Document mbj0B2MjdLpm17wXE8NaKMbOk
-J"' " ` v*-f-t<^V,
COMPANY CONFIDENTIAL
VW"j* Wt<* SXi-r+NW*-* ^ > Tg*---,
`VC'- Anniston Plant .
-v \
TECHNICAL SERVICES DEPARTMENT
MONTHLY REPORT
Anniston
Summary
C. K. Eastman A. G. Hill L. C. Lahman J. C. Landwehr
G. W. Miller W. B. Papageorge W. F. Taffee . H. L. Williams
Month
September, 1969
Cost Improvement Results - ,
Est. Act. $63,120
Target $66,285
% of Target 95.SZ
General Offices
YTD
$430,976
$438,570
98.5*
H. S. Bergen / \ C. Carder V /. Danna (5)
P. B. Hodges D. B. Hosmer (2) W. A. Kuhn J. A. Morgan W. R. Roblrds J. E, Smith J. A. Stephens R. J. Stratmeyer H. S. Trail
OTHER LOCATIONS
A. H. Foreten Alvin, Texas
D. W. Jackson WGK
M. Patrick So. 2nd St
Organic Division
The Solid Aroclor 5460 yield increase instrumentation has been installed. Calibration and start-up will begin when 5460 is produced in early October,
The Sandvik belt test on Montar 5 was successfully completed. Installation costs will be estimated in October,
Muriatic Acid - MIP was reviewed in plant on 9/10. Necessary revisions to be completed during October.
Agricultural Division
;
The Acetone Recovery project was verbally approved 9/29 for $32,125 capital and $28,600 expense. Expected savings are $40,000/yr.
C.E.p. has suspended scoping and estimating activities on original Sulfur Recovery Project and will evaluate alternates to obtain the major yield savings at a lower capital cost.
Niran - Tentative Process Amendments are being prepared for
plant trials of Freon-21 replacing Freon-11 as chlorinator
coolant and HCl replacing nitrogen as chlorination sparge
gas. .. .....,
- : - v .'
DSNIM 377550
v- "
COMPANY CONFIDENTIAL INFORMATION
"This document contains confidential information which is the property of Monsanto Company. Only those portions of the document relevant to a duly authorized individual's need to know may be exerpted for him. The report must not be sent outside the Company without written approval and the recipient is accountable for its safe keeping, exerpting or otherwise disclosing of its contents and for its proper disposal."
STLCOPCB4099282
Company Confidential 2.
Utilities Evaluation of Central Air Compressor system started, with December report target.
Design & Drafting Data being gathered for electrical protective device study which will lead to recommendations to improve reliability of overload protective devices in important feeders. Construction drawings forwarded for Biphenyl Pilot Unit building and Parathion emergency generators.
Pollution Control HC1 neutralization pit continues to successfully treat all waste acid. Construction 95% complete on test unit for removal of solids in Waste Treatment Plant effluent. Start-up targeted for early October.
Quality Control The Plant Quality Score was 86.1, down 7.6 from August with a YTD score of 88.1 against a 1969 target of 95.0 minimum. Unfavorable trends continue in Aroclor 5460 solubility, Aroclor 1242 low dis tillation and TC Chlorides. Raw material benzol remain at low distillation level, with intermittent high toluene.
. C. Landwehr :kd
DSW 377551
STLCOPCB4099283
ORGANIC DIVISION 1969 TSD COST IMPROVEMENT
ANNUAL JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV .DEC
Sol.Aro. Level
TAR
2250 2250 2250 2250 250. 225Q. 2250 2250 2250
Ind. & -Still SpG EST
AFE 3015
ACT
Solid Aro.
TAR
Lower 5060 Soft. Point
ESTJ ACT
--- "-
2600 2600 2600, 2600 2600 2600 2600 2600 2600 1500 5490 4390 215 C 4670 800C 4230 773O 3475 1500 5490 4890 2150 467 C 800C 423U 7730
-
--
Sol.Aro.-Still Coolant temp.
TAR EST.
160 170 160 170 160 170 160 170 160
- --
--
AFE 3015
ACT
Sol .Aro. -Chlortor TAR
Batch End
EST:
AFE 3015
ACT
390 --
390 390 390 - -- '
**
390
390 '"
390
390
590
Sol.Aro. Yield . TAR
SW/R Composition EST.
