Document jgdqkdQ3dwpvwB2ZXLpd3omgO

To: Distribution Interoffice Communication From: Date: Subject: G. E. Hopkins April 28, 1986 Process Engineering Total Project List VISTA Attached is an updated issue of the total project list for Process Engineering (previous issue was dated January 16, 1986). It is planned to continue to update this list at least quarterly. Let me know if you have any comments or questions. Jrj. , Zlf. 'fafrpJ'u*L/l- G. E. Hopkins br cc: RAC-PEM-MLA-MCM-JRH-WPS-MWC-SCR-VMF-SVC-PLF-JMT-SRAMBD-MGH-PFF ClJH 0000S8S4 PROCESS ENGINEERING TOTAL PROJECT LIST PROJECT >esign Projects EnYlrsamsatal-LCoatlnuedl 5. Hazardous Waste Storage Tanks Secondary Containment ENGE^ PRIO- EITI PRESENT STATUS___ 1 Will coordinate with T-405/452 Compliance Order Plan implementation. Need to assign. REQ'D. COMP. _DATE_____________ July 30 FY 87 Budget Design Need to be installed by August 1987 6. Stormwater Segregation 7. Mobile Waste Collector (HoneyWagon) 8. EDC Railcar Spill Pans 9. Heavy Ends Containment 10. T-405/T-452 Revisions Design (per Compliance Order) 11. Recycling VCM Samples Back to theUnit 12. VCM Shiploading Line Depressuring Revisions 13. T-450 Bottom Replacement MBD MWC JMT MBD MWC VMF MCM 14. Parallel Steam Stripper Operation 15.Cathodic Protection for Storage Tanks GED/DKH MCM 1- Expected to be required for new NPDES permit. 1 Design for first model issued. 2 Design issued for review in April. 1 Need to assign. July 30 FY 87 Budget design Awaiting Construction May 1 Final design 1* Cost estimate for new tank design for T-405 and changes to tank base being prepared. AFE writeup in review. May 2 AFE submittal 1 Final design issued February 6. Cost estimate $18M. AFE in typing. May 1 AFE submittal 1 Need to evaluate per commitment to DEQ following relief valve discharge of Feb. 28. May 15 1 Will use a high pressure water cutting method to April 30 remove existing bottoms. Tank inspected and holes Wet tank located. Preparing design for conversion to wet EDC design tank. AFE draft in review. April 30 AFE submittal 1- Need to assign. Probably will be required to meet new NPDES Permit. May 15 Budget Design 1st Qtr. FY 87 AFE Submittal 2 D. Hansen evaluating. May 15 Budget Design Estimate and Writeup - 4th Qtr. FY 87 AFE Submittal PROJECT h Saety_ft..Healtb i. Noise Reduction BL-302 Relief Valve Discharge Liquid Drainage. f. Noise Survey Items i. Nitrogen Purge for Caustic Tanks TOTAL PROJECT LIST PRIO RITY PRESENT STATUS REQ'D. COMP. DATE VMF MWC SVC MWC 2 On hold. Awaiting evaluation of BL-302 closure control. 2 Will design collection pots. 2 Bleed valves on instrument air valves noisy. Designing condensate traps or mufflers. 2 Final design issued in February. Cost estimate completed in March. Need to submit CWO. April 30 CWO submittal TOTAL PROJECT L IS T 1 CEOCLJ. Q c? [ wQHa||j1 11 01 ft B Hft r1 H3 LiUCcnzmqjj O >i SH ft cq <--<0i CO -OP C S(Qs+H> IuhSk5os oS-qcn0H1o JS3nO ff<tt Pf-EM3tHtas fl-E-O5McnH-1lIsiO--ffpS4t3lDttt)1iCfpa31?t sCff<CtODtt facb4tf)l CC0pO5- -H . f4bt1a f>t- <C30*03O3 fp0t OPP' ff<tt cCO- Pin >ft- On tM <pft oCO P5s f3j ptcno 45 d P TWJ P3Q m P%pPi <Pb33OCTPh3QO) GPPf p wf<t 1 tC-O- a3 sf-t P-PP*--i JCS3OO