Document Eq2p0KwZabEL6DkX4MLKq3qgj
1
VINYL WINTERIZATION AND OPERATIONS PROGRAM
% -
1983-1984
TABLE OF CONTENTS
Section Title
Page No.
I. Introduction
1
II. Safety Aspects Of Winter Operation
2
III. Common Pitfalls Of Winter Operation
A. Reactors B. Dryers
IV. WINTER ALERT Plan Activation
A. Criteria & ActivationResponsibility B. Action Steps C. Staffing D. Mechanical and Process EngineeringRole During WINTER ALERT
Conditions
9 9 12
13
V, Operator Checklists
A. Chief Operator B. Lead Operator - New Module C. Lead Operator - Old Module D. Lead Operator - Dryers E. "A" Operator - New Module F. "A" Operator - Old Module G. "A" Operator - Rotary Dryers
"A" Operator - Fluid Bed Dryer
18 24 27 30 31 35 39
VI. Steam And Electric Tracer Masterlist And Tagging Program
A. Steam Tracer List And Test Method B. Electric Tracer List And Test Method
41 49
VII. Personnel Policy During Winter Coverage
VAB.0001136658
A
I. INTRODUCTION
The winter of 1981--1982 proved to be one of the coldest the Aberdeen area has seen in years. The severe weather resulted in substantial lost production, excessive energy costs and significant freeze damage to Vinyl Area equipment. The winter painfully highlighted the Vinyl area's lack of preparedness for cold weather operation. Many wasted days and manpower was devoted to replacing freeze damaged equipment and thawing out of most of the balance, In reviewing the 1981 winter's performance the Vinyl Area was deficient in two primary areas:
Lack Of Adequate Freeze Protection For Vinyl Piping And Equipment. Many piping runs froze simply because they weren't insulated or were insulated to a poor standard. Critical instrumentation was rendered useless because leads were packed with an incorrect mixture of anti freeze. Many tracers simply weren't functional, etc. and
Lack Of Winter Operations Training For Vinyl Operations Personnel. Operations response to cold weather was more reactive rather than preventative. No winter operations training was conducted and it showed. Many tracers weren't activated because no one knew where they all were. Operator's daily routines were not structured towards cold weather operation, etc.
In efforts to avoid a repeat performance, an extensive winterization project was developed in the spring and this manual was written to document Aberdeen's winter operations plan. The whole thrust of our efforts will be directed towards preventing a unit freeze up rather than reacting to a freeze up after it occurs.
Our goals for this coming winter will be:
No operator injuries as a result of cold weather operation and
No major downtime as a result of cold weather operation.
The winter of 1982-83 showed significant improvement over the previous winter. The majority of vinyl piping and equipment was properly insulated. Winter operation training in the vinyl area helped to minimize equipment damage and downtime.
1
f
VAB.0001136659
A
II. Safety Aspects Of Winter Operation
Winter time "operation can pose safety hazards beyond normal operations and consequently requires additional care and precautions.
Icy Surfaces and Associated Slipping Hazards
Hot Steam Tracers
Increased Risk Of External Power Failure
Cold Weather Exposure Problems
Losing Instrument Control Due To Wet Instrument Air
Potential To Freeze And Break Process Lines And Or Equipment
Personnel Working In Unfamiliar Areas
All of the above pose potentially serious safety problems. Careful planning of work, additional supervisory staffing during WINTER ALERTS, enhanced operator awareness, and development of routine winter job responsibilities will be our route to safely coping with severe cold weather operating conditions. The attached program along with proper training is directed towards our goals of:
No Operator Injuries As A Result Of Cold Weather Operation And
No Major Downtime As A Result Of Cold Weather Operation
Icy Surfaces- Slippery surfaces should not only be recognized but special precautions should be taken such as:
Spreading Sand And Salt Or
Roping Off The Slippery Areas To Prevent Personnel Entry
Hot Tracers- In 1982 three 1st aid cases were incurred due to minor burns due to exposed steam tracers. While most of the tracing has been upgraded and insulated for personnel protection, we must keep our guard up. Our steam tracing runs well above 250 F and in cold weather can burn you before you even feel it. Further, if you are handling steam hoses youT11 need leather or other heavy gloves, cotton gloves do not provide adequate insulation for your hands. In 1983, there were no 1st aid cases due to tracer bums.
*
Power Failures - During ice or snow storms there is an increased risk of external power failure due to power lines getting "knocked down". This is especially important in the reactor areas and requires a heightened awareness of Emergency Systems, such as EMERGENCY AMS KILL SYSTEMS, EMER GENCY INSTRUMENT AIR SYSTEM, and the EMERGENCY COOLING WATER SYSTEM. Field Operator mobility may be impaired due to slippery surfaces, panel operators need to recognize this fact and be responsive for Emergency Panel Kills.
VAB.0001136660
A
Cold Weather Exposure- All operating personnel should prepare for the worst and come equipped to spend long hours in cold weather (including panel operators). Cold weather can be comfortable if we dress for the occasion* As a minimum I would recommend:
Hard Hat Liner
Thermal Underwear Or Insulated Coveralls
Warm Gloves
Ski Hat And
Water Proof Boots
The company has provided some of the above 9 the balance you should use your own judgment based on the job requirements.
DRESS FOR THE OCCASION AND YOUR OWN COMFORT.
INSTRUMENT LOSS-- The occassion may occur when you may lose instrument control due to ice formation in the process instrument air system. Some instrumentation may give faulty readings due to cold weather impairment. As a general practice you should assume the worst and act accordingly. FIELD-PANEL COMMUNICATION AND TEAMWORK CAN HANDLE THESE SITUATIONS AND RESTORE INSTRUMENT CONTROL. The main point is don't play the guessing game, operations and instrument support will be on hand to help correct problems.
ANTICIPATE PROBLEMS?
POTENTIAL TO FREEZE AND BREAK PROCESS LINES OR EQUIPMENT- While special precautions and procedures have been developed to prevent freeze damage to piping and equipment the smart operator will be aware it can happen and pre-think what he would do in various senarios if freeze damage did occur:
- How would freeze damage impact?
- Where can equipment be isolated?
- Safety Implications?
- Etc.
PERSONNEL WORKING IN UNFAMILIAR AREAS
During unusual winter conditions some personnel may be assigned to work in areas different and somewhat unfamiliar to their nornal assignment. In most cases they'll be working closely with experienced personnel but the key is:
IF YOU HAVE QUESTIONS ASK!
Experienced personnel should watch out for others working in their area as well as themselves.
3 VAB.0001136661
1
Flnallyi the above are typical safety problems which one might encounter during a severe cold weather operation. All the situations and senarios which could occur are beyond the scope and volume of this manual. A few words of guidance:
ANTICIPATE PROBLEMS EXPECT THE UNEXPECTED MURPHY'S LAW IS AGAINST US AND ANY WINTER CAN POTENTIALLY BE THE WORST ON RECORD
VAB.0001136662
il
III. Common Pitfalls Of Winter Operations
A. Reactor Areas
As we move into severe cold weather periods, it is well worth the time to review critical areas where freeze-ups can bottle neck plant opera tions. Three simple but important points to remember are:
Water Freezes At 32F VCM Freezes at -244F Water In VCM Will Freeze and Form a Slush at 32F
Since it rarely gets to -244F in Monroe County, it is safe to say we
can forget about pure VCM freezing. Water is the key culprit, and
anytime the temperature gets below 32 F our guard should be up.
Unfortunately, in a suspension PVC process, water is likely to be in
many places throughout the unit. Any major freeze ups have a high
potential to curtail operations, be the problem in the charge system,
reactor instrumentation, recovery system, cooling water, reactor
cleaning system, or EPA Systems. The PVC process in itself generates a
significant amount of heat to offset freezing complications, therefore,
the key is to keep the unit running. This involves every operator
closely monitoring his area of responsibility and quickly responding to
minor problems as they occur. successful winter operation.
The following are key elements to
DEVELOP A WEATHER AWARENESS AND KNOW THE WINTER ALERT PLAN
Recognition of upcoming cold weather and activating the winter opera tions steps before the cold weather moves in, is perhaps the most impor tant step to keep the unit on-line. In order to keep vinyl operations personnel informed on weather conditions, a 24 hourly weather scanner was installed in the Vinyl Shift Supervisor's Office. When cold weather is forecast, the Operations Superintendent or Operations Supervisor will activate the WINTER ALERT plan which is detailed in Section IV WINTER ALERT Plan Activation. The plan
Staffing Considerations Operator Responsibilities Operations Guidelines
Become familiar with the plan and your responsibilities.
THOROUGH AND TIMELY STEAM AND ELECTRIC TRACER ACTIVATION
It is cost prohibitive to operate our steam and electric tracers throughout the winter months (December, January, and February). It has been estimated that the steam tracing in the plant uses approxi mately 14,000 Ib/hr. of steam which is a cost of $95/hr. or $2,280/day. While we should not hesitate turning on the tracing in anticipation of extreme cold weather, we should not hesitate to turn off the tracing as weather permits. In the face of severe cold weather it is important to activate and check tracer operation before the cold weather strikes.
5
VAB.0001136663
THOROUGH AND TIKELY STEAM AND ELECTRIC TRACER ACTIVATION (Continued)
Inactive steam tracers will be first items to freeze DON'T LET THIS
HAPPEN. Operators in conjunction with engineers have spent a lot of
time and effort identifying and listing
supply valves correspon
ding steam traps and circuit locations for electric tracing. These
lists should be used in the TRACER ACTIVATION and problem tracers
repaired quickly.
