Document baQpoJ87roGNM92D14nbO1pOy
MANUFACTURING IMPROVEMENT PLAN FOR
PLANT INCINERATOR DEPARTMENT 790
PREPARED BY: BARBARA CARLISLE
APPROVED: J. PEDUZZI, PROD. SUPERVISOR
ISSUE DATE:
jT/77
j j ------ VA'/7>
W. A. KUHN, MANAGER OF PLANT SERVICES AND CAPITAL PLANNING DSW 185622
STLCOPCB4051771
-TABLE OP CONTENTS-
Page
OVERVIEW. . .............................................1
CAPACITY.......................................
2
COSTS..................................................................2
SAFETY........................................................ . 4
ENERGY..................................................................4
DSW 185623
STLCOPCB4051772
DISTRIBUTION
D. P. Alt F. J. Basile E. R. Billen J. W. Boehm K. E. Boucher P. Brewer R. E. Bunge B. K. Carlisle W. C. Engman R. W. Flint R. L. Harness H. J. Horner W. A. Kuhn - B3NH A. E. Ieisy
D. K. Lynch
D. Metherd
R. H. Munch - TIB
P. S. Neuhoff
C. P. Orr
- G2WD
C*______Raton------- -B2SfC
J. Peduzzi
R. A. Pohl
- B2SB
E. M. Potter - B2NK
J. Schriner
W. L. Smull
L. W. Sprandel
R. Sterghos
B. R. Williams
DS\N 185624
STLCOPCB4051773
MANUFACTURING IMPROVEMENT PLAN
PLANT INCINERATOR
DEPARTMENT 790
__________
Page 1 March 1977 WGK
OVERVIEW
The specific purpose of the plant incinerator, since its origin, has been to destroy Aroclors. Other plant wastes, such as ONA, PNA, Chlorophenols and Santophen I have also been incin erated to utilize excess capacity. MCB pilot plant wastes are scheduled to be incinerated in 1977 as well. Since a permanent shutdown of the Aroclor Department (Dept. 246) will occur late in 1977, eliminating internally generated Aroclor wastes, shutdown of the plant incinerator must be considered as a strong possibility.
The current waste inventory of 2 M pounds (a four-month supply) and the 3 M pounds of wastes to be generated during 1977 by Dept. 246 would allow the incinerator to operate near capacity through 1977.
An area-wide incinerator is scheduled for start-up in early 1980. It is to be capable of disposing of all known and projected incineratable Monsanto wastes in the St. Louis area. Presently, all WGK wastes, with the possible exception of Aroclors, could be incinerated outside the plant for less cost than at the plant unit. Operation and retention of this facility after 1977 appears to be economically undesirable, unless a viable specific need for high temperature incineration is identified. The position of the business group toward disposal of customer Aroclor wastes needs to be reconfirmed; the previous position has been that all customers will be referred to contract incinerators on the basis of lower cost to the customer and no liability to Monsanto. It might, however, be' desirable to retain the incinerator as a test unit for obtaining design data for the area-wide incinerator.
During 1977, a formal economic evaluation will be completed to determine the best course of action for incineration between now and when the new area-wide incinerator is brought on-stream. Until this decision is made, technical effort in the unit will be kept to an absolute minimum.
DSW 185625
STLCOPCB4051774
MANUFACTURING IMPROVEMENT PLAN PLANT INCINERATOR DEPARTMENT 790
Page 2 March 1977 WGK
A. CAPACITY
The incinerator is budgeted to dispose of 6m# of residue in 1977. While the incinerator standard capacity is 500.000 lbs/month, waste receipts are expected to total 550.000 lbs/month until 9/77 when they will drop to under 200.000 lbs/month, for a total of 5.1R pounds for the year.
The table that follows shows the amounts of the various wastes expected to be incinerated in 1977.
Dept.______Product
Projected Waste Incineration, M lbs.
219/222 ONA/PNA
.30
226/237 Chlorophenols
.72
239
Santophen I
.84
MCB Pilot Plant
.11
Aroclors Customer Returns
.47
246
Aroclors & Montars
2.64
5.08
B. COSTS
Budgeted incineration cost for 1977 is $.133/pound based on burning 6M pounds. The 1976 cost was $.106/pound.
DSW 185626
STLCOPCB4051775
MANUFACTURING IMPROVEMENT PLAN PLANT INCINERATOR DEPARTMENT 790
Page 3 March 1977 WGK
COSTS (cont*d)
The following table shows estimated 1976 and 1977 costs for contract incineration of plant wastes that could alternatively be incinerated in the plant.
Department1976 Cost.1977 Cost
Contract Incineration Cost
$/lb.
(includes freight)
237 248
221 247
238 229
Chlorophenols Santophen I ONA/PNA MCB Pilot Plant Metafractions MIBK Lab solvents S-160 Benzyl Chloride
.070 .071
--
--
.091 .173 .067
--
--
.07-.10 .07-.10 .07-.10 .07-.10 :i2i .106 .082 .071 .068
Of the possibilities for Aroclor waste replacement that have been considered thus far. Metafractions and MIBK are the most logical, although they still do not economically justify continued operation of the incinerator. The very low cost of contract incineration of Benzyl Chloride/S-160 makes it a less desirable alternative.
Rough estimates show that, omitting the costs of a NOx control system which would be necessary, costs of plant incineration would be as follows, based on 1977 costs and 5 M pounds incineration capacity: (416,000 lbs/mo.)
Total Dept. Cost
Out of Pocket Cost
Out of Pocket Cost
(including depreciation cost) (excluding depreciation cos
____
$63,600/mo. 15.3^/lb.
$46,200/mo. ll.l<r/lb.
$40,900/mo, 9.8C/lb.
Total outside incineration cost for the 5 M pounds considered
DSW 185627
STLCOPCB4051776
MANUFACTURING IMPROVEMENT PLAN PLANT INCINERATOR DEPARTMENT 790
Page 4 March 1977 WGK
COST (cont'd)
in the previous situation would be $46,600/mo. or 11.3C/lb.
lbs/mo.
Chlorophenols
60,000
Santophen I
70,000
ONA
25,000
MCB Pilot Plant
10,000
Metafractions/MIBK 251,000
Total
416,000
Outside incineration, estimated $/mo.
.10 .10 .10 .10 .12
6,000 7,000 2,500 1,000 30,100 46,600
It should be noted that the above numbers are preliminary and only indicate the need for a formal economic evaluation to determine the future of the existing incinerator.
C. SAFETY
The departmental Safety audit was begun late in the year, and is expected to be completed'during the second quarter of this year.
D. ENERGY
Due to the anticipated shutdown of the WGK incinerator anywhere betweer early 1978 and early 1980, the energy audit scheduled in 1976 was deferred indefinitely.
The incinerator is a relatively low energy consumer as indicated by the following table:
ITEM
INCINERATOR USAGE
TOTAL WGK USAGE
% OF TOTAL WGK USAGE
DSW 185628
Steam (MMBTU) Gas (MMBTU) Electric (CKWH)
Plant Water (M Gal) Purchased Water (M Gal)
970 568 833
4083 848
300030 21700 72300
790300 167094
.32 2.6 1.1
.5
.5
STLCOPCB4051777