nM *Wton oCM P oe JfOtQpa OiCn cooID C (COCH1) H iP-Oc&1 >r1f-ot1--ZPPPo4)+gpJtc04))) j5oS cPP* 1P3 0 --CI T3 34Hd) TCPO54iP-JH G o J) -1 H C PaOITJJsO30oco P3<nn >PPS4 fll>t < X3dI ih ffl 4) 1W) CJ 1) Pft P in a3 -O4P} O U ft <oM c o pPO> ft PW P J3 P 4a1) ftt jpj X3mI f46t0) f541t)] -cc fOlyt DT33DT3C3TD33O0P. PP54S) in OP> zp 0 3 ft mCO MCcfl Ms4) 0>45) 4GH) PP43) PO 3PC Pi4n) p -p43CoOo) Po pfoCO4t5 G<-> Zx4455l ft PCJV tii4ponino). pft zo cj J5Os tneo p> iC0*f--O5ti Jp4O5 CPe4f4O55t cH 345 >4) P PO ft T43iinn>-5. C-d4lO Qi4n5 co *bcHO Pp3tHo coo x: tnM a p o p T4435) Z -4o5 I--I --M p m cH PmP4455 Xo>oP E CP T4<3i?n5n >CPg, C3O p0i0font ft Pp45 J3i4On5 TC) 1tCo/D5 i--l CPC0O bj) J4=P5> 4t>5 CQ p3r( QWCP > 5s 05 X> PO 0pft p bdHO a p S3 pH J3 rH fOt cbo f4 o p zd 1 CM CO CM 1-H CO CM u>CO QCO E C>COJ CJ z E C>COJ afftt O! O 5s o pc j--i yyyMHn cy0am3i d a. a p > fot zpp | to fHut >tpi\l fat c rH CoJ nco n > oz PB p p z to o 5P5-s U 05 *Ho r0p-cofEH5t P pc0 pp E pp HGH V) be JGO \PPton ft pp z o zu pu-< JCopO CJ JPf=t bcn pp0 ft EdO E CPO PE CO fXt G p <pp EmcP- bCO o0 COfc<M3t cm P 313 C5OS 9 ' ---- CUH OOOOOc; ob.c^:; /' TOTAL PROJECT L IS T 1 1 a. | e1 O1 CJ lz] H <i OQ O' I H1 os i i tG =1 3 H 21 X tn a oM ptr Hp a 03 d a 21 U3 p V to TJ 3 Q O >min C bo >. t-- P P 01 3 Ol 41 trtQ U"5 pa p 3 ai P S 4) W 4> G p bO E p 41 T3 G 313 > H to p C pP h 0) C P bo >P ts 01 -o "* <P id 3 3 1) EOlD^D (0 P P P E P ,Q CO 3 to P Cs] 0a o< PSPP "3 P >a3 PGO T0b333O P 4o1 P+<J0 P jt-o. a(o bfl f4GO)t.CoCaDDi PcGol>upH > TOG3 pEOlH *03o3 <P1OhGa0"1. tCo-D> a. -oXl v4aa0) >a- G Tg3 Pc O 4J 0) G41 O41 *G3 P >-> P PP41 OCGL,O-CH pGbto0 aoi bGG(aoGaH0O> XGGS Cto -0H pa o bo c *pG3H r<H0 >oi a a CL, * CM p a -S 4J p os o td O P E a> c > - IQ G ap aa Oh <n ptbCoo XpGVEC> >tGo 3OaE PP4C(0E0>) -* <4OGGH> PG t3o G41 p <Oyh to Pt4Go1 PPP4) G3c4)r-aHC<0J pP to *4-1 pc4> g v pPel4Gb) pOG431 g X PbGO p0o o G H pP3 U7 G41 PpP 3 pO P GGa to G -D4CO1 X4) pPP .5 -< - PO4raOIhl1 pC41 E4UG1 p a O4S1 PS4(h0) 3 PPMG oo 0 pO PG >O e 41 g ta c Pp 0 0 u pGo(S4h31 *CocH p E o G P G in r-i px04t3s3a1 l--PGl oa<a cCCOO- p >[xH, PSh 3 PPG. p PE P 10 X3to) C p -p4bo1o O 3 41 XI o p3 Xu OG GG pE i ii x Q a ao --3 ae a a CM o 3 E xP30s1 pHts XH vVGjI 41 <4H -4o) P3 C GbO E i p o 1 u4) TSO3h TOS p 3 C\J C-I s -> OG -CPMiG1it11 p_j ,P--,GM1 P nbC aH r> X3>1 .>3i a H Oa ffiI p tn POi >, 3>G41 P 1 4fGf1i 4Sh1 i--0C, *PHSus oGaG CXJ GpH t-H O a3 41 E<0 iGf) ^430") C 60 p40to1 X3uGl *UH TpC303OQJ 6G430-! pPtca PPOC0o PGOGS4Gh' pPuG 0O o OP Cc0J ' CpEo03J1 Cpu3GJl PPGD < Xo >o aG r--G4O041))< GO CJ CW8 00003S5 ROJECI tliscellanfiflus Small Pump &. Piping to Rerun Check Tank Material S-206 VCM/Caustic Static Mixer EHGR* TOTAL PROJECT LIST PRIO R1IY PRESEHT.STAJUS REQ'D. COMP. HATE______ JMT 2 No progress. JMT 1- Design and cost estimate issued. Need to establish need and then submit CWO if decided to install. o o o o CO o~ 'O PROJECT II. PLART-ASSISIAUCE.PBQJECIS 1. VCM Alkalinity Problem Safety Audit - Cracking Furnaces i l . Kanegafuchi & BASF CatalystEvaluations i. Exchanger Revisions for UCAR (Dome) i '' 15. TAR Accounting Program Compressor EUGR^ TOTAL PROJECT LIST PRIO RITY