PROTECT AGAINST WET INSTRUMENT AIR
In order to have reactor instrumentation and valves operate properly in below freezing conditions, it is extremely important to have dry instru ment air. The tell tale sign of wet instrument air are numerous valves sticking due to water condensing and ice forming in the solenoids or instrument air lines. The most important winter parameter in the instrument air system is air dryer performance which is indicated by the dew point. The dew point is just that, it is the temperature where water will condense (form dew) out of the instrument air. If it is below freezing when the water condenses, it will freeze and "block" air flow to instruments and valves. The dew point of the instrument air going to the reactor area is indicated by an LED readout and circular chart recorder located Inside the Deltech air dryer aluminum building southeast of No. 8 and No. 9 air compressors. It is normally the Utility Operators responsibility to monitor air dryer performance. During winter operation periods supervisory personnel and Chief Operators should keep a close track of dew point performance by record ing dew point readings. If the Instrument air system gets wet it will become necessary to blow out air lines at strategic points in order to purge the system of water. Bleeders on air surge drums in the units should be cracked open to allow any water in the system to bleed out.
BEWARE OF THE AIR!
KEEP THE RECOVERED MONOMER WARM
In order to prevent ice fromation in the VCM receivers and sub s equent
slush blockage of the VCM charge meters, it is important to keep the
recovered monomer warm. This is easily done by closing back on the
cooling water going to the RVCM condenser in the Recovery Areas. A
small amount of water should be maintained to all of the condensers to
prevent the coolinge water lines from freezing,. The Recovered Monomer
piping leaving the condensers should be warm to the touch, Heating
coils have also been installed on the bottom of all VCM
to
help add additional small amounts of heat.
MAINTAIN ADEQUATE WATER REMOVAL FROM THE RVCM RECEIVERS
Keeping the RVCM warm is half of the battle. If 50F RVCM at 15% per batch contacts 16F FVCM at 85% per batch the combined temperature will be about 21F. If there's water in the RVCM it will freeze form a slush and stop up the VCM charge turbine meters. It is critical to remove all water from the RVCM before prepumping or charging a batch. Make sure when you drain the RVCM receivers to the Batch Water Stripper or Blow down tank that all the water is drained and then drain extra. Watch for a pressure rise in the batch water stripper or blowdown tank. Take the time to do a complete drainage job.
r*
*4
i
- ..
j.s- I
U -
. -ik
ft
VAB.0001136664
A
KEEP THE CAT BOMB HPSW LINES FROM FREEZING
Although the HPSW lines to the cat. bombs are insulated, they are not traced and will freeze if water is not flowing slowly through the small piping. Following a charge or kill a small water flow should be main tained to the reactor sample port through the bomb. Reactors cannot be charged or killed if the water lines to the cat bomb freeze. DON * T LET THE CAT BOMB WATER FREEZE.
BEWARE OF FAULTY DELUGE SYSTEM TRIPS
For obvious reasons it is highly undeslreable to have faulty deluge system trips during severe cold weather. The deluge system will remain in operation during winter conditions for fire protection, but any signs of a system problems should be treated on the highest priority as instrument help will be on-hand. If necessary the system can be blocked in and a man assigned to stay with the cut-on valves.
AN APPROPRIATE DELUGE TRIP CAN SAVE PERSONNEL AND EQUIPMENT, A FAULTY DELUGE TRIP CAN TURN A REACTOR MODULE INTO A GLACIER IN COLD WEATHER.
KEEP THE NEW MODULE SEAL OIL SYSTEM WARM
In 1981 a total of 6 seals were lost on the 4 New Module reactors during a cold 3-day period, due to ice balls forming in the seal oil. Since that time steam coils have been installed in these seal oil tanks to keep the seal oil warm. The key is to keep the seal oil warm (not hot) to prevent ice formation. The old module has been equipped with elec tric traced and insulated seal oil lines. Seal oil temperatures will be recorded in order to monitor Duraseal operation.
DRAIN WATER FROM IDLE EQUIPMENT TO PREVENT FREEZE DAMAGE
Significant freeze damage occurred in the winter of 1981/1982 simply because idle equipment was not drained. In order to prevent freeze damage, equipment should be kept recirculating or drained as a general practice. Idle equipment in VCM service should be recovered, blanked and drained if necessary.
Items include spare cherawash pumps, spare service water pumps, etc.
CLOSELY MONITOR COOLING TOWER OPERATIONS
While the PVC process can generate significant amounts of heat, the cooling towers can remove even more if not properly operated. Since last winter automatic cooling tower fan controls have been installed on all the Vinyl Towers to control the cooling water at 55 F. This will help prevent ice formation on the towers which can seriously damage the cooling towers.
It may be further necessary to take banks off-line or cut off a recir culation pump in order to keep the cooling water about 55 F.
VAB.0001136665
A
The dryer areas are not quite as susceptible to freeze problems as the reactors, but do require special winter attention, as bottle necks in the dryer can be just as devastating as bottlenecks in the reactor areas. DON*T LET SLURRY RECIRCULATION LINES FREEZE Slurry lines not recirculating are to be flushed with water to be followed by draining and blowing out the lines with air.
FROZEN SLURRY RECIRCULATION LINES ARE UNACCEPTABLE! DRAIN IDLE EQUIPMENT & PIPING TO PREVENT FREEZE DAMAGE PVC slurry like water will freeze at 32 F. The two constituents in the reactor and dryer area are slurry and water. Both can freeze, both can halt production. Every operating personnel on-shift has an important job to do. Team-work and good communications will be key in a successful winter operation.
VAB.0001136666
A
IV. WINTER ALERT PLAN ACTIVATION
A. Criteria And Activation Responsibility
In order to maintain Vinyl Operations and protect Vinyl Area Equipment from freeze damage it will be necessary to closely monitor upcoming weather conditions and activate winter operations plans before the severe weather hits the area. In the event of forecasted subfreezing conditions for an extended period of time, it will become necessary for the Vinyl Operations Superintendent or the Vinyl Operations Supervisor to declare a Vinyl WINTER ALERT with immediate implementation of the associated action
The Vinyl Operations Superintendent and Vinyl Operations Supervisor will be responsible for monitoring upcoming weather conditions on a daily basis. A 24 hour/day weather scanner has also been installed in the Vinyl Shift Supervisor's office to keep Vinyl personnel appraised of upcoming weather conditions.
Typical criteria to warrant a WINTER ALERT would include any of the following:
Forecasted snow, sleet, freezing rain, or ice storm.
Forecasted temperatures to be below 32 F for 24 hours conse cutively
Forecasted temperatures to be below 20 F for any period of time.
The key to the WINTER ALERT Program is to be prepared and ready before the cold weather strikes rather than attempting to thaw the unit follow ing a freeze-up. In order to accomplish this we must depend on fore casted weather conditions and there will likely be some "false alarms" as the weather service forecasts are not near 100% accuracy.
"AN OCCASIONAL FALSE ALERT IS ACCEPTABLE. A UNIT FREEZE-UP BECAUSE WE FAILED TO DECLARE A WINTER ALERT IN THE FACE OF SEVERE WEATHER IS UNACCEPTABLE"
B. WINTER ALERT ACTION STEPS
When a WINTER ALERT is declared the following 12 action steps will be taken:
1. Activation of all electric tracing per master list by Chief Operator. (Refer To Section VII Steam And Electric Tracer Master List.)
2. Activation of all steam tracing per master lists by reactor "A" operators.
3. Winter Protection Checklists will be activated and completed by each operator on a shift basis. (Refer To Section V. Winter Protection Check Lists).
9 VAB.0001136667
A
B. WINTER ALERT ACTION STEPS (Continued)
4. Notification of Off-Shift Vinyl Operating personnel scheduled for the upcoming shift of the WINTER ALERT and determination if attendance is a problem. (Refer To Section VI Vinyl Depart ment Personnel which will list employees by shift, their tele phone number and town of residence.) This will be done by the Vinyl Operation Supervisor.
5. Since every operator will have an assignment, it will be necessary to operate with full staffing during the WINTER ALERT as follows:
1- Chief Operator 3- Lead Operators 2- "A" Operators - Reactors 2- "A" Operators - Dryers
If the operating shifts are not staffed to full-strength, coverage should be arranged by the Shift Supervisor for his shift and the upcoming shift.
6. The Vinyl Operations Superintendent will notify the Mecha nical Superintendent, Plant Superintendent, Chief Process Engineer, and Director of Administrative Services as support from these area will likely be required.
7. The Mechanical Superintendent will arrange for a 24 hour/day maintenance support team to include:
1- Instrument Technician 2- "A" Mechanics
The maintenance support team will remain in force until the WINTER ALERT is over as determined by the Mechanical Superin tendent in conduction with the Vinyl Operations Superintendent.
8. The Vinyl Operations Superintendent will arrange for additional operating supervision during Winter Alerts as follows:
Day Shift
7 a.m. - 7 p.m. Vinyl Operations Superintendent-Dave Hollis/Joe Ware Vinyl Operations Supervisor - Chris Turner
Night Shift 7 p.m. - 7 a.m. An Additional Vinyl Shift Supervisor Vinyl Operations Engineer - Mike Nathan
VAB.0001136668
A
B. WINTER ALERT ACTION STEPS (Continued)
These personnel will be responsible for overseeing ALERT PROGRAM on shift and in the field. They wil] Trouble Shooting assistance as required. The add: supervision will remain in force until the WINTER declared over by the Vinyl Operations Superintend* Operations Supervisor.
9. Depending on the severity of the WINTER ALERT and road
conditions, the Vinyl Operations Superintendent wi
------
the Director of Administrative services to arrange
dations for off-shift personnel at the Shelaine Cc
Restaurant.
