L. 0. Chambers, K. G. Hale (A. G. McCarty)
Debottleneck to 1.8 M,________________________
Capacity Savings
TSD Objective
$27.500__________ B - 9(a) i`
Letdown time continued good during August. Savings of $1260 were gained during the month.
Installation of a new filter pump was completed removing a bottleneck to capacity gains by further reactor cycle improvement. However, long cooling cycles have recently developed in the acidifier, and these will be investi gated in September.
DSW 551273
STLCOPCB4089690
>' -
- .................'--'""I <
,Company confidential 6
NIRAN K. G. Hale, D. W. Dudley, T. W. Lawrence, J. L. Gaines, (A. G. McCarty)
Demonstrate Parathion Recovery__________________
Savings $17,400 10-15% Reduced COD
TSD Objective B - 5(a)
No change in status. Construction in progress on test facilities
Savings $12,900
TSD Objective
Acetone Recovery_____________ 20% Reduced COD__________
B - 5(i)
Recovery tests on #3 condensation reactor were completed in August. Re sults have not been evaluated as yet. Initial design and drafting were complete 8/12. Review of design will be complete 9/11. Project will be submitted for approval 9/12. Project transmittal to Maintenance will be 9/19. Construction still slated for fall turn-around.
Central Chlorine Unloading for Niran
TSD Objective Savings $21.000B - 6(a)
Operation of new unloading facilities good except for rate. Rate has.not improved over present due to lack of sufficient air pad. Evaluation of new compressor versus rebuilt compressor underway. Evaluation will be complete by 9/15 with EDC dependent upon decision.
Sulfur Recovery
$271,000/Yr. Net Savings
TSD Objective
from Residue407. Reduction in SOoB - 5(d)
C.E.D. is active on summarizing scope and initial estimating. Anniston TSD providing assistance as necessary.
Optimize Cl2 & N2 LevelsSavings $40.000B - 5
TSD Objective
Savings of $6600 were realized during August, when compared to June YTD usages. Methanol and P^j yields increased slightly over July. TSD continues to monitor yields and Cl2 & N2 level tests.
No. 3 Chlorinator Long Profit New Sales: 25,000/Mo. TSD Job No. 927 Cycle TimeProductivity Savings: 5.000/Mo. TSD Objective B - 5
No. 3 chlorinator changed out 8/11 - 8/16. Operations since 8/16 indicate approximately 2.0 hours reduction in batch cycle time. Productivity savings of $3250 were obtained in August.
os***14
STLCOPCB4089691
- Company confidential 7.
NIRAN - (Cont'd.)
Profit New Sales and Productivity
Improve Chlorinator
Savings $48,000/Mo. per 0.5 Hour TSD Objective
Cooling SystemReduction in Chlorination TimeB - 5(g)
Information on boiling refrigerant cooling indicates that heat transfer advantage will be obtained from Freon-21 over the currently used Freon-11. A recommendation for a plant trial of Freon-21 will be submitted after some additional work to optimize the present system.
PROCESS AND QUALITY ANALYSIS J. L. Murphree, Allen Hale (W. B. Dunlap)
Process Surveillance
The first semi-annual recalculation of control chart standards has been completed. The results were as follows: 36 improvements, 11 relaxations, and 17 unchanged. This three to one improvement in product quality is consistent with past history of the Quality Control Program.
PNP - Identification of
Potential Savings
Critical Variables,$60.000TSD Job No. 8^9
TSD Objective C - 3
Correlations (99,9% confidence) have been found between PNCB usage and re actor pressure, temperature and caustic concentration when these variables are combined into a calculated parameter,T, which is the difference between the reactor temperature and the boiling point of the reactor mass. From these correlations several combinations of variables will be defined and tested to restore standard PNCB usage for a $10,000 per month savings over
present levels.
Automatic Still Control
Potential Savings ______ $79.000
TSD Job No. 964
A progress report was written outlining the Phase I approach adopted by the Task Force (Dunlap, Lawrence, Veazey). An AFE is being written. The Parathion MIP prepared by Process Engineering Group I shows a required date of 10/1/70 for a decision on distillation practice. A target of 3/1/70 is realistic for installation of Phase I instrumentation, leaving 6 months for study and modification to meet this deadline.
ENGINEERING DESIGN AND SERVICES
Mechanical/Electrical/Instrument Design and Drafting
J. C. Price. J. A. Veazev. J. 0. House. G. W. Richey. R. V. Carlisle. R. L. Brewer, J, K. Rennie. J. Childress (W. F. Taffeel ___________
The new emergency generator, for replacement in the Parathion department, has been received. Completion of design and installation is targeted for September.