AFE 3016 '
ACT
2750 2750 2750 2750 2750 ?750 2750 2750 , *
Solid Aro. Montar 5 Flake AFE 2949
TAR EST ACT
1080 1080 1080 1030 1080 1080 1080 1080
---"
Sol .Aro. Blend 4465
TAR EST.: ACT
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500. 1690 1920 1680 1490 710 1180 990 221r 1690 1920 1680 1490 710 1180 990 220
Sol.Aro.-Vertical Still Cond. AFE 2324
TAR EST: ACT
70 80 70 80 70
70 90 90 9 0 90
--
70 90 90 90 90 -
Sol.Aro.Cl2 T/C Dock AFE 2342
TAR EST: ACT
940 0
0
940
950 "
Sol.Aro.-New Cl2 TAR
Unload - No Delay EST'
CED 1831
ACT
900 900
950 940 950 940 2330 5050 2320 1650 233O 2050 2320
950
940
950
Solid Aro.-Flake TAR
& Drum
ESI.
CED 1430
ACT
Liq.Aro.
TAR
48-53 M #/yr.
EST
AFE 2545
ACT
3000 3000 5000 5000 5000 5000 5000 5000 5000 5000 5000 5000
C00J
rA
ro
'0 0
0 looo 2000 2000 2000
3000 3000
0 10 00 2000 2000 3000 300L 3000
3000
- - - *- -
--
0 5500 0 5500
-- -- -
Liq.Aro."No.2
TAR
3000 3000
Still Entrain Sep. EST.
AFE 3093
ACT
Liq.Aro. -Montar Disposal AFE 2952 Warehouse Reduce Manpower CEA 1452
TAR EST/ ACT TAR EST; ACT
1080 1080 1080 1080 1080 1080 1080 1080 1080 1080
0 00
00 0 -
0 00
00
-
000
K'
000
ro
2000 3000
3000 3000 3000 3000 3000 3000 3000 3000
2000 2000 200C 3000 3 000 3000 3 000 3000 30.0C 2000 200C 200C 3000 3000 3000 3000 3OOP
Liq.Aro.New
TAR
Burners #3 Still EST
ACT
1500 1500 1500 1500 1500 1500 1500 1500 1500 1500
0
0 1500 3000 900 0
-
0 0 1500 3000 900 -
Biphenyl Relocate TAR
No. 1 Preheat EST
CEA 1892
ACT
HB-40
TAR
2nd Autoclave AFE 3102
EST ACT
500 500 500
1500 15 0C
0 1560 0 6 10
3000 3000 3000
2230 2580 0 3490 242C 0
500 1870 1370
500
.0 0
500 500 500 0 "151)0 0
0 1500
500 -
500
3000 3000 3000 3000 3000 3000 3000 600 9000 6000 5600 4200" 5UU 600 10,40d 8600 7450 6950
500 3000
500 3000
DSW 377552
STLCOPCB4099284
ORGANIC DIVISION 1969 TSD COST IMPROVEMENT
Bi0 Improve Tower Treat. AFE ^155 Improve Pit. Power Factor
Central Air System
Optimize Rx Time
PNP Reduce Mole Ratio NaOH/PNCB PNP New Wash Water Pump " PNP AFE 2998 Automatic pH Control PNP HC1 Filter Pump
New Blow Tank
HC1. 150,000 Gal.-HCl Storage Tank AFE 2468 Produce Staley Grade Acid AFE 3076 Clg-Plt, Shutdown
CEA mi Hg Recover from Residue
Hg Wash Tank
AFE 2802 Biphenyl Productivity
Total Organic By Month M $
Total Organic YTD M $
TAR
EST ACT TAR EST ACT TAR EST ACT TAR EST ACT TAR EST ACT
TAR EST ACT TAR EST ACT TAR EST ACT TAR EST ACT TAR EST ACT TAR EST ACT
TAR Est ACT TAR EST ACT TAR EST ACT TAR EST ACT
TAR EST ACT TAR EST ACT
450 0 0
900 0 0
450 5
0
900 500 500
450 0
450 584 585
450 645
450
450
450
900 900 900 900 ~9U(T 900 83O 990
900
900
900
1000 1000 1000 1000
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
0 3420 0
0 0 2940 riser 0
0 3420 0
0 0 2940 2370
4000 4000 4000 4000 4000 4000 4000 4000 4000
0
00
000
0 00 0 0
50 50 50 50 50 50 50 50 25 50 50 50 50 50 50 50 25 50 50 50 50 50 50
500 500 500
mo 330 330
200
200 200
350 340
330 340 330 340
200 200 200 200 200 200 200 200 500 200 200 200 200 200 200
1760 1760 1780 1760 1760 1780 1760 1760 1780
0 _ .'