10. The Director of Administrative Services will place a purchasing
_____ -
department representative on ,,stand-by"in the evei
purchases are required.
\
11. On-shift personnel will keep appraised of upcoming weather conditions by the Weather Alert radio scanner which is installed in the Vinyl Shift Supervisor's office.
12. A separate Winter Log Book for WINTER ALERT periods will be kept in the Vinyl Shift Supervisor's office and record weather related problems experienced on-shift. These may include freeze damage, line freeze-up, etc. This will be especially beneficial to document winter problems and help assist future winter protection efforts. All problems, however minor, should be written down to prevent them from happening again.
13. All reactors will be placed on 5385 production when a WINTER ALERT is declared. There are several reasons for this:
a. High calcium stearate level should enhance dryer rates.
b. Gels and associated filter changes will take a second priority.
c. Reactors will be chem washed each batch which is not condusive to optimal wire and cable properties.
d. There will be a minimum of dump line-ups switching which takes up valuable operator time.
There will be a minimum of dryer cleaning which takes up valuable operator time and could potentially slow up the reactor areas.
14. WINTER ALERT follow-up - A WINTER ALERT HIT LIST will be written up outlining actions steps and responsibility for corrective measures. The list should help alleviate problem areas prior to the next cold weather spell. This list will be compiled from information written in the winter Log Book. Be sure to use the book.
11 VAB.0001136669
A
C. WINTER ALERT STAFFING
In the event of a WINTER ALERT condition the following staffing will be instituted:
DAYS 7 a.m. - 7 p.m. \ Vinyl Operations Superintendent - Dave Hollis/Joe Ware Shift Supervisor Lead Operator - New Reactor Module
i
Lead Operator - Old Reactor Module / Lead Operator - Dryers ( "A" Operator - New Reactor Module
"A" Operator - Old Reactor Module uA,f Operator - Rotary Dryers "A" Operator - Fluid Bed Dryer \ 5 2- "A" Mechanics 1- Instrument Technician "A" 1- Purchasing Agent (Stand-By)
1 1
\ NIGHTS 7 p.m. - 7 a.m. Xt. x-- Vinyl Operations Supervisor - C. W. Turner 2 Shift Supervisors Vinyl Operations Engineer - M. L. Nathan Chief Operator Lead Operator - New Reactor Module Lead Operator - Old Reactor Module "A" Operator - New Reactor Module "A'1 Operator - Old Reactor Module "A" Operator - Rotary Dryers MA" Operator - Fluid Bed Dryer
2- "A" Mechanics 1- Instrument Technician "A" 1- Purchasing Agent (Stand-By)
f
-+H-r ' r P-'X
I *[P-
1..................
.................... b~. ' -Itk--
-L T-
-
I|
-
.1 -'ll '
! . 1 ?H." | M
l,i
, -
-i-
-JT-lTiif
h- i- |-
V I-
VAB.0001136670
IV
C. VINYL DEPARTMENT PERSONNEL AND SUPPORT AREA INFORMATION
Name *Joe Ware *Dave Hollis *Chris Turner *Mike Nathan *Rodger Collins
Tommy Cummings
A"It A It Shift
Position
Telephone No.
Plant Superintendent
1-327-5018
Opera. Superintendent
369-6422
Opera. Supervisor
369-7381
Vinyl Operations Engineer 369-8613
Shift Supervisor
369-6184
Production Scheduler
369-6058
Town of Residence Columbus Aberdeen Aberdeen Aberdeen Aberdeen Westfield
**Bobby Hawkins Doug Spann Jerry Eastman Jimmy Tate A. C. Pettus Bob Newman Lander Keaton Nathaniel Wilson Reubin Gates Verneeta Blanchard
Shift Supervisor Chief Operator Lead Operator Lead Operator Lead Operator "A" Operator - Reactors "A" Operator - Reactors "A" Operator - Dryers "A" Operator - Dryers Utility
343-8832
Hamilton
1-205-698-8562
Crews, AL
1-205-698-9494
Sulligent, AL
256-7455
Aberdeen
369-6636
Aberdeen
369-4030
Aberdeen
343-5301
Hamilton
369-4354
Aberdeen
343-5426/369-6566 Aberdeen
369-6855 (Brother) Aberdeen
"B" Shift
**Don Johnson Bud Stone Harold Sanders 0. C. Pace Reggie Jones Jeff Shields Fred Davis Huston Smith Charles Kinsey Ernestine Carter
Shift Supervisor Chief Operator Lead Operator Lead Operator Lead Operator "A" Operator - Reactors "A" Operator - Reactors "A" Operator - Dryers "A" Operator - Dryers Utility
256-8279 1-205-698-9324 256-5562 256-2830 No Phone 256-4820 369-7779 369-6549 369-7926 369-7193
Splunge Sulligent, AL Becker Becker Aberdeen Amory Aberdeen Aberdeen Hatley Aberdeen
MC" Shift
**Ray McGee Steve Kilgore David Sprowell Bill King Walter West Lee Childers Charles Morris Charlie Polk Brooks Cowley Gary Funderburk
Shift Supervisor Chief Operator Lead Operator Lead Operator Lead Operator "A" Operator - Reactors "A" Operator - Reactors "A" Operator - Dryers "A" Operator - Dryers Utility
369-6674 1-205-698-8497 343-5100 256-7086 369-8236 256-8670 343-8849 369-2891 256-7277 369-4021
Aberdeen Sulligent, AL Hamilton Greenwood Springs Greenwood Springs Wren Hamilton Aberdeen Amory Gattman
VAB.0001136671
Page 2
A
Name
Position
Telephone No
Town of Residence
i "D" Shift
**Alton Reeves --
Shift Supervisor
369-6919
Sam Stokes
Chief Operator
1-447-3489
R. C. Towery
Lead Operator
1-651-4087
J. D. Sims
Lead Operator
1-651-4455
Bob Morgan
Lead Operator
369-9464
Willie Jackson
"AM Operator - Reactors 369-6338
Darnell Perry
"A" Operator - Reactors 369-2092
Freddie Franks
"A" Operator - Dryers
369-7723
Cleveland Brown
"A" Operator - Dryers 1-494-5474
D. W. Clark
Utility
Willie Malone
General Helper
David Covington
General Helper
Hamilton Okolona Smithville Greenwook Springs Aberdeen Aberdeen Okolona Aberdeen West Point
Yard Department *Dean Honeycutt
Tom Bales Milton Threadgill Roy Ray Jimmy Brewer Needham Stahl Horace Lindsey Bernard Garth
Yard Supervisor Yard Operator Yard Operator (A Shift) Yard Operator (B Shift) Yard Operator (C Shift) General Helper Yard Operator Yard Operator
343-5595
369-6734 343-8419 369-2155
Hamilton Aberdeen Greenwood Springs Hamilton Greenwood Springs
KEY SUPPORT PERSONNEL
Maintenance & Mechanical Engineering
*Rick Snowden
Mechanical Superintendent 1-327-7382
Jerry Horstman
Maintenance Superintendent 369-6005
G. Morgan/C. Davis Maintenance Supervisor, I&E 369-8780
Randy Polk
Sr. Mechanical Engineer 1 327 6766
Gil Morgan
Contract Supervisor
369 6522
*Dan Miller
Maintenance Engineer
1-356-6274
Columbus Aberdeen Aberdeen Aberdeen Aberdeen Columbus
Process Engineering Dick Frohreich Veldon Messick Vernon Thornhill
Chief Process Engineer Senior Process Engineer Senior Process Engineer
1-328-3628 327-0741 369-8952
Columbus Columbus Aberdeen
Administrative Services
*Joe Higginbotham
Dir. of Adminis
Joan Pope
Buyer
1-327-0827 Unlisted
Columbus Aberdeen
Note: * 1st Notification Call List By Operations Superintendent To Advise A WINTER ALERT Is In Effect.
** 1st Notification Call List By Operations Supervisor To Advise A WINTER ALERT Is In Effect.
Aberdeen Temperature Columbus Air Force Base Weather Aberdeen Area Temperature
369-6471 1-434-7798
256-8512
i. -i.
| ^ . .1 J....
H.
nT
VAB.0001136672
A
i
D. MECHANICAL AND PROCESS ENGINEERING ROLE DURING WINTER ALERT CONDITIONS
Mechanical or Process Engineering personnel will be assigned on-shift coverage to provide technical and supervisory support during severe winter conditions when necessary. These individuals will work closely with the Vinyl Opera tions Supervisor on days and the Vinyl Operations Engineer on the night shift. The selected individuals are extremely knowledgeable on 1983 Winterization/Energy programs and have demonstrated good trouble shooting abilities.
Some of their key contributions are envisioned to be:
1. Conducting area tours especially concentrating on critical operating areas where problems could impact on continued Vinyl Operations, specifically monitoring the following:
a. Survey overall panel operations for unusual conditions.
b. Survey cooling tower operation (temperatures, optimum bank on-line, optimum pumps on-line, any freeze problems, etc.)
c. Survey charge system status, (VCM temperature, water temperature control, methocel charge system status, any problems with water injection to initiator bombs.)
d. Keep an eye out for potential freeze impact on idle equipment.
e. Survey Recovery System Operation (RVCM temperature, seal flow's, general operating status.)
f. Survey status of Dryer Recirculation loops, (which loops are active, idle loops flushed and drained, etc.)
g. Survey reactor agitator seal systems, (seal oil temperatures, seal flows, system pressure, etc.)
h. Survey steam and electric tracing on a spot basis.
g. Survey EPA Systems and Operation (Incinerator, batch water strippers, blow down tank.)