RESERT_STATUS REQ'D. COMP. ________DATE_____ JMT 2 Monitoring effect of recent revisions & procedures. Providing assistance as needed. Tests conducted on effect of S-206 caustic recirculation rate and new procedures implemented. JMT issued design for better mixing of caustic and VCM. 2 WPS setting up procedures/plan for safety audits. SVC 2 Evaluating R1 catalyst installed during T/A. R&D has Oct. 1986 samples of last bed of catalyst. (Decision on catalyst to replace during T/A. SVC 2 Letter issued. SVC 2 Will issue final critique after expense AFE closed. TOTAL PROJECT LIST i PROJECT : 111 ENYlBQHMENTAL.IIEtlS ENGR^ FRIO- B11X PRESENT STATUS REQ'D. COMP. DATE_____ ;1. Environmental Compliance InternalReview System (Report Card) ERT 1- In progress. i . Notification of EPA of Underground Storage VMF 2 Forms filled out and submitted to E.. Taylor for LCCC notification. May 8 | 3. VOC Regulations Implementation - 2 No progress. Need to assign in next few months to start determining scope. Dec. 1987 I I. RCRA Permit Application MWC 1- NOD Response submitted to DEQ on Oct. 12 and approved in Dec. Will issue summary letter to plant of out standing items needing to be implemented. DEQ technical review still pending (timing unknown). T-405 and T-452 Cleanup Plan (ex Design) (a) (b) (c) (d) Disposal of cleanup drums Sampling of T-405 base Remedial action plan Other compliance schedule items MCM/HBD/ JMT 1 Plan submitted for DEQ approval on Jan.3. Discussed with DEQ in Feb. T-405 cleaned, emptied, and in- Per compliance order schedule spected. Holes found in Dec. Approved plan received from DEQ as new compliance order in April. Procedure to remove and dispose of old T-405 issued and approved by DEQ. Samples of soil under tank analyzed. Appears to be landfillable. T-405 removed from base April 16. T- solids transferred to Fiberpacks week of April 14. In cineration by Rollins scheduled week of April 21. i. RCRA Permit for Incinerator Incinerator Area Sewers Alternative Procedures Writeup MWC/MGH 1 MWC L Mike Hayes prepared Part 1 Application. MWC went to seminar on Incin, Permitting in March. Part 1 Application Submitted March 31 to DEQ. 3. Groundwater Cleanup i. Copper Pit Cleanout MCM/SVC 1* MWC 2 Received Compliance Order from State in April. Team established to document spill history, etc. Conoco issue Phase II report to DEQ. May install a few recovery wells. Vista/Conoco discussions on funding and project management still ongoing. to May 10 Spill History due to DEQ but 60 day extension expected to be approved. Need to obtain sample for lab analysis. 0. Consent Decree Notifications/ Implementation (ex Design) cjj(i 0oosr Bai MCM 1* Revised plan issued Dec. 26 reflecting EPA amendments. Plan enforceable addendum to Consent Decree as of Feb. 7, 1986. Admin. Measures Schedule issued in March. Admin. Measures Aug 7, 1986 Physical Measures April 7, 1907. .'BQJECT ENGiL. TOTAL PROJECT LIST PRIOBUT PRESENT-STATUS REQ'D. COMP. _____ DATE_____ 11. Solid Waste Permit Application 2 .2. ' T-405 Dike Cleanup (a) Reports-7-day report/Contingency plan report (b) Disposal of drums (c) Logbook (d) Cleanup ii3. Incinerator Acid Pit3 Sewer Flow Testing VMF/JMT SVC 2 [14. j [ I New NPDES Permit Implementation (a) Characterization Sampling fit Analysis (b) Impact Determination (c) Compliance Program Development PLF/MWC 1* | 5. Environmental Weekend Duty Action Flow|.8. SPCC Plan Revisions to Reflect Non- [ I .7. hydrocarbon Hazardous Materials Ethylene Dome Flare Permit | 18. Engineering Audit of Caustic Dryers VMF VMF 2 1- MGH WPS/VMF 2 1 . lJ. Procedure for High Level in Flame Arrestor 10. T-450 Spill Cleanup JMT/VMF 1 1 '2. PCB in Heavy Ends Notification -:2. Phenol System Removal WPS/PLF 1 JMT 1 Phil Ward handling for LCCC. July 1986 (Expected) 7-day report issued. Visit by EPA conducted Jan. 10 Cleanup complete. Working on drum disposal. Scheduled to landfill with CWMI on April 25. Need to run test since repairs to line feeding trim pits made. Met with EPA in Dec. on expected permit requirements. J. Ledvina obtained updated requirements in March. Permit draft received from EPA April 16. Plan to start characterization test run May 7; and steam stripper test run in late May. Will then develop comments on EPA draft and determine requirements to comply. Need to include in Environmental Information Manual. Incorporating WPS/GEH comments. Will include materials such as ammonia, muriatic acid, etc. June 13 Comments to EPA Oct 1 Permit takes effect Apr. 30 May 19 (per regs) Part of commitment to DEQ following VCM release of February 5. Need to assign. Notifications/Letters issued in Jan. & Feb. Met with DEQ in Feb. on plan to clean soil under tank through groundwater cleanup. Disposal of contaminated soil outside the tank scheduled with Chemical Waste Manage ment on April 25. Analysis completed by TMS. J. Ledvina issued guide lines letter. Preparing notification. April 30 Working with CWMI on disposal of excess phenol. Will need to ensure proper asbestos notifications made. May 1 000005862 CUH iltQJECl Environmental Items (Continued) :J. Evaluate Extension of PRC-901 Range or Alternate to Determine Quickly Approach to RD-901 Burst Pressure. M. Disposal and Replacement of 1,1,1Trichloroethane Solvent for Degreaser :5. Process Trenches Cleanout and Disposal '6. T-2 Cleanout/West Basin Cleanout :7. Evaluation of Flow Limiting System for Reworking Material EHGIL. TOTAL PROJECT LIST PRIO - EIH EEESEU1_TAXDS REQ'D. COMP. _____ DATE_____ VMF 2 Part of recommendation by DEQ in letter of 11/14/86. JMT JMT JMT VMF 1- Find out if supplier can recycle one drum of material. Check with degreaser manufacturer if non-chlorinated solvent can be used. 1 Need to do to allow process trenches repair for Closed Process Sewer project installation. 1- Discussing with various contractors. Preparing cost estimate for west basin solids disposal. 1- Recommendation by DEQ in letter of 4/21/86. O -i_ O o o o o cn CO oCo PROJECT [V. ENERGY..ITEMS ENGIL. TOTAL PROJECT LIST PRIO RITY FEESENILSTATIIS REQ'D. COMP. ____DATE_______ 1. Production Rate Vs. Energy Consumption Curve 2. Turbine Monitoring Program For BL-501T JMT JMT i. Exchanger Monitoring Program JMT i. Insulation Survey Program JMT ). Steam Trap Inspection & Maintenance Program JMT 5. Furnace Monitoring Program l. Cooling Water Monitoring Energy Training Sessions with Oper./Maint. JMT j Electrical Survey Update JMT 3 SCR issued letter demonstrating present correlation no longer valid and does not cover recent high rates. 