On 7/15/76, preliminary ground rules were established for termination of op'eration for the Aroclor Department. On September 29, 1976 we reviewed and revised these ground rules. Minutes of the meetings are being circulated for comments. Substantial reduction in expenditures are possible by adopting the new ground rules. Summarizing: Department Decontamination Dismantling Reduce to Size Prepare, Ship & Landfill Totals 7/76 $ 600, 000 400,000 200, 000 300, 000 $1,500,000 9/76 $ 150, 000 (500,000 ( 300, 000 $ 950, 000 Tank Car Fleet Decontaminate 45 Cars Totals, Cars & Dept. $ 500,000 $2, 000, 000 $ 135,000 $1, 085, 000 Add; Remove, Replace, Bury Old Car Insula tion, if required Grand Total -$2,000, 000 215, 000 $1, 300, 000 These estimates are ball park numbers and should be within + 15% of the expected actual. STLCOPCB4076816