2. Keep appraised of upcoming weather conditions.
Be alert and responsive to winter or any safety problems you may see in the operating areas.
~u --
l'
i . r 't M v-.-v -
r i i q-y
f .|v
VAB.0001136673
D. MECHANICAL AND PROCESS ENGINEERING ROLE DURING WINTER ALERT CONDITIONS 4. Work closely with Operators and Supervisors as trouble spots arise. Keep an open ear and an open mind. 5. If numerous problems do occur it may be necessary to go to "zone" supervision mode and the engineer will be asked to supervise activities in a certain area be they opera tions or maintenance coordination. 6. Participate in shift change and various coordination meetings. 7. Assist in documenting winter problems in the Winter Log Book and aid in developing both short and long term solutions. 8. Prepare work orders regarding trouble areas. 9. Become familiar with quality aspects of PVC resin production.
These individuals are key in the respect they are "Rovers", trouble shooters, and can provide supervisory support.
VAB.0001136674
V. OPERATOR CHECKLISTS Following are the winterization checklists for Vinyl operations per sonnel listed below: A. Chief Operator B. Lead Operator - New Module C. Lead Operator - Old Module D. Lead Operator - Dryers E. "A" Operator - New Module F. "A" Operator - Old Module G. "AM Operator - Rotary and Fluid Bed Dryers These lists should be considered in addition to the normal daily check lists for each operating personnel position. The list touches on the major items but one should use his/her own judgment on other items known to be problems during freezing conditions.
VAB.0001136675
WINTER PROTECTION
Name
-* CHECK LIST
CHIEF OPERATOR
Date
Objective:
You are responsible for: monitoring and preventing key support equipment from freezing; providing guidance to Vinyl Operators; and assisting as a troubleshooter as required. Particular emphasis should be placed on:
Cooling Tower Operation
Dryer Recirculation Lines
Incinerator Operation (On-Line and Spare)
Instrument Air Dryer Performance
Deluge System Problems
Batch Water Strippers
As a Chief Operator your broad experience will be invaluable to work in concert with the Shift Supervisor to provide appropriate guidance to both field and panel operators. Our goal is to keep the unit on-line in a safe, efficient, and environmentally sound manner.
1. Any cold weather presents hazardous slipping problems, watch your footing. Put down salt or sand in bad areas. Rope area off if necessary. There's also alot of exposed steam tracing which caused 3 first aid cases in the winter of 1981, watch out! Less experienced operators, utilities or general helpers may be assigned to you and your area. Consider yourself their "big brother". Watch out for them as well as yourself and give them any pointers you can.
2. Steam and electric tracer operation is critical in winter operation. At the beginning of each shift you should check all steam and electric tracers to ensure all is operational. On the front end of a WINTER ALERT this will be your most impor tant responsibility.
Electric tracing checks will consist of two items. First, field checking each electric tracer breaker to ensure it's on. Second, field checking any current lights to tracers in the field. A list of Electric Tracers, Breaker Nos. and Location, and current light location has been included in SECTION VI B. All electric tracing breakers have been relocated to separate breaker boxes.
___ _________ Checked once per shift.
VAB.0001136676
A
Steam tracing checks will consist of checking the steam tracer supply valve and the corresponding trap and checking that the tracer is active and hot. A list of tracers, their location, and brass tag identification number has been included in SECTION VI A. Steam Tracer List.
Checked once per shift.
3. WET INSTRUMENT AIR CAN QUICKLY SHUTDOWN THE PLANT. The instrument air dryer is normally monitored by the utility opertor but as added insurance, the Chief Operator will check and record the dewpoint four times per shift from the LED Readout and also note the highest dewpoint recorded on the circular chart. Remember the dew point will indicate the temperature at which water will condense out of the instrument air and subsequently freeze. The dewpoint should run less than -30 F. The dewpoint LED readout and recorder are located in the Deltech air dryer metal shed, southeast of number 8 and 9 air compressors.
F 1st Check _______________________________________ F 3rd Check
F 2nd Check _______________________________________ F 4th Check
F Highest temperature on recorder
4. COLD RVCM CAN CAUSE WATER IN THE RVCM TO FREEZE. Twice per shift the exit temperature on the RVCM condensers should be checked by hand, it should be warm, not hot to the touch. If it's cold the cooling water to the condenser should be pinched back (but not completely closed to prevent the cooling water line from freezing).
Time:
OldModule 1st check
Time:
OldModule 2nd Check
Time:
NewModule 1st Check
Time:
NewModule 2nd Check
5. Cooling tower operation requires special attention in the winter periods to prevent tower damage and erratic reactor operation. Cooling tower fan controls were installed on all vinyl towers to control the water at 55 0 F. There may be situations where addi
tional steps may be required to maintain the 55 F cooling water temperature such as shutting off the two expansion towers, but keeping a small flow going to the by-pass lines to keep return header from freezing. All vinyl towers are to be checked 3 times per shift. The checks will consist of reviewing stable performance as indicated by panel temperature readouts and physically inspect ing each tower for icing.
19
VAB.0001136677
A
Review Panel Temperature Control D-500, D-600, D-700 Towers (3 Times/Shift)
Review Panel Temperature Control New Unit Towers (3 Times/Shift)
Field Check For Icing D-300 & D-400 Towers (3 Times/Shift)
+
Field Check For Icing D-500, D-600, D-700 Tower (3 Times/Shift)
Field Check For Icing
New Unit Towers
(3 Times/Shift)
As any problems arise you should maintain close contact with Panel Operators.
.6 Survey areas for stagnant water lines which might break. Open water bleeders as necessary, preferably route water to sewer with hose to prevent creating icy surfaces. Areas to watch for are utility stations, safety shower/eyewash stations, mechanical seal flush lines to idle pumps, water make-up lines to new and old module recovery syste flush lines to recovery system equipment.
New Module Old Module
VAB.0001136678
7. Maintain close contact with panel operator regarding RVCM receivers draining. Any draining problems on the RVCM receivers deserves immediate attention. Xt is essential that water be removed from RVCM and the BDT and BWS maintained at a temperature where a clear indication of drainage will be obvious. Review this with each reactor module panel operator. They are to contact you immediately should a drainage problem arise.___________________
8. Check each and every dryer area slurry reciculation line with the responsible Dryer "A" Operator. Lines not recirculating are to be flushed with water and blown empty with air once per shift.
- V-10 Recirculation from 501 blend tank
- Pond Resin Recirculation from 550 series blend tank
- V-ll Recirculation from 501 blend
- V-ll Recirculation from 407
- V-10 Recirculation fro 502, 747 Blend Tanks
- V-ll Recirculation From 502, 747 Blend Tanks
- Fluid Bed Recirculation From 502, 747 Blend Tanks.
- Drain Line From Fluid Bed Scrubber to 654 Blend Tank.
9. Assist In Permitting Maintenance Work.
10. Whenever the ambient temperature drops below 20F, the AMS Kill System for each reactor is to be checked on a once per shift basis. The checkout will consist of a small AMS injection into the reactor by cycling the automatic AMS valves. The system is to be checked for proper valve operation and positive indication of AMS addition. The Lead Operator for the module, the reactor module "A" Operator, and the Chief Operator will be responsible for the checkouts with the Lead Operator coordinating timing for each reactor. The check out is to be done after dump is complete and before rinse to sewer. Responsibilities will be as follows: 1) Lead Operator - will be responsible for cycling the automatic valves using the manual addi tion button and checking lights on close panel indication, 2) Chief Operator - will be responsible for checking the automatic valve operation in the field, and 3) Reactor "A" Operator - will be responsible for checking AMS pot for positive outage indication by measuring level before and after the AMS addition.
if -
- i h.'
It
p ..
r---rl
' ,. n---{fa j .
-i : I
fl
t
VAB.0001136679
A
OLD MODULE AMS AUTOMATIC VALVE OPERATION
300
400
500
600
700
NEW MODULE AMS AUTOMATIC VALVE OPERATION
741
__________________ 742
743
744
745
11. The following items are to be checked on both incinerators in addi tion to normal checks on a once per shift basis:
East West
_____
_____
Check safety shower for water flow by turning on eyewash station for a few seconds. (Safety shower is electric traced and insulated and should not freeze.)
_____
Check steam trap for proper operation.
_____
Check and record readings for water flow to scrubber.
_____
Check and record readings for total water flow to incinerator.
12. Just prior to the end of shift collect each operator1s check sheets and review with Supervisor.
CHIEF OPERATOR CHECK SHEETS
LEAD OPERATOR - NEW MODULE
_________ ___________ LEAD OPERATOR - OLD MODULE 22
VAB.0001136680
i
+
VV-..I-. j .. J(f . --.: - / - -.|t' = H ?v. -. -rp.'i----r **( . HI -Hr-
h r- y . -1: ;-v -
^ PA-..............hi it1 Wf Ipp .v :- -qpi-ii it
:i-p *. h^i.^ot - *-.-: f-t - -^fi-; . .i.
-f
t
LEAD OPERATOR - DRYERS "A" OPERATOR - OLD MODULE "A" OPERATOR - NEW MODULE "A" OPERATOR - ROTARY DRYERS "A" OPERATOR - FLUID BED DRYER This list should be considered in addition to the normal daily checklist, The list touches on the major items but you should use your judgment on other items you know to be problems during the freeze conditions. If you have any questions regarding this check list you should contact your Supervisor.
i
VAB.0001136681
Name
Date
WINTER PROTECTION CHECK LIST
LEAD OPERATOR - NEW MODULE
Objective:
You are responsible for closely monitoring the new module and the incinerator panel operation to insure problems are detected and responded to quickly to keep the equipment on-line.