2 Looking at with respect to reduced pressure drop to determine when turbine wash is needed. 2 2 2 3 Was assigned to SBL. Need to reassign. 3 Was assigned to SBL. Need to reassign. 2 Requested by MLA. 2 Previous survey done by MWC in 4th Quarter 1984. Dec. 1986 TOTAL PROJECT LIST .'BQJECT EN<jS_ PRIO BIT^ REQ'D. COMP. --DATECOMMENTS EEGULAILSCHEDULED_ITEMS ^ Environmental l. LE5HAP Quarterly Report VMF/MCM 2 March 15 June 15 Sept. 15 Dec. 15 Conoco supposed to have 5 days to review per Consent Decree and Asset Purchase Agreement Annual Emission Testing (Incinerator Stack & Steam Stripper Discharge) PLF 3 Sept. 18 (Test) Oct. 17 (Report) i. Semiannual Report of Oxy Shutdowns VMF 3 Feb. 16 Aug. 16 ; . Annual State Air Quality Report (EIS/PS) -3 March 1 Will need EIQ also in 1987. Annual RCRA Training VMF/MWC 2 May 19 Operations, Lab, and Maint. training complete for 1986. Need to do for some of the staff. MWC revising slide/tape program. i. Monthly Progress Report VMF 1 10th of ea. month to WPS Annual Environmental Meeting -2 Mayl4-15 . Monthly NPDES Summary PLF 1 15th of each month NESHAP/LESHAP Calculations and Reports of Releases (Relief Valves, Oxy Shutdowns, Incin. Bypasses, etc.) VMF 1 As needed .0. Quarterly Consent Decree Implementation Status Reports MCM 2 April 15 July 15 Oct 15 Jan 15 Conoco 5-day review required 1. Monthly T-450/452 Compliance Order Progress Reports MCM 1 3rd of each month 2. Quarterly Groundwater Order Progress Reports MCM or MGH 2 July 10 Oct 10 Jan 10 April 10 Present expected due dates may change after discussion with DEQ. Conoco 5-day review required. 3. Weekly Report Card VMF 1 Every Monday afternoon 4. Annual Env. Cost Report for Bureau of Census MWC 3 March 1 5. OSHA Engineering Controls & Work Practices Update ^ 00qQ()5865 MWC Jan. 1 July 1 TOTAL PROJECT L IS T 3 Ou s 0O w H< OQ Gf W CC 03 CO 3s CO In Ldij +3 _0Q 3 o U 3m 4g) X4) i(s0 D3O > 0 [S<Z x cp u(0 4> & 2 *H +03 O X X -P OP C 0 -< s Li 4) X E 0) P 00). U3 H o ZJ n nw E-- B- U X 2: X X >-3 m 1 X +3 Li 0 a 4) X is Li 4) C a >, I-H Li is 4) *3 Li Ll <3 a3 w O' Xt43) H fc< L0i <W 10 to P <0 M cP 0 < <y is Cl id Li 4) 4) < -O 3 O ca E3 C 0 ca 35 s 3 4) P C/) 03 4) 0 0 CO Li c0 is W 3 O CO O Li nj M Li 4) 4) 4) 0-1 rtj '--1 CP > X w 40 >, .3 is -H is is X p fcQ Li ---i --I Li X X c 4) > 0 4) 0 C 4) V X Cx] 8 x X CUH 000005866 ^BQjIECl Other l. Monthly Progress Report (a) Process Engineering (b) Laboratory Quarterly Capital Budget l. Safety Training (a) Laboratory (b) Process Engineering i. Goals Progress Update Monthly Capital Budget Project Status Review Quarterly Total Project List Review / . Recruiting EUGEL. TOTAL PROJECT LIST PRIOBITX REQ'D. COMP. DATE COMMENTS WPS PLF 1 1 WPS/GEH/ MWC 2 2 GEH/WPS/ PLF 2 GEH/WPS 1 GEH/WPS 1 MWC 12th of month 12th of month each each November 22 February 22 May 22 August 22 Monthly Every other month Jan 30 April 30 July 30 October 30 7th working day of each month January 15 April 15 July 15 October 15 O S= o o CO O' TOTAL PROJECT LIST . R0JECT n. EDLLOtf-UB-BBOJECTS 1. Ethylene