0 2640 3290 2990 0 2830 $^$0
780 780 790 780 780 790 **
8880 8880 8880 8880 8880 8880 8880
8880 223C
+2385 L9900 i-1990C +2855 19900
250 250
3910 0 3910 . 0
250 0
0
250
0 0
250 250 250 250
00 00
0 00
5600 5600 5600 5600 Tgoo 5600 5600 5600 5600 5600 5600 5600
0 9(J0u 15,00C 0 0 0 3ffiiDl 2700 0
1800 5900 13500 0
0
0 307 8C 2700
250
29^3 $7.5 42.$ 51.1 51.6 51.6 51.6 52.7
50.. 6
27" 1 30.2 11.5 36.3 39.^5 107.4 53844 49.41C 16.5 23.8 27.8 11.4 25.75 45.9 110.$ 258J6
2JO 50.1 79.4 116.9 159.2 21(33 23lT 3133 3S.1 `417.8 47_1._3 521_.9_
46.9 78.8 79.6 115.9 144.4 25a5 $1555 368.86 3 16.5 40.3 68.1 79.5 105.2 151.1 251.25] 319.45 2
luded for May & June
**$27,780 adjustment included for months
January thru June.
DSW 377553
STLCOPCB4099285
AG DIVISION 1969 TSD COST IMPROVEMENT
ANNUAL
Cooling Tower
TAR
Repiping
EST
AFE 2598 Optimize N2 &
-ACT TAR
Cl2 Levels
EST
ACT
Increase Waste
TAR
Acid Sales
EST
-ACT
Chlorinator R.I.
TAR
EST
AFE 2244
ACT :
EVOP Condensation TAR
Rx. EST
ACT
Cl2 Unloading
TAR
EST
CEA 1831
ACT
Recycle Wash
TAR
Water
est:
AFE 2960
ACT '
Parathion Recovery TAR
EST
AFE 2655
ACT.
Reduce Acetone Losses
TAR EST
ACT
Formulations
TAR
EST
AFE 2897
ACT
Change Cooling
TAR
H20 Item 7J7
EST
AFE -5067
ACT
Well H^O to Jets
TAR
EST
ACT
Ag. Division by Month
TAR EST
ACT
Ag. Division YTD
TAR EST
ACT
Ag. Division
TAR
untargeted-R.M.
EST
Charges optimizati- rACT
Organic Div.
TAR
Untargeted - HC1 EST
Catch Tank& Coale^ eACT
Ag Div.-Untargeted TAR
$3 Cl2 Change out
EST ACT
JAN
750 0 0
750 0
750 0
FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
4^0
0 0
420
0 0
410 0 0
410 6
0
420 0 0
420 0
410
420
420
6600 6700 6700 6600 6700 6700
0 00 0 00
00 00
0
i 03
400 300
400 500 300 400 300 300
00
0
0 00
0 0. 0 O 0
250 250 250 250 250 250
00
0
* 00
750 500
500 750 750
0 12,615 0 12,615
5000 5000 5000 2000 2000 2000
0 0 1580 00
290
0 0
290 0 0
290 0
290
290
290
5800 5800 5800
-
IW
ON 4>
OO
00
oo ip *il0 ,
4300 4300
1600 1600 1600 1600 1600 1600 3000 6600 10,GCCi 4570 2000 3950 43OO 10,400 928^ 4570 1205
125 125 125 125 125 125 120 130 155 272 333 310 120 180 171 272 333
125 500
125 500
125 500
750 500 9145 9145 917-5 14675 1468 5 14685 .14575 1 448 5 14485 12$5 3,12C 6,730 10,155 4842 4033 1371C
0 12/35 4,420 10,580 9459 484:
1500 POOC 11145 20290
44i rd 58785 73470 38C45 102530 117015
12,65
23,015 37,770 41,91c 45,949 6^114
0 12,65 L7^035 27,615 37,07441,916 48,4%
0
17 OC 369 C
0
5000 0
1700
00 0 6250 596C 4690 I330lj 935C 6817 4920
- 4180 3250
DSW 377554
STLCOPCB4099286
AROCLOR
Company confidential
5.