1. When the unit is on WINTER ALERT all reactors are to be charged with 5385 until the WINTER ALERT is passed.
2. Reactors are to be chem washed after each and every batch to keep the chem wash system hot and on-line._____
3. It's extremely important to keep the recovery system running at all times and warm during winter alerts. If Its going to be a while between recoveries (more than 1 hour) strip the new unit blowdown tank. This will keep heat going into the system and prevent a recovery system freeze-up.
4. Drain both RVCM receivers to blow down tank frequently to prevent water accumulation and associated line freeze-ups. It is very important to keep water from contacting cold VCM as a slush will form, stopping the turbine meters.
5. Do not prepump any RVCM into the fresh VCM receiver.
6. If charging gets bogged down it is adviseable to hold one reactor down for repeat false charges and recovery to keep lines from freezing and systems hot. The false charge should consist of: 100 CTS H20 100 CTS RVCM 50 Gallons Methocel
Consult supervisor before doing this.
7. Keep supervisor advised of operating problems with the following critical instrumentation:
REACTOR PRESSURE TRANSMITTER COOLING WATER FLOW TRANSMITTER
741
742
743 744
745
ij
r- 'I
p'L ' - p
t - i1
''c
i' >
"ii
'f
t
L--rL|-Lt'--
.. -1..
|-H I.M
,f*r.
t ' J '
t
VAB.0001136682
7. (Continued) as well as the following instrumentation:
K. 0. tank pressure control
FVCM receiver level
East RVCM receiver level___________________________
West RVCM receiver level
BDT pressure transmitter___
Incinerator flow transmitter
RVCM receiver pressure transmitters
8. Monitor the RVCM receiver temperature on panel indication every hour. Notify supervisor if it drops below 32 F.
(A.M. and P.M.) 7:00 8:00 9:00 10:00 11:00 12:00 1:00 2:00 3:00 4:00 5:00 6:00
Temp. F
9. Monitor the tower cooling water temperatures each hour. The fan controls are set to maintain a 55 F cooling water temperature.
(A.M. and P.M.) 7:00 8:00 9:00 10:00 11:00 12:00 1:00 2:00 3:00 4:00 5:00 6:00
Temp. 0 F
_____
Notify the shift supervisor if the cooling water temperature drops below 50 F.
10 Beware if your VCM
counting slowly or start drifting far
apart. Slush may be forming in the RVCM
. VCM may actually
be going through much faster than meters are reading and thereTs a
chance of overfilling the
Stop the charge and notify super-
visor immediately.__
11 Donft take chances on valves without indications. Get field operator to verify position and notify supervisor for repair. We111 have instrumentation personnel on shift.________________________
12 Whenever the ambient temperature drops below 20' F, the AMS Kill System
for each reactor is to be checked on a once per shift basis. The
checkout will consist of a small AMS injection into the
by
cycling the automatic AMS valves. The syvstem is to be checked for
proper valve operation and positive indication of AMS addition. The
Lead Operator for the module, the reactor module "A" Operator, and the
Chief Operator will be responsible for the checkouts with the Lead
Operator coordinating timing for each reactor, The checkout is to be
done after dump is complete and before rinse to sewer, Responsibili-
ties will be as follows: 1) Lead Operator - will be responsible for
cycling the automatic valves using the manual addition button and
checking lights on panel for open and close indication, 2) Chief
Operator - will be responsible for checking the automatic valve opera
tion in the field, and 3) Reactor "A11 Operator - will be responsible
for checking AMS pot for positive outage Indication by measuring level
before and after AMS addition.
25
VAB.0001136683
s
r at.
Close Light
741
742
743
744
745
13. We had some failures of the Emergency AMS Kill System which dumped large quantities of AMS Into various reactors. Keep a close eye on peculiar reactors that have no call for cooling water.. Notify super visor and have the field operator check the AMS pot on that reactor. DO NOT RECOVER until advised by the supervisor to do so.
WE DO NOT WANT TO CONTAMINATE THE UNITS RVCM WITH HIGH AMS LEVELS. THE REACTOR WILL BE HELD DOWN IF THIS HAPPENS.
This list should be considered in addition to the normal daily check list. The list touches on the major items but you should use your judgment on other items you know to be problems during freeze condi tions. If you have any questions regarding this check list you should contact your supervisor.
l f.
I : f'l '
-e-
'i '
fl f-
f
^ iff. m r . -3 '
-I
VAB.0001136684
Name
Date WINTER PROTECTION
CHECKLIST LEAD OPERATOR - OLD MODULE
Objective:
You are responsible for monitoring the old module, the Batch Water stripper, and the Emission Recovery System to ensure problems are detected and responded to quickly to keep the equipment on-line.
I. When the unit is on WINTER ALERT all reactors are to be charged with 5385 until the WINTER ALERT is passed.______
2. Reactors are to be chem washed after each and every batch to keep the chem wash system hot and on-line.
3. ItTs extremely important to keep the recovery system running at all times and warm during WINTER ALERTS. If it is going to be a while between recoveries (more than 1 hour) strip the Batch Water Strippers using the main recovery system. This will keep heat going into the system and prevent a recovery system freeze-up.
4. Drain both RVCM to Batch Water Strippers frequently to prevent water accumulation and associated line freeze ups. It is very important to keep water from contacting cold VCM as a slush will form, stopping the turbine meters.
5. If charging gets bogged down it is advisable to hold one reactor down for repeat false charges and recovery to keep lines from freezing and keep systems hot. The false charge should consist of:
100 CTS H0 100 CTS FvCM
50 Gallons Methocel Consult Supervisor before doing this.
6. Keep Supervisor advised of operating problems with the following critical instrumentation:
An instrument technician will be on shift to make any repairs.
Reactor Pressure Transmitter
Cooling Water Flow Trans.
D-300
D-400
D-500
D-600
D-700
VAB.0001136685
WINTER PROTECTION CHECKLIST
LEAD OPERATOR - OLD MODULE
6. (Continued) As well as the following critical instrumentation: Steam Pressure: FVCM Receiver Level N. RVCM Receiver Level S. RVCM Receiver Level RVCM Receiver Pressures 701 ERS Pressure N. BatchWater Stripper Pressure_______________ S. BatchWater Stripper Pressure_______________ N. BatchWater Stripper Level___________________ S. BatchWater Stripper Level___________________ K. 0. Tank Pressure Controller
7. Monitor the cooling water temperatures on D-500/D-600 cooling tower. (A.M. & P.M.) 7:00 8:00 9:00 10:00 11:00 12:00 1:00 2:00 3:00 4:00 5:00 6:00 Temp. F___________________________ _________ ______ _____ _____ __________________________
Notify the Shift Supervisor immediately if the cooling water temperature drops below 50 F. The tower is equipped with an automatic fan control to control water at 55 F. 8. Beware if your VCM meters start counting slowly or start drifting far apart. Slush may be forming in the RVCM receiver. VCM may be going through much faster than meters are actually reading and there is a chance of over filling the reactor. Stop the charge and notify supervisor. 9. Don't take chances on valves without position indications. Get field operator to verify position and notify Supervisor for repairs. We'll have instrumentation personnel on shift.
VAB.0001136686
I I- WINTER PROTECTION CHECKLIST
LEAD OPERATOR - OLD MODULE
10. Whenever the ambient temperture drops below 20F, the AMS Kill System for each reactor is to be checked on a once per shift basis. The checkout will consist of a small AMS injection into the reactor by cycling the automatic AMS valves. The system is to be checked for proper valve operation and posi tive indication of AMS addition. The Lead Operator for the module, the reac tor module "A" Operator, and the Chief Operator will be responsible for the checkouts with the Lead Operator coordinating timing for each reactor. The checkout is to be done after dump is complete and before rinse to sewer. Responsibilities will be as follows: 1) Lead Operator - will be responsible for cycling the automatic valves using the manual addition button and check ing lights on panel for open and close indication, 2) Chief Operator - will be responsible for checking the automatic valve operation in the field, and 3) Reactor "A" Operator - will be responsible for checking AMS pot for posi tive outage indication by measuring level before and after AMS addition.
Time
Open Light
Close Light
300
400
500
600
700
11. We had some failures of the Emergency AMS Kill System which dumped large quantities of AMS into various reactors. Keep a close eye on peculiar reactors that have no call for cooling water. Notify Supervisor and have the field operator check the AMS pot on that reactor. DO NOT RECOVER THE REACTOR until advised by the Supervisor to do so.
WE DO NOT WANT TO CONTAMINATE THE UNITS RVCM WITH HIGH AMS LEVELS. THE REACTOR WILL BE HELD DOWN IF THIS HAPPENS.
This list should be considered in addition to the normal daily checklist. The list touches on the major items but you should use your judgment on other items you know to be problems during freeze conditions.
If you have any questions regarding this checklist you should contact your Supervisor.
29
i I
I
r- i
VAB.0001136687
IM
WINTER PROTECTION CHECKLIST
LEAD OPERATOR - DRYERS
Name Date
Objective:
You are responsible for monitoring the rotary and fluid bed dryers to ensure problems are detected and responded to quickly to keep the equipment on-line.
1. Keep Supervisor advised of operating problems with the following critical instrumentation.
An instrument technician will be on shift to make anv repairs.