Storage Terminal Firewater System ENGB^ SVC PRIO- BUY PRESENT STATUS 1 AFE approved 8/2. Final process design issued in Nov. 1985. REQ'D. COMP. _____ DATE_____ Delisting of Secondary Treatment Facilities Waiting on State approval. AFE changed. May be required to send sample analysis of sludge to DEQ. Aerating west basin. Transferrring some sludge after aeration to thickener. \ i. Flame Arrestor Flush | .. S02 Cylinder Heating Pads VMF VMF Monitor to determine if equipment flushing continues to solve level control problems. CWO waiting for approval. >. BL-307 Seal Revisions SCR Getting requote on "G" type (per MLA). >. Lab Sample/Reagents Disposal j\ Olin HC1 Meter i I Laboratory Equipment i !J. Steam Stripper Packing Replacement | SVC/FLF 1 PED/SVC 2 PLF/GEH 2 SVC 2 Guy Bergeron prepared mechanical design and estimate for $18M for recycling to T-110 using carbon steel piping instead of Kynar. PLF has contract with Ensco for lab packs. SVC preparing AFE submittal. Final design issued Dec. 1985. Meter installation in progress. Previous Olin HC1 expense AFE was capitalised in February. AFE approved in Dec. 1985. Headspace analyzer delivered in April. Coulometric analyser received in Feb. Packing received and installed in February. to monitor efficiency and life. Need ilO. Maintenance and Accounting Computers MWC 1- Computers are here. Accounting computer installed and started up. Maintenance computer installation still in progress. 11. Steam Stripper Controls MWC 1 New temperature controls installed in March. Need to monitor effectiveness. Test run planned in late May. i.2. Check Tank Dip Legs JMT 1 Procedures letter issued. Need to monitor effectiveness after installation. 13. S-412 Pumpout JMT 1 CWO approved in April. 14 . BL-501T Lube Oil Pump MBD 1 Final process design issued on April 2. AFE approved April 22. CUH 000SB68 -ROJECT ENGE. /II . DEPARTMENTAL_D^ELQPI4ENT i . Reorganise Filing System - Process Engr. Design & Procedures Manual Updates GEH/WPS ) . Specification Sheet Guidelines ' Flow Orifice Notebook -j . Relief Valve Notebook 3 . Pump Notebook i . P&I Updates i . Heat Exchanger Notebook 3 . VCM Physical Property Notebook Updates 1 0 . Technical & Management Development Seminars 1 1 . Environmental Notebook Updates SVC 12. Training Lab Techs to use Lotus Wastewater Logsheet MBD TOTAL PROJECT LIST PRIOEIIX PRESENT STATUS 3 3 Draft of first issue in typing. 3 3 3 3 3 3 3 Provide as needed. 3 2 1- Have converted program to reflect completion of P-10 operation. Need to prepare instructions and write protect. REQ'D. COMP. ___ DATE_____ April 30 O sz o o o o o co O' -0 'RQJECT /III. COMPLETED- PROJECTS \. D3ifia_ExJscts_-_EnyironinJit.al 1. Consent Decree Projects (a) In-situ Oxygen Analyzers ENGR. VMF (b) Automatic Tie-Breaker WPS/SCR 2. RCRA Hazardous Waste Storage Area Building JMT Design. Eroiects - SaLaty &_HaaIth. 