E. E. Bowles, C. R. Mcllwain, J. W. Mattern, (V. R. Haupt)
Evaluate QuaterphenylPolyphenyl Effects on Solid Aroclor Yields;NFC
1969 Savings $63,200 $14.000
TSD Objective B - 8(a)
Radioactive source for level alarm installed. Representative from Ohmart Corp. conducted radiation survey and instrument checkout. Start up delayed because of department downtime and producing Solid Aroclors other than 5460. Expect to start mid October.
Montar Use and Disposal
Savings $13,000
TSD Objective
Project 2952
____________ NFC
$10.000B - 8(g)
Request to change route of piping to avoid going through the Chlorine plant has delayed installation of project. Necessary equipment delivery date is estimated at 4-6 weeks.
Sandvik Belt Cooler for
Solid Aroclor Expan-
TSD Objective
Montar 5 Solidificationsion EvaluationB - 8( j)
The Pilot Unit Testing has been successfully completed with good results. Price and size estimations have not been finalized. However, preliminary "ball park" figures show that a belt to handle 8000^/hr. requires a cooling width of 4 ft. x 55 ft. long. The purchase price of this size unit is in the 35 M dollar range.
Porocel Columns CEP 2152_________________
Assist ProductionTSD Job No. 950
North Porocel columns to treat chlorobenzenes were started up on September 19, 1969. Results of first trial were inconclusive. Further quality improvement tests are planned.
The start-up of the South columns has been delayed by the Aroclor fire. Start-up is now planned for the week of October 6, 1969.
BIPHENYL-SANTOWAX
W. G. Niemeyer, D. A. Self, J. M. Jones, (V. R. Haupt)
Debottleneck BiphenylSantowax Distillation Area to 87,6 M lbs./yr. Biphenyl______
Capacity Increase
TSD Objective B - 7(a)
Installation of by-pass loops with blow-out connections for the two Santowax C flow meters was scheduled for 9/10/69. However, only about one fourth of the planned work was completed. The problem was that the operators were not able to unplug the recycle line and it was not safe to cut and weld on the line. Maintenance is now scheduled to unplug the line. A capacity/performance test run will be conducted on the Santowax distillation column after the meters are re-installed and calibrated.
DSW 377555
STLCOPCB4099287
BIPHENYL-SANTOWAX - (continued)
.Company confidential 4
Low Biphenyl Santowax for FDA 5460;Support B - 7(b)
Sales
TSD Objective
A tower water loop study is in progress to try to increase the cooling
water flow to the Biphenyl/Santowax distillation area. Increased cool
ing water flow to the distillation area is required to produce low
biphenyl Santowax.
.
Prediction and Control of
Dust Explosion Potential in
Biphenyl Flaker Packaging
System_______
'____________
SafetyTSD Job No. 951
At our last plant meeting on this problem, we decided to convert the biphenyl packer from fluidizing with air to fluidizing with nitrogen. However, the estimated operating expense for nitrogen is much higher than originally thought. The estimated operating cost for nitrogen will be $13,000 to $14,000 per year compared to $1500 that was originally esti mated. We plan to proceed with this conversion, in spite of the high cost, to eliminate a hazardous situation. Inert gas generation equipment will be evaluated to compare operating costs and most economical method used long term.
Designed Experiment Run on
Process
TSD Objective
No. 1 Biphenyl Furnace____________ StudyB - 7(e)
All the samples have been analyzed. Preparation of a progress report is in progress. Test results will be used to update math model of this process.
Install Knockout Tank on Santowax Jet Vent
. SafetyTSD Job No. 862
Complete design package was transmitted to Maintenance for construction on September 9, 1969.
Natural Gas Safety Shut-off
Interlock Switch
Safety
TSD Job No. 948
Complete design package was transmitted to Maintenance for construction on September 25, 1969.
S^377556 STLCOPCB4099288
Company confidential 5.
HC1 G. L. Moore, L. 0. Chambers, K. G. Hale, (A. G. McCarty)
Production of Staley Grade Acid - AFE-5076 __________
New Earnings $288 M
TSD Objective
Potential Savings $71.000B - 10(c)
Savings of $13,300 resulted from the Coalescer and Catch Tank project during September. Spare elements of a modified design are being completed by the vendor.