Kotary Dryers Torque Controller Inlet Temperature Transmitter Outlet Temperature
2
3
4
5
6
7
8
Fluid Bed Dryer
Backmix Resin Temperature Indicator/Controller (TIC-503) Backmix Inlet Air Temperature Indicator/Controller (TIC-507) Resin Discharge Temperature Indicator/Controller (TIC-506) Plugflow Inlet Air Temperature Indicator/Controller (TIC-508) Hot Water Coil Temperature Indicator/Controller (TIC-505) South Centrifuge Torque Indicator/Controller (JIC-50I) North Centrifuge Torque Indicator/Controller (JIC-502) Backmix Section P Indicator/Controller (PDIC-503)
2. Monitor each dryer closely to watch for Bird Centrifuge problems, i.e. pluggage and pin shearing, and for backup problems in the transfer systems. Although watching for these problems is part of your daily routine, it Is especially critical to identify and correct these pro blems during freezing weather conditions. The longer the dryer is down, the greater potential there is for slurry lines to break.
30
VAB.0001136688
A
Name Date
WINTER PROTECTION CHECK LIST
NEW MODULE~REACTOR "A" OPERATOR
Objective: You are responsible for preventing equipment from freezing in your area and keeping the new module on-line.
1. Any cold weather presents hazardous slipping problems. Watch your footing. Put down salt or sand in bad areas. There's also a lot of exposed steam tracing which caused 3 first aid cases in the winter of 1981, watch out! A utility or a general helper may be assigned to you and your area. These are relatively inexperienced in the reactor areas, consider yourselves their 'big brothers . Watch out for them as well as yourself and give them any pointers you can.
2. Keep water bleeding to catalyst charge bombs and to drain when not in use to prevent freezing.
Times Checked
741
742 _____________ _____________ Check twice per shift.
743 _____________ _____________
744 ___________ _____________
745 _____________ _____________
3. Keep steam on both seal oil recirculation tanks to keep them warm, not hot, to prevent seal oil header freeze up. Check temperatures four times per shift.
East
West
Time
F Time
F
Time
F Time
F
Time Time
F Time F Time
F F
4. Keep a good steam supply going to the coils of the area drum shelter. Check the trap operation.
VAB.0001136689
%
5. Cut back water flow to both RVCM condensers in recovery area to keeg^ RVCM going to receivers warm. (This will prevent ice for mation in receivers). DonTt completely shut water off in order to prevent cooling water line from freezing. Check twice per shift.
Time
6. Check the blowdown tank temperature. Set point should be 125 F.
Time
Check twice per shift.
7. Steam hoses should be blown empty and stored in a warm area when not in use. A supply of extra steam hoses will be kept in the MCC Building
8. Keep water and steam at utility stations bleeding to prevent freezeup.
9. After each batch is dumped, the dump line is to be completely drained by opening the bleeders on the discharge of each slurry pump and allowing any liquid to gravity flow back through the header. The case drains on both slurry pumps should be opened to allow flush water in the dump box to drain to the sewer.
10, Check recovery knockout tanks frequently to make sure they stay warm. Cut back on cooling water to recirculation cooler if necessary. Do not shut water completely off or line will
'twit
freeze.
11. Put makeup water into knockout tanks frequently to prevent line freeze ups.
12. Check seal water separators to make sure they stay warm. Cut back on cooling water to seal water coolers if necessary. Do not shut water completely off or lines will freeze.
13. Put makeup water into the seal water separators frequently to prevent line freeze ups.
14. Routinely monitor dishcarge pressure of recovery compressors. If its over 75 psig advise supervisor and start trouble shooting. - possibly high receiver pressure - possible plug between compressors and receivers - seal water separator too high a level
15. Keep safety showers bleeding to prevent freeze up.
16. Any water accumulation will prevent slipping potential. A supply of salt will be kept in the MCC Building as well as a drum of sand in the unit. Slippery areas should be sprinkled with salt sand or roped off to prevent slipping injuries.
32
VAB.0001136690
-
i i : i- . i- i - * ->1 >p - - - r it-.......................
...
.............
i.-'
. -r t --
........................- r-
t i . ........... |~
. /..j.
.t| . ..
i p*. . l,i ..................................- Ji"
tt
A
17. It will be important to frequently check the lip seal flushes and spray head flushes on each reactor to insure flow is maintained to prevent freeze-up.
(AM & PM)
Lip Seal Flush_
9:00
1:00
5:00
Spray Head Flush
9:00
1:00
5:00
741
742
743 744
______
_______
WHHIMMhaiMIM
_________ ________ _________ _____
745 _________ ________ _________
18. Keep cooling water to the methocel makeup tank jacket bleeding to prevent freezing.
19. Keep bleeder going upstream of control valve for charge water temperature control to prevent freezing.
20. Keep bleeder upstream of cold water make-up filter to steam heater going to prevent freezing.
21. Whenever the ambient temperature drops below 20F, the AMS Kill System for each reactor is to be checked on a once per shift basis. The checkout will consist of a small AMS injection into the reactor by cycling the automatic AMS valves. The system is to be checked for proper valve operation and positive indication of AMS addition. The Lead Operator for the module, the reactor module "A" Operator, and the Chief Operator will be responsible for the checkouts with the Lead Operator coordinating timing for each reactor. The checkout is to be done after dump is complete and before rinse to sewer. Responsibilities will be as follows: 1) Lead Operator - will be responsible for cycling the automatic valves using the manual addition button and checking lights on panel for open and close indication, 2) Chief Operator will be responsible for checking the automatic valve operation in the field, and 3) Reactor "A" Operator - will be responsible for checking AMS pot for positive outage indication by measuring level before and after AMS addition.
VAB.0001136691
A
Tim^
Initial Outage Final Outage
________
741
_____
__________________ _____________ __ 742
_____
__________________ _______________ 743
_____
__________________ _______________ 744
_____
__________________ _______________ 745
22. Steam trap supply valves should be checked once per shift and the corresponding trap(s) checked to be sure the tracing is hot and functioning. _____
23. The 2-ME addition system on 745 should be drained and water left bleeding after each charge.
This list should be considered in addition to the normal daily checklist. The list touches on the major items but you should use your judgment on other items you know to be problems during freeze conditons.
If you have any questions regarding this check list you should contact you supervisor.
34 VAB.0001136692
A
Name
Date
WINTER PROTECTION CHECK LIST
OLD MODULE REACTOR "A" OPERATOR
Page 1 of 4
Obj ective:
You are responsible for preventing equipment from freezing in your area and keeping the old module and emissions recovery system on line. You will be given additional back-up support from the utility as required.
1. Any cold weather presents hazardous slipping problems, watch your footing. Put down salt or sand in bad areas. Rope off area if necessary. There's also a lot of exposed steam tracing which caused 3 first aid cases in the winter of 1981, watch out! A utility or a general helper may be assigned to you and your area. These personnel are relatively inexperienced in the reactor areas. Consider yourselves their "big brothers". Watch out for them as well as yourself and give them any pointers you can.
2. Keep water bleeding to catalyst charge bombs and to sewer when not in use to keep from freezing.
Times Checked
D-300_____
___________
D-400
D-500____________ _____________ Check twice per shift
D-600
D-700
3. Cut back water flow to both RVCM condensers in the recovery area to keep RVCM going to receivers warm and prevent ice formation in the receivers. (Don't cut off water completely or line will freeze). Time___________ _________________ Check twice per shift.
4. Cut back water flow to RVCM condenser on top of roof in ERS to keep RVCM going to receivers warm and prevent ice formation in the receivers. (Don't cut off water completely or line will freeze.)
___________
_____________ Check twice per shift.
5. Keep bleeders going to PVA makeup water lines.
VAB.0001136693
t
WINTER PROTECTION CHECK LIST
Page 2 of 4
OLD MODULE REACTOR "A" OPERATOR
6. Keep a bleeder going on hot water tank makeup water line upstream of on/off control valve by cold water filter.
7. Keep bleeder going upstream of control valve on cold water for charge water temperature control to keep from freezing.
8. A low point drain was installed on the water rinse line just north of the hot water charge tank downstream of the on/off control valve. All bleeders upstream of the control valve should also be opened to allow this section of the line to drain. Don't let the rinse line freeze! The line should be drained if it wonTt be used for a one hour period.
9. Keep water and steam bleeding at utility stations to keep from freezing.
10. Maintain a good steam flow to the coils of the area drum shelter. Check the trap operation.
11. Steam hoses not in use should be blown empty and stored indoors to prevent freezing. A supply of extra steam hoses will be kept in the old control room.
12. Keep water going to K.O. tank recirculation cooler. To prevent exchanger from freezing and breaking.
13. Calcium stearate will freeze at 40 F. Once calcium stearate freezes, it is not reusable. Do not store outside of the calcium stearate storage room. The steam space heater should be turned on when the ambient temperature approaches 40F.
14. Routinely monitor discharge pressure of recovery compressors. If it Is over 75 psig advise supervisor and start trouble shoot ing.
possibly high receiver pressure - possible plug between compressors and receivers - seal water separator too high a level
36
r -i ' * ' r - * -f-
r. .
L-I :i H-
iI
> i
VAB.0001136694
A
WINTER PROTECTION CHECK LIST
OLD MODULE REACTOR "A" OPERATOR
Page 3 of 4
15. Check recovery knock out tanks frequently to make sure they stay warm. Cut back on cooling water to recirculation cooler if necessary. Do not shut water completely off or line will freeze.
16. Keep safety showers bleeding to prevent freeze ups.
17. Put water into knockout tanks frequently to prevent line freezeups.
18. Put makeup water into the seal water separators frequently to pre vent line freeze-ups.
19. Check seal water separators to make sure they stay warm. Cut back on cooling water to seal water coolers if necessary. Do not shut water completely off or lines will freeze.
20. Keep some cooling water going to shells on emission recovery seal water subcoolers to keep form freezing and breaking.
21. It will be important to frequently (3 times/shift) check the lip seal flushes and spray head flushes on each reactor to insure flow is maintained to prevent freeze-up.