1. EDC Tarstill Pump Replacement SBL/MWC 2. C-500 Stack Fire Protection and Snuffing Steam MWC Cssign_ErQjfiia_^_Energi: 1. Steam Vent Flow Totalizer Drsign_Er'2Jsci3_-_G?at_Sayiaa 1 . High Pressure Nitrogen Savings MWC MWC COMPLETED , PROJECT LIST COMMENTS Nov. 1985 Nov. 1985 Feb. 1986 Westinghouse analyzers installed in both incinerators. Working fine. Need to prepare as-built P&I for completed projects file. Installed and tested during November shutdown. issued by Randy Denton (LCCP). Status letter Installed by March 1 to meet commitment in RCRA Part 2 Permit Application. Nov. 1985 Nov. 1985 Centrifugal pump installed. Working fine. built P&I for completed projects file. Need to prepare as- Lightning rod and nozzle for steam installed during August 1985 turnaround. Determined steam line not needed. Will use hose when system needed. Nov. 1905 Installed and working fine. Nov. 1985 Installed and working fine. completed projects file. Need to prepare as-built P&I for 1. Polymers Evaluation for Wastewater Treatment MWC/HLH Environmental__Itfima 1. Procedures for PPG Shipments Rejection SCR 2 . NPDES Permit Application Update MWC 3. LCCC Winter Wastewater Plan MBD/MWC 4 . Hazardous Air Pollutant Emissions Survey for DEQ CUH 000005870 MBD/VMF Jan. 1986 Various vendors tested. Bid awarded to Nalco. Nov. 1985 Dec . 1985 Mar. 1986 Apr. 1986 Procedures issued. Included in Environmental Information Manual. Issued to DEQ and EPA. permit for LCCC. Combined LCCP, LCLAB and LCVCM into one P-10 flow stopped in early March. No violations by either LCCP or LCVCM during winter. Summary report being reviewed. Issued to DEQ on schedule. H d] w H 1 StJ3 3j WJ1 at-* 3 a H Cc u E-< W a ut n 3 T5 P rH rH Ul *-H 0 o Oh to a < 41 cc m n CO o 3W < z i a t- 41 o na P ow O 0< OH o M pc e a H 41 p x <w CD p O rH 3 0} +1 S 01 Cl P 3 CD 0 (X OH 0 -P H -H P o o XI c ai c cn xj o 01 *lH 3 cp 41 H CO Xi s3 p ,-H rH 01 CD rH -p > H 01 4) 2 a P CO OP <kH rH *D 3 0) p to 4-> o 01 O 1--l 3 5s . o CD 01 c E- C o O< Cl TJ -rH CP W *3 W -p -1--1 eD O rH O m p a P rH 00 > tD 01 XI 0) p 41 0) 3 3 --rp-1 oi --c to -P 01 01 0? HH o HH CO CO to CD CO CO 0i--5t 01 rH ai X) c p 4 CD <D Cn X> z Hj* CO 05 rH p 41 p P CD 3 O' J= p "T bfl C *iH p 3 XI XJ 5s 01 4) 3 01 > p 01 rH 3 01 pP 41 0 p 4H p 0) rH Xl 41 01 3 01 01 0) P >H 3 X) P 41 p Oo Oa p 41 04 os in CO CO 05 CD 05 rH rH > XI o 41 z Cn \ E01 ca w o tn 23 s Ex] ^ > x> p o rH -"I 5s a CD E-" 2W xj Hc w H 9 01 p Q 01 0 U 41 4H u ] m 0 P Is p g Cl, <0 41 Pi 41 rs 3 | n c 40 H ~c <a CO .rH rH P! 4J H a 41 ct] o 41 C 3 a -4 ~4 X a P rtj 4) Cl u -4 > E j] T1 => H >1 U9 U3 W in *-y CO a Cn Cn o sz > >z 01 03 c rH 00 ap CO p 01 c 0 9s s' o 4>1 --1 41 P rH p 3 3 to a 01 o oH H ^H CD P o tn o o *-iH 11 g CM p CO 41 O p p CO u o Q 1 p H41 w 5*4 m tx] 6< H 4) c-- 3 rH CM w cm 000005871 ttf d H C* a a w a i M a <H t a a a a 03 a 0 4) 0) $a Q CJ 0 p 3 O .Gn n ue 3 W O 4) In V a u <0 c r4 0 43 P an os O 03 r-t r-t JO 43 o JO M 0. r"H i--t 0) H It S3 in no G 0x. a 4i +5 C 4) oc H c Po o tn H Lt -H fl) fH Q, a U 4) P to 33 4) <0 CO 5 *5 43 0 2C (3 co CT> JO 43 kt v o Q P ai l--l H 0 JO a o H --1 a u o o CO V 4) o a to X CJ5 X u V a 0 V 0 u V G P O z <> co 05 J=> 4J U, W Ct M CO P Xu >aj w C 4) ES-<) S.Q3 o o try a. 1 t3 i GU [ OO PH1II C/3 u p -t U3 P u pP 10 u a S3 0 P o p ci M CM u p Ci M *rNiHH C flj cd to PcoIl Gl HI 43 C 43 Ja CM 1 ou P 4) El -H a Ss C a 3> ot SI 45 0) 01 03 p 2a; Co_3 u p P --1 w a. ci >i P M HI 0 u <p 0| -1 it CP 0 Ct < uX cn CUN 00000587