Plant pilot carbon treatment studies are scheduled to be run in November. The objectives are; 1) Accumulate design data necessary to expand the carbon treatment area, and 2) determine the carbon treatment and condi tions necessary to produce "Staley" acid. An experimental project for pilot test facilities is being issued ($700 experimental expense).
' Issue HC1 MIP __________
TSD Objective Planning;___________________ B - 1(b)
Plant review was held on 9/10/69. Revisions are being made to several sections as a result of plant review. Revised copies will be submitted for final review by 10/31.
Reduce High Free Cla in Muriatic Acid _______ :Quality ___________________ TSD Job No. 950
An expense project is being issued to install necessary piping to air blow a second storage tank and provide a temporary air supply until the cause and/or cure to the high Cla problem can be found.
PNP L. 0. Chambers, K. G. Hale, (A. G. McCarty)
Debottleneck to
1.8 M
___________________
Capacity Savings $27.500________
TSD Objective B - 9(a)
Process changes targeted at reducing PNCB usage resulted in let-down problems during September. No savings resulted in September. Additional changes will be made and monitored by P. & Q.A. to attempt PNCB usage optimization.
NIRAN
K. G. Hale, D. W. Dudley, T. W. Lawrence, (A. G. McCarty)
Demonstrate Parathion
Savings $17,400
TSD Objective
Recovery ________________ _______10-15% Reduced CODB - 5(a)
No change in status. Construction in progress on test facilities.
DSW 377557
STLCOPCB4099289
Company confidential 6.
NIRAN - (continued)
Acetone Recovery___________________
Savings $12,900 20% Reduced COD
TSD Objective B - 5(0
Recovery tests on #3 condensation reactor indicate a 30% reduction in acetone loss. Gross savings (ethyl and methyl) from increasing acetone recovery is $40,000 per year plus a 20% reduction in COD load. Project 3340 was verbally approved 9/29 for $32,125 capital and $28,600 expense. Manpower evaluations are presently underway to determine what parts of the project will be installed during the '69 fall turn-around.
Central Chlorine Unloading for Niran ________________________
Savings $21,000 _____________,______________
TSD Objective ________ B - 6(a)
Evaluation of rebuilding 12 year old compressor vs. purchasing new com pressor favors the new compressor. Compressor will not be purchased or installed until late winter to prove worth of air pad on "cold chlorine cars" during winter.
Sulfur Recovery
$271,000/yr. Net Sevings
from Residue 53% Reduction in S0oB - 5(d)
TSD Objective
C.E D. has suspended work on the Sulfur Recovery scope and will evaluate alternates to obtain yield savings at a lower capital cost.
The new objective would be to remove sulfur and recycle organics, but not clean-up sulfur for re-use.
... Profit New Sales and Productivity
Improve Chlorinator
Savings $48,000/mo. per 0.5 Hour TSD Objective
Cooling SystemReduction in Chlorination TimeB - 5(g)
A Tentative Process Amendment is being prepared to cover plant trial of Freon-21. If approval is given, expect to begin trial approximately one month prior to the end of the 1969-1970 Ethyl run and extend approximately one month into the 1970 Methyl run.
Improve Intermediate Distillation CapacityCapacity TSD Job No. 972
Possibilities are remote for obtaining significant increases in inter mediate distillation capacity with existing equipment. It is felt that thin-film or wiped-film equipment may be suitable for processing this type of material rapidly. Contacts will be made with thin-film vendors to explore the possibility of application to this problem.
DSW 377558
STLCOPCB4099290
NIRAN - (continued)
Company confidential 7.
Replace Nitrogen with HC1 for Chlorination Sparge Savings $60.000TSD Job No. 605
_
Anniston PR&D has shown that HC1 sparge produces no adverse effects during chlorination compared to nitrogen sparge. Since HC1 is produced during chlorination, it could possible be recovered for use as sparge gas replacing nitrogen. A tentative Process Amendment will be prepared covering a plant trial of sparging with cylinder HC1.
PROCESS AND QUALITY ANALYSIS
J. L. Murphree, Allen Hale, (W. B. Dunlap)
Process Surveillance
.
An 18 month downward trend in distillation level of raw material benzol was revealed, culminating in 6 tank cars out of specifications. Toluene in benzol was found to be out of spec. These factors may be related to a documented increase in Aroclor 1242 TC Chlorides over the last 5 months.