(A.M & P.M.)
Lip Seal Flush
Spray Head Flush
9:00 1:00 5:00 9:00 1:00 5:00
D-300
D-400
D-500
D-600
D-700
22. Keep some cooling water going shell on ERS condenser on roof of recovery building to keep from freezing and breaking.
23. Monitor temperature of fresh receiver and notify supervisor if goes below 32 F. There's a temperature gauge on the 1st platform. _____________ _____________ (Twice per shift)
VAB.0001136695
A
WINTER PROTECTION CHECK LIST
OLD MODULE REACTOR "AM OPERATOR
Page 4 of 4
24. After each batch is dumped, the dump line is to be completely drained by opening the bleeders on the discharge of each slurry pump and allowing any liquid to gravity flow back through the header. The case drains on both slurry pumps should be opened to allow flush water in the dump box to drain to the sewer.
25. Whenever the ambient temperature drops below 2QF* the AMS Kill System for each reactor is to be checked on a once per shift basis. The checkout will consist of a small AMS injection into the reactor by cycling the automatic AMS valves. The system is to be checked for proper valve operation and positive indication of AMS addition. The Lead Operator for the module, the reactor module "A" Operator, and the Chief Operator will be responsible for the checkouts with the Lead Operator coordinating timing for each reactor. The check out is to be done after dump is complete and before rinse to sewer. Responsibilities will be as follows: 1) Lead Operator - will be responsible for cycling the automatic valves using the manual addition button and checking lights on panel for open and close indication, 2) Chief Operator - will be responsible for checking the automatic valve operation in the field, and 3) Reactor "A" Operator - will be responsible for checking AMS pot for positive outage indication by measuring level before and after AMS addition.
Time
Initial Outage
Final Outage
300
400
500
600
700
26. Steam trap supply valves should be checked once per shift and the corresponding trap(s) checked to be sure the tracing is hot and functioning.
27. Keep water bleeding through experimental CTA pot for D-700 to keep HPSW line from freezing.
This list should be considered in addition to the normal daily checklist. The list touches on the major items but you should use your judgment on other items you know to be problems during freeze conditions.
If you have any questions regarding this check list you should contact your supervisor.
VAB.0001136696
NAME
WINTER PROTECTION CHECK LIST
DRYER "A" OPERATOR
DATE
Objective:
You are responsible for preventing equipment in your area from freezing and keeping all dryers on-line. You will be given additional backup support as needed.
Particular emphasis should be placed on:
Dryer Recirculation Lines
Fluid Bed Dryer Operation
1. In conjunction with the Chief Operator, every dryer area slurry recircu lation line needs to be checked once per shift. Lines not recirculating are to be flushed with water and blown empty with air once per shift.
Time
Line
Status
V-10 Recirculation Line From 501 Blend Tank
Pond Resin Recirculation Line From 550 Series Blend Tanks
V-ll Recirculation Line From 501 Blend Tank
V-ll Recirculation Line From 407 Blend Tank
_________
V-10 Recirculation Lines From 502 and 747 Blend Tanks
________
_________
V-ll Recirculation Lines From 502 and 747 Blend ________ Tanks
_________
Fluid Bed Recirculation Lines From 502 and 747 Blend Tanks
________
_________
Drain Line From Fluid Bed Scrubber to 654 Blend ________ Tank
2. Although temporary sheds will be built around the slurry pumps for 407, 501, 502, and 747 blend tanks and steam will be injected, there are still several potential freeze points in these systems. The following items should be checked on a once per shift basis:
All idle (spare) slurry transfer pumps servicing 407, 501, 502, and 747 blend tanks have case drains open with mechanical seal flush lines open.
All bleeders upstream of automatic flush valves west of slurry pumps are to be cracked open.
A
39
A
VAB.0001136697
WINTER PROTECTION CHECK LIST
DRYER "A" OPERATOR
Special caution should be taken when entering area under temporary sheds since there will be water on the ground from bleeders and condensed steam.
3. The following items on the fluid bed dryer are to be checked on a twice per shift basis:
Time
______
______
The water scrubber pumpover pump drain casing is to be open and flush water line on the suction of the pump is to be cracked open when the pump is not in use.
______ ______ The spare scrubber recirculation pump case drain is to be open and the mechanical seal flush line open.
______
______
Crack open bypass and control valve for make-up water to the scrubber to allow water flow. Since this action will con tinually add water to the scrubber, a more frequent check of the scrubber level Is needed.
______ ______ The spare hot water recirculation pump case drain is to be opened and the suction valve is to be cracked open.
______
______
Check all utility water stations to make sure supply valve is cracked and water is flowing. Run water hoses to local sewers. Stations are located:
a. Grade level by hot water tank. b. Grade level by plugflow supply blower. c. Second grating level on north side by scrubber. d. Bird level.
4. Keep water bleeding on water make-up line to the glycerine tank to keep line from freezing.
5. Keep glycerine solution recirculating through the hydrometer loop to keep this line from freezing.
6. Crack open the bypass valve on the cooling water temperature control loop for both fluid bed transfer blowers to allow some water to flow through these lines.
7. Check the cooling water supply lines to #1 and //2 transfer blower after coolers to make sure some water is flowing through these lines.
This list should be considered in addition to the normal daily checklist. The list touches on the major items but you should use your judgment on other items known to be problems during freezing conditions.
40
VAB.0001136698
VI. A. STEAM TRACE LOCATION DRAWINGS
Steam trace location drawings for old and new reactor module areas are included in the following pages.
t
i
VAB.0001136699
A
i* ** I4
, * `-
v,, L4
'I 4
,I
.f
', #
*J t
*SS
* '- ^
ii
/f
* r-
J
'f *K4
**
'y/-4? yoi-VE&'l t:>iRUHR tonon
ttf .' ;6MT <m/^SS,
i'/'
/i. sSI - '-> '1 f*J/.
-~J~b'Hpc #t j-r/wcJ
/<*V) wW
l+`sr fit -tt>i ta*0*-
J -+T~D ~?C/l j-'w/tr //*j FKofif Hl t>
TumP-S, F- rrff.S, i;KCPhi&G?.$,5t.rit
- Tt>TMSPuSpOplOy /.tlk.f /spoir7rct>t3$-;&7*ifo- F7s0oSu-'JryvCt Stf/HrMAt CaHFAU*<mZeF-f.'S.A*S-T>rT?7*A|'-i(-Wc titnr* of-
W'$fP/*70H3,t>- 7St>u#r'MPtbY.fPtAIktiS,'H.*\ rV/fitit>KsSu'?.X>iJHfr 7c~,0/Apfiisp- 47l0eZr-s7t03
CPtlrSp/S - nO*P4- A/i> <T/+ 0)- 1PZ TfitiK
r+Tp Jo3 VOtf Sbtft Hto Surra.
FURoe /`'tip TO TSfiiTPM op ~roi ^
--i-**
S&A* y/k:/yirUt^nSyor?unoiiA3*tt'{Aiw*
JL*^*6~ y'Lf
304/1 tic p
5&y/*E/*j0Xl* TK^KJ- tJifLrrt
WISJ 57jAVi)t\ iV tfrft &P
iS - Sew# 77?#^
To ourftr pA\>? `Barren of
7&t TP Til |#.T 4>P &4>r# IfitA I
-TMfZtPfrfz -Spurt* +y iroxrrt $*w/
/felt y*Mf~i+'Sr Tfifip.
to Bpttpm qf ipl St<9/tra/#&
TfpJnAl pAAtrt Tbit &prr&tt of
l~/,AW0ry<'S&r t9F~CAtTaot0rtMtr7iio&0/cPy TT7ooi>tF* tfVpllFPiO -TRAPS' tipfrti H'Cor 5//i4yj0i4
F&St, /V fy* L M' Vtsiz' ry/i
y*0 0/Z 7J>3 7Ati*
Ly>,t'FYoi/f7GCPa+JIAI XH,O
Bt4 T*JrAr*+zJH-tA
p*
1
Uf?A;4 itrtf ftrA1 yp$ ro
-MTAK4fi;pyoSt&'' tBippxtrtt*pm*+PfFsr7p**
5 yw
tFrL't `Asr
TO CXocs 0yK /V/ ^ Fztppt 70 3 - 70
CA*/*J6 I>AA.*1
-cT?rF'fiFF7Sv^o-3 f-SU7Q/1pU(Tp0mtyf yP*fS>riT'VrtOArt
cfreAn
GOtDThG lOCHTiOtl- OFF S TfAM
SUPPIY TO B.W.S.-F)PP./ WEST OF RECOVERY STRUCTURE. ft?? I1* ABOVE GRADE.
To F*F*$tw* Fl**S*t SuftVY
Tld;A>tfi0 'dR**C*JT< T#t>&rk*- SoMF>*?poU! t-rf 4 Surplus &p*o r^ *v3
ro j-tst Vd# ru fiti+t r rAUK nuHrit*
- -r0ps> - rtPKtyy &f cp/ze^f"
pi*++ips
\j*7p fteaue/u i.-J F#m
&t>jror-%3of S^T/)f At v p;/r Tacks - up
tTfoe!s7r>9aMcArtoiQstsTHroiWfofi-
~ rR*p$- rtr/ffiKTH *>Fsr Sr/i*ULiorf OF F,?t&% /%.r L tryft, wes r f#a ?*
Jto p.Fts. u>* f/vst* `Sirpp/T /'*ie jUtTtt
PF TOt To TpP
ysOP fy*t OtrtUZol ` lot Jit
GO I DTAG
-* Trf>Fp/fpSl- C/J<k*KTrt
>F 5At >ife p
FAcAArt6aM$t
ro StAl Hto Vf/Htis OF
70* ~ 75- roy
ST tJfif TH H'S r
o OF 70Z. TAtiK.