0SW 551275
STLCOPCB4089692
ENGINEERING DESIGN AND SERVICES - (Cont'd.)
.Company confidential 8
Acetone Recovery - $12.9/yr,, savings and Automatic Still Control $79 M/yr. savings received major instrument-electrical attention during August.
Premises were prepared and forwarded for the following projects: Dis mantle Santowax OMP Facilities, Dismantle Old Santowax Still, Install Barricades Around Aroclor Heaters.
Review drawings were completed for the following projects:
Reduce Acetone Stripping Pressure - Niran, Install Jet Vent, Tank Santowax (AFE 3052 - $2.5 M), Biphenyl Pilot Unit (AFE 3297 - $13 M), Debottleneck Solid Aroclor (AFE pending - $20 M).
Construction drawings were completed for the following projects: Biphenyl Column Level Alarm (AFE 3O58 - $3.3 M). Drafting in progress on the following projects:
Replace Niran Generators (AFE 33^5 - $41.9 M), Install Heat Exchanger in Biphenyl (AFE 3282 - $1.4 M).
UTILITIES ENGINEERING
J. C. Price, M. L. Marcum (W. F. Taffee)
Initial results of Biphenyl Cooling Tower Treatment are good and August
savings for this project are estimated to be $600. Transmittal of this
project is scheduled for September. Completed final design of Steam
Meters (AFE 2821 - $12.9 M) and Water Meters (AFE 2984 - $18.9 M) and
forwarded for drafting. Completed review of steam plant operation and
collection about 50ft of data required for preparation of the Steam Plant
MIP.
.
Plant Improvement
G. C. Goodwin (W. F. Taffee)
AFE 3226 - $9.0 M - Automatic Fail Safe Valves for Niran Raw Material Storage was forwarded for approval. AFE 3293 - $7.1 M - Upgrade Existing Fire Water System was approved. Design is scheduled for late September.
Design packages were forwarded for: Aroclor Safety Shelter (AFE 3202 $1.5 M), Niran Safety Shelter (AFE 32O3 - $1.5 M), Biphenyl Safety Shelter (AFE 3204 - $1.5 M), HC1 Area Drainage (AFE 3221 - $1.9 M).
POLLUTION CONTROL
E. G. Wright (W. F. Taffee)
Waste Audits Aroclor, HC1, Niran and PNP
TSD Objective Pollution Abatement _____________ F - ^
Report on waste audits in Aroclor and HC1 departments was completed and and issued during August. Audits in Niran and PNP departments have been completed and report will be prepared during September.
DSW 551276
STLCOPCB4089693
> '
Company confidential 9.
POLLUTION CONTROL - (Cont'd.) HC1 Neutralization Pit____________Production Assistance
TSD Objective F-4
A test run is being conducted on the HCl neutralization pit to determine its capacity and to determine how often it must be cleaned out. Pre liminary data indicates with clean and fresh rock and design retention time it will completely neutralize the present average daily loads from the Aroclor department.
Waste Treatment
All wastes were effectively treated during August. Solids sewering continues to create some problems. Average daily values for Monsanto effluents are as follows.
PNP COD Parathion BOD
Specifications 5 ppm
200 ppm >^1.0 ppm (Max.) ^1200 ppm
oS\N 55A277 STLCOPCB4089694
PLANT LABORATORIES G. W. Miller
.Company confidential 10
'NSI>
.A
PROCESS RESEARCH AND DEVELOPMENT J. T. Bell
Of the 105 PR&D mandays available in August, 67 were expended on projects listed in the 1969 PR&D Program. In addition, 8 mandays were used in the HB-40 Color Improvement project with the remaining mandays divided between vacations, illness, supervisory, and miscellaneous duties.
Blend Scavenger Refinement (Aroclor)
Improved Aroclor Electrical Properties
J. L. Brown
Active work suspended temporarily by equipment failure. The necessary changes to the refining column are set for 9/15/69., at which time the project will be resumed.
HB-40 Process
Determine Process
Studies Variables;W. H. Howard
Contamination in the laboratory equipment has prevented hydrogenation by a continuous process. Substitution of equipment has reduced but not eliminated thA problem. This study is approximately 25 mandays behind the schedule of the project work plan.
Biphenyl Tubular
Obtain Desired
Pilot Studies ___________ Biphenyl/Terphenvl Ratio
J. L. Brown ,,
Cost estimates for the proposed Biphenyl Pilot Building currently being prepared by potential contractors are due 9/2/69. Final plans will be, completed and issued for construction by 9/8/69.