PNP-Identification of
Potential Savings
Critical Variables______________ $60.000_____________
TSD Objective C - 3 TSD Job No. 8^9
A final report on yield study was written. Reactor settings will be ad justed and controlled experimentally to verify the statistical prediction of the study.
Potential Savings Niran Still Control; _____________ $79.000TSD Job No. 964
An AFE was approved to obtain and install control equipment. Design and drafting is scheduled for the 4th quarter. Installation EDC is 3/1/70.
ENGINEERING DESIGN AND SERVICES
.
.
Mechanical/Electrical/lnstrument Design and Drafting ' .
J. C, Price, J. A. Veazey, J. 0. House, G. W. Richey, B. D. Morgan, R. V. Carlisle, R, L. Brewer, J. K. Rennie, (W. F. Taffee)
Design was completed on Project 3161 - $3.8 M, Automatic Temperature Control of Thio Acid Reactors #1 & 2. Review drawings were transmitted with con struction drawings to follow in October.
Design is in progress on Project 3H8 - $9.7M, Modify Agitator Interlocks on all critical vessels in the Niran department. Transmittal is expected in October.
os**1559
STLCOPCB4099291
ENGINEERING DESIGN AND SERVICES - (continued)
Company confidential
8.
The following project safety reviews were held or attended: Fire Pump Capacity Check Equipment (AFE 5227 - $4.1 M), Install Pressure Control Valves in Fire Protection System (AFE 5211 " $5.7 M), Biphenyl Pilot Unit (AFE 5297 - $15 M).
A program is underway to gather data necessary for preparation of a short circuit coordination study of the electrical portion of the Niran department. The results of this study will lead to the compilation of a program for testing switches, circuit breakers, protective relays and, in general, all major electrical equipment that could cause prolonged downtime due to its failure.
Training and supervisory time remained at a high level this month because of time necessary due to three recent manpower additions to the department. One E & I Technician is on loan to the Maintenance department to instruct maintenance employes in an electrical instrument course.
Premises were prepared and forwarded for the following projects: Niran Intermediate Tank-Car Cleaning, Building 27 Dismantling, Eliminate "Head Knocker" at Aroclor.
Drafting
Review drawings were completed for the following projects:
Install 4" Heat Exchanger in Biphenyl (AFE 5282 - $1.4 M), Final Wash TankPNP (AFE 5542 - $2.0 M), Automatic Temperature Control of Thio Acid Reactors (AFE 5161 - $5.8 M), Dual Chlorine Relief Valves - Niran (AFE 55IO - $5.5 M), Acetone Recovery (Electrical) (AFE 53^0 " $50.7 M).
Construction drawings were completed for the following projects:
Replacement of Water Loop-HCl (AFE 32b0 " $8.4 M), Biphenyl Pilot Unit (AFE 5297 - $15 M), Debottleneck Solid Aroclor (AFE 2897 - $20 M), Replace Niran Generators (AFE 5505 - $41.9 M), Install Nash Compressor at Eimco Filter-Waste Treatment (AFE 2820 - $4.6 M), Acetone Recovery - (Piping) (AFE 5540 - $50.7 M).
UTILITIES ENGINEERING
J. C. Price, J. 0. House, M. L. Marcum, (W. F. Taffee)
Transmitted review drawings for Test Heat Exchanger (AFE 5282 - $1.4M) on Biphenyl Cooling Water. The design package will be transmitted in October. Started preparation of Utilities Improvement Items for inclusion in the Aroclor MIP. Started evaluations of projects to replace existing air com pressors with a Central Plant Air Compressor (estimated gross savings $12.0 M 16.0 M per year) and to Improve Plant Power Factor (estimated gross savings $5.0 M r $9.0 M). The premise for the power factor project is expected to be forwarded in October and for the compressor project in late November or early December. Continued work on Steam Plant MIP with completion scheduled for December 15.
dS\N 37756
STLCOPCB4099292
Company confidential 9.
PIANT IMPROVEMENT
G. C. Goodwin, (W. F. Taffee)
A premise was prepared and forwarded for Renovating Niran Control Room and Lunchroom. Design package was forwarded for: Up-grading Fire Pro tection System (AFE 3293.- $7.1 M).
Messrs. K. B. Davis and J. Harrison of the Alabama State Highway Depart ment visited the plant on September 26, to discuss the relocation of Highway 202 across Monsanto property. They presented two schemes for the connection of old Highway 202 to the new 202 on the southeast side of the plant.
POLLUTION CONTROL-
E. G. Wright, (W. F. Taffee)
Air & Ha0 Pollution Complaints
Community and
TSD Objective
Governmental Relations ______ B - 2
No air or water pollution complaints were received at the Anniston Plant during September.
P.C.B. in Choccolocco Creek ________
Pollution Abatement
TSD Objective _______F - ^
The first set of samples taken from Choccolocco Creek show levels of P.C.B. from 2 to 8 PPB. These levels will be checked at periodic inter vals beginning in October with another set of samples from the creek.
HC. Neutralization Pit
Production Assistance
TSD Objective F -4
The pit continued to neutralize all of the acid sewered this month. No un-neutralized HC1 has left the plant since August 8. The pit is showing no signs of reaching a break-through point at the present time. Plans are to continue to extensively monitor the pit until it has reached the break-through point.
Choccolocco Creek Wildlife Studies
______ Pollution Abatement
TSD Objective F - 4 __________
Requested Drs. Gunning and Suttkus to do another study of Choccolocco during the fall season. This study will probably be conducted during late October, Samples of the fish and other wildlife from the creek will be collected, frozen, and sent to Organic Research for P.C.B. analysis. This will provide some base data for evaluating the magnitude of the P.C.B. problem in Choccolocco.
DS\N 377561
STLCOPCB4099293
Company confidential
10.
POLLUTION CONTROL - (continued)
Eimco Filter at Waste Treatment
Production Assistance
TSD Objective F - 4 TSD Job No. 808
Construction is 95% complete. Start-up is scheduled for the first or second week in October.
Waste Treatment
All wastes were effectively treated during September. High solids continue to be a problem. Successful operation of the Eimco filter should eliminate the problem. Average daily values for Monsanto's effluent are as follows:
PNP
COD
Parathion
BOD
Specifications 5 PPM
^=200 PPM -==1.0 PPM (max.)
^200 PPM
DSW 377562 STLCOPCB4099294
PLANT LABORATORIES G. W. Miller
Company confidential
11.
PROCESS RESEARCH AND DEVELOPMENT J. T. Bell
Of the 105 PR&D mandays available in September, 63 were expended on projects outlined in the 1969 PR&D Program. The use of the remaining mandays were divided among vacation, supervision, illness, and miscellaneous.
Blend Scavenger
Improved Aroclor
Refinement (Aroclor) ______ Electrical PropertiesJ. L. .Brown
Evaluation of Type 4A Molecular Sieve as an absorbant for column refinement of Aroclor-Scavenger mixes was begun on 9/24 with completion targeted for 10/15/69.
HB-40 Process Studies
Determine Process _______ Variables _________________
W. H. Howard
Equipment failure has temporarily suspended attempts to prepare HB-40 via a continuous process. This aspect of the study is to be continued on 10/3. The effect of quaterphenyl level on reaction times and catalyst requirements has been determined by a batch process. Santowax C has been hydrogenated to HB-40 with an extended reaction period.
Biphenyl Tubular Pilot Studies
Obtain Desired _____ Biphenyl/Terphenyl Ratio J. L. Brown
Plans for the Biphenyl Pilot Laboratory were completed on 9/9 and trans mitted to maintenance. The plans were issued for bids on 9/10. A delay of 15 days caused by failure of contractors to bid promptly has been encountered with construction now targeted to begin on 10/15.
Low Color Aroclor 5460
Develop Alternate Process _____ ;G. L. Arnett
The distillation of Aroclor 5060 and 5460 over a combination of lime and NaOH is effective in reducing color. DTA studies indicate thermal stability of the combination of Aroclor 5060, NaOH, and lime up to 400C. Samples have been forwarded to St. Louis for corrosion studies. A PR&D report is being prepared.
Parathion Isomer
Reduction
____________Increased Yields
________ ;G. L. Arnett
This project has been delayed by illness but will resume by 10/6.
DSW 377563
STLCOPCB4099295
PLANT LABORATORIES -(Cont'd)
Company confidential
12.
PROCESS RESEARCH AND DEVELOPMENT -(Cont'd)
Parathion Condensation Reaction Studies Increased YieldsI. Ransaw
The project work plan has been interrupted to derive a method for determining the actual % conversion in the condensation reaction. The reliability of the method is to be determined by 10/3 with the study, as written in the work plan, to resume on 10/6.