Muriatic Acid Organics Level Determination I. Ransaw
The laboratory study as defined in the project work plan has been completed. A PR&D report will be issued 9/3/69.
Low Color Aroclor 5460
Develop Alternate Process
G. L. Arnett
An alternate process to the sodiutn treatment of Santowax has been demonstrated.
The distillation of Aroclors 5060 and 5460 over a combination of lime and
NaOH is effective in reducing color. The optimum levels of the color reducing
agents have been determined.
.
HB-40 Color Improvements
Column Absorption
J. T. Bell
The identification of HB-40 color bodies by infrared and gas chromatograph
techniques have been unsuccessful. A study of various bed lengths has been
delayed by a lack of high color starting material.
-----
DSW 551278
STLCOPCB4089695
> PLANT LABORATORIES (Cont'd)
.Company confidential 11
PROCESS RESEARCH AND DEVELOPMENT (Cont'd)
Parathion Isomer Reduction
' Increased Yields
G. L. Arnett
A project work plan has been issued with work to resume immediately.
Parathion Condensation
Reaction Studies
Increased Yields
I. Ransaw
A project work plan was issued 8/15/69 to cover the initial phase of the study. Effort is being expended to determine the cause for the low assay parathion that is being produced in the laboratory.
ANALYTICAL AND QUALITY CONTROL S. 0. Kemp Complaint Report Quality
None YTD Quality Complaints/100 Shipments 0.23
Target 0.20
DSW 551279 STLCOPCB4089696
COMMUNITY RELATIONS. PERSONNEL. RECRUITING. AND DEVELOPMENT
Personnel 1. G. W. Richey, BSEE from McNeese State, reported to work on August 18
and assumed the position of Electrical-Instrument Engineer I. 2. J. 0. House reported for work on August 18 as Senior Design Engineer. Development 1. R. V. Carlisle, G. W. Miller, T. W. Lawrence, I. Ransaw, and J. L. Brown
attended "Safety Management Seminar" conducted by Liberty Mutual Life Insurance Company at Holiday Inn, August 12-13. 2. J. C. Landwehr participated in Innovation Exchange Program August 7-8 at the Avon Plant. 3. V. R. Haupt visited Goslin Corporation August 8 at which time Aroclor 1268 flaking was demonstrated successfully. 4. All department supervisors attended the workshop sessions at which time Van der Water Associates, Inc. presented the feedback of the recent plant attitude survey. Visitors 1. Mr. C. A. Beuhler from the WGK Plant visited on August 11 and 12 to obtain information necessary to compile an "L" manual for the Anniston Plant. 2. Gene Stewart of CED visited on August 13 and 14 concerning new HC1 tank car loading track. 3. W. R. Robirds visited August 24 at which time the lastest revision of the Parathion MIP was reviewed. 4. R. S. Yates visited August 11 and 12 to discuss solid Aroclor expansion.
DSW 551280
STLCOPCB4089697
) -
' DISTRIBUTION OF TIMS BY TECHNICAL SERVICE
PROCESS IMPROVEMENT
NSW PRODUCTS
PLANT IMPROVEMENT
ASSIST OPERATIONS
SPECLAL ENGINEERING SERVICES
TECHNICAL MANPOWER
MISCELLANEOUS ACTIVITIES
AND ABSENCES
STLCOPCB4089698
IN MiMNTENANCE
FOR CONSTRUCTION
IN MAINTENANCE COM?LETED
NOT CLOSED
PROJECTS SUBMITTED
FOR APPROVAL
APPROVED PROJECTS IN TSD
TSD PROJECT SUMMARY
DSW 551282 STLCOPCB4089699
)
ANALYTICAL SAMPLES
LABORATORY ADMINISTRATION
ANALYTICAL MANPOWER
Manpower/sample
0.6 \---------- i
0.4
.........I 0.2 1
i^ i
ll I'V^i i i...
ii i1 . 1 1 ___ 1__,
| ----~f | ii ii
11.00
1 --m-- --j--j
10.00
1 j^\\\
I1
$/Manhours
9.00
1 r' 1
8.00 1 1 11 11
7.00
\\\ V! w
\t\\ ///v
\W 1 w1
11 ____ L ^1
r i_____
% Total Plant
Operating Cost
r <=--j
i n3
ii 1i
Overtime "L
--^-- i 1
STLCOPCB4089700