Acetone Recovery (Parathion)Reduce COD LoadG. L. Arnett
Sample analyses have been made to support a plant demonstration of increased acetone removal in the condensation step. This study has been terminated.
ANALYTICAL AND QUALITY CONTROL S. 0. Kemp
Complaint Report
Quality Number
Material
Customer
12-A-69 13-A-69 14-A-69
Aroclor 5460 HB-40 Aroclor 1268
Swift Addyston Plant Central Solvents
YTD Quality Complaints/100 Shipments 0.24
Reason
Organic Matter Color High Melt Point
Target 0.20
DS\N 377564 STLCOPCB4099296
.Company confidential 13
COMMUNITY RELATIONS. PERSONNEL. RECRUITING. AND DEVELOPMENT
Community Relations
1. J. C. Landwehr, W. F. Taffee and E. G. Wright attended a talk by Dr. Roy Ledbetter, Alabama State Extension Entomologist, on the positive benefits of DDT at the September meeting of the Decatur, Ala. Kiwanis Club, September 11.
Personnel
1. Brode D. Morgan, BSEE from the University of Arkansas, reported to work on September 2 as Electrical-Instrument Engineer I.
2. Ralph Noel, D.O. student, Cobb High School, started to work in ED&S
September 18, 1969.
,
3. G. L. Moore, Co-Op from Ga. Tech, has returned to school to complete studies to obtain degree in Chemical Engineering.
4. All members of TSD attended a seminar on Parathion Poisoning Symptoms conducted by Ishmeal Ransaw, September 16, 1969.
5. All members of TSD attended Job Holders meeting conducted by
W. B. Papageorge, September 24, 1969.
'
Recruiting
1. Summer employes reported to school September 15: P. D. Kinnear to the University of Chicago, M. L. Marcum to the University of Tennessee, J. L. Gaines to Auburn University, and A. I. Hale to the University of Mississippi.
Development
1. J. C. Landwehr participated in Innovation Exchange Program at Bridgeview Plant (Chicago), September 25-26.
2. V. R. Haupt visited the Newport England Plant to assist with Biphenyl problems, September 4-20.
3. G. L. Arnett held a seminar at the Luling Plant, Luling, La., to train decontamination team, September 25.
Visitors
1. Bob McCutchan visited the laboratory September 17 concerning Aroclor.
2. W. A. Kuhn visited September 3-4 and was special guest at the seminar and barbecue for new employes.
3. George Hunt from S&PP section of CED visited the plant on September 30 concerning the electrical failure in the Aroclor department on September 27.
DSW 377565 STLCOPCB4099297
PROCESS IMPROVEMENT
T- 1
DISTRIBUTION OF TIME BY TECHNICAL SERVICE Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec.
NEW PRODUCTS
PLANT IMPROVEMENT
( ASSIST OPERATIONS
SPECIAL ENGINEERING SERVICES
TECHNICAL MANPOWER
MISCELLANEOUS ACTIVITIES
AND ABSENCES
DSW 377566 STLCOPCB4099298
IN MAINTENANCE
FOR CONSTRUCTION
600
1
500 ~
400
500
200
100
00
IN MAINTENANCE COMPLETED
NOT CLOSED
TSD PROJECT SUMMARY
--------
--1 1-- ----- --j1--~
i1 s=s4
--__ ---------
PROJECTS SUBMITTED
FOR APPROVAL
cQZo <
CO
o H
APPROVED PROJECTS IN TSD
DSW 377567 STLCOPCB4099299
LABORATORY ADMINISTRATION
0
ANALYTICAL SAMPLES
60 1967 1968 J F M A M J j
i
56 i
i
52 *
i
48 i
f
A iV
i44 ^ fi
i ^h,//
\\ 0
40 l
1V .
2400
2300
2200
ANALYTICAL MANPOWER
2100 2000
1900 1800
1700
------i--
i
i
i
.
1
I1
A,
\1
ii
i
i
1
i
.
^'IkJr
__ ___ LU
'i *i
Ii
A - S 0 *
ND
_
Manpower/sample
$/Manhours
% Total Plant Operating Cost
2.0
1.5
1.0
0.5
SSBSSiSgj
I
czilj:
(. Overtime L
111 ' 11
STLCOPCB4099300