AFE
5Tt~o#i /{* *> S yFpii YfAf&*rHt*Ac4*/\o\s j
SC/H Ac* f,!TSIS FAtr*
BFTusFFrt 7d?OJy
TO
Trto- FcG0. tivi- C r PU"TMOPSSyrTPfFfii *****
f r rrwP% * |* f r
Loo9Tiod: AT
< t>urpir
STAiiGotl AlORTM R V.C. At
Co/lfCTTArtK.
4 /0 SE4t Hto
ISU DATE
DESCRIPTION
tv CKP APD
~ourter /.JesF&H
'OOT'ft R.V.C.M' TfitiK
CONOCO CHEMICALS
-TRftRS- O'&srof J- p-UPifi
ABERDEEN KCOH. As
MISSISSIPPI
01D MOD
STEhh TRACiNGTO
FMiS\iOfJ RtCt) [/FRYscale:
aped: date:
No.
V&#.6011
/o c>
t - J ...................
:
'
-y-i'
>': i *;:.;- \
fc 1 1
i -"
.
- -^,
`
-:
i7.l
* ^ , t .*
*
,i ;?
\
* < . ; ;>:
V*-.<
_.
'* * 1? J
i% *
* `'
1
...
* r> V ,..1.
;s
> fc
* '
''
* r. 4 s' '> * 4
r
. 'V j*
A f
I
' i
V t
.
C * 11 l
*>
k
i' j * A - b <, *
-
i
.
=
" , ,.,
*#-.
f- i ` ^ 1 '*
M
n^
->Te> rf 4 B Pi Coi/TkY CO/i f'K SSD*-lt
PMc. PuhPi, STMl tfto Codrpol(?z 4 p;p;A<5t Press uzf TPfbis. - rPn ?5 - A) GM/lVT Ltbbi Abtirp >P TTai Mt o Rum p5<
->7b OPftid )idc OFF P`D TfttlKf, Kciki'M 1/iT't od
PuMp TO WMF R Z>KAidtfd FPom L-R.J.
Lr-GOlD TATt *10*1 LoCftTlCi\S>AH
Sps Tfn T/es id, fiakt u p mc //>
Both 5Ai Mc0 SEPARATORS. - tRa-Ps - &-) D/lE Sol/r/J of tt. p- $. h'- p///-1PS
&'/)b&y <3 RAPE- odF at McpulE
601D TP>6 roe
to Aura. ~Dls~ Ut/W6*e PAlVC OFF RV-A' Ctf/K&i
5r/ldood<- WFsr s;dE of izttoreKY &/;iv>id<Sr 7D tfPS.WT TlUStf TO 3Acp f/uS M FtIter,
botfiriod
or vrccyrry />*:#
Pur i p D.SCMaT&T
SiDF OF PV.fh
CHARGe /4TX. TKAFS- fer j*
SFA/ tfioF/ustf To MoPrd $ Gourd Ko.
STEAM S
TAM* RFCiRCu/ATl od PutiPS.TF/E PR0CFS5 pAiy To B#CK PiUSH bilTFP-,
HBs.w. 1>MF Pack to Put iR tfzt> RUSH To [Tv.
TWAM Sums-
5AM -pRe-ritATt'f:
JET
levyl weVs i-SiGpr gJ/ass Bontrf,#. TAMPS
AFE
-TP/IPS' AT STAdCt od So(4 TH
ftp ff.PS.W PUmF5,S/ ftbovE gtax>. fast m*p.
TAG
rt/ol
GO I DTAG
#/o^
ISU DATE ________ DESCRIPTION
Y CKD APO
botflTiOtl- terFrlf/40RTri BAST OF
tfoPrtf Ko. taMK RFC1RC ulATlod Pump, A pp- /o' /9bo ye g z/i d e.
CONOCO CHEMICALS
ABERDEEN ^ con id
MISSISSIPPI
M O DU IE
STEAM TRAC i MG TO
L REC (W t R Y
appd: oate:
AREft
scale: vAB.nnnl 136701
G o i r> TAOS
No '#/r>T/t>2-/oP- to*)
^i *
H ,. i';
-i .
lH
'#:V > - v -- .
4.**.*
I
,
-' i> < ..
J 4*
-+TO PRESSURE
rK/hJ M.' 7Tf fc3.
'Tif/tOPFiBB.fW/f.Sfi-*'
r1 *T.TFOCEfTiW?i/eEMl-i :eTti*'iZTOAoltFtpi,FO' pB,TUO s& 0. 7JP/!/J,Sf(?
Pune $=/?> dz. /'**.
.5 OUTri '&,*/ %/ yl* ic <TiV *" *T Obi
o.vu. 5. i;
r <'>/>?. <r
\ys t n?/p.
r? -g 50ur/t
'w5oi D T#<s * /-TOP Ofsvs
SO*<ifSTVHlfpj/Of}f-Tf#3$.?UTTf<*At*Cr'jK*y&fiPf'?.
r o-
r*?/}
pa
T~ T./,-/Jf FRAr1
-/*r s^rr/iF TKrtpi
B/ii^ P^u^J rstAX T&
'*v7y?/^p
&r r~r s. ` i^^sr 7
TOfTAsr THA*isF\
AietS M ODWf F/o * E>DtS/J TA^K TV>
' Titfirs - Slip Ser *>F rgMPS WG1} OF 747, /JOKr# * P f?. #*S." f-*z:f~K f* F *
6011 n M r
f>TD CCHP foO fFO 1/fiF fpCT DFIU6S SHEO
'?/' TcO!.Z/}TIo/)-- i5fc7J HoFTft EAST Of .R.S 71j V. /.
TO FT:
TO tJiRrH T v, (. H. yecEiveRL>72> T/JSKISMftHsfMO farof
l l Ft I r 1`I* A; .
iAv/^ />:. Af-
7".^/?.5
- -TTr/)PS- Aioi?r^ s;j?
>-t
----------
I|-->Wr6aKf&HjVT'7-i"'-C>/--iM>T/'"ver/; vX* /; :
f// Si O f?t
BorrflM TPflF.
7~ c oF fki \
BHD OF B.W- S' j ~ TfAFsTp^ oHB fir STfi^CJOf! Fficr S/UET Of F.R.c.
7) pp z a' m
Ofie fir b.ukc. Ten^heK Pump-
ft b'OFF 6 TFoe.
I E.
S r/7>,/7 S LA m Y To B if: / /?5/
IO nR ArtU ifiFS I f nr,
>TO 1fiSV-HAThV> SFf-fVrA OF 'REC-OyEP. Y \Gi.E
7^> 1&>TTOt\ OF
Svt~uCrHkt IPil'.FCt. H*
5-'i>r ToP
M G>0)D7fe
*}on
jbocarioiJ: Apr 5' fast
Of SoutH P.ucH.
RCflyFR.APR/f flBovE G~RftT>
Wikrrsr-
FflS T OF
KV'C. ft
I
);!'(.LiVl P'i HT>o F.yc.n.
TECS > VR, $V.COVTFX X /;'If TO T. l>< C. M fi; c. K
&0IDTA6
FTOH Ew-;;.. To /..RFr_r> ifKY CYSTFti
/O 3
SECT;.0/1 VSg'ST 2F RECOVER.'! ftRFf
-TRAPS- Ar SrAriaoA in'crsipr OF
Ld& ; - to'at oa app
RFC c ye, _ y Fr/ a - WFT T TRAF-
P/?<rp, `BOTH Ff-C Tt.
F/tsr of FECoi/eKED
FTFFH PACKS, SFfiI ^o
to P.y.c.M- cjMf&g: Fun
V.Ch. FECEWERS-
t both Fy.c.M- chmgg FVmw
iriStj )ATD SfCTiOil of fy.c.tf. Fffo h`U To
APP15' ABOVE GRADE.
Tv Fourtt Kv. c. m. kecei
TRlAPS-iivTesfJrK5 'Df H c*rr om rit A V.
Fy.C.ft ~PFCEii/`F.%'RVt!cnfierce /jJc FRot-t phter
PfiCK To C.t/fi R&S METtR-
-TRAps-Ok) HoPrfi Tec. -tvs r TRAP
4*
AFE
To f y- c.ei.Ptce>yR
fevet ~re<.K.
-TR/irs- *S r 3 '.P^Borron TRAp
S.
TO BOTTOF OF F,fC. n RFCeirf R
- traps - EASTS;DC Top TRAP
(nOioTBS
G 4 *32.
Sour/i Kec - South TRAP; FPFSH
RFC.-AioR.TH TRAP, Sourfi c>f-
f.y.c-M' F^cjcs, fiT R.y.c.tt- cHflyac
PuMpt HpktH of ficH F-y.C'MPutTpsf south rPf> ufioeR F-y. c m-
hoCAT{Oli--tA5TOF FV.C.h. -RECEIVER f>PR<-ffit?ove GKfWE.
ISU DATE
DESCRIPTION
CKDlAP
CONOCO CHEMICALS
ABERDEEN Coll l*k
MISSISSIPPI
DID A1ODUIE
STEAK TRACiA/6 TO
(C.MCMR6E f\RFMBWS.*cai:
appd: date :
I .. CjO/d t7' --
| N o. #c^3-/D3 _
6702
*. :.! \\ twiS,+ ^Sl V \\:"^y * / ' ? * Vir
-. .^5 - .J|**rf >: *\*t
J- ' ^v;;: ^,-'M
. , v.; -V- :; ;'VirK-pP7'^
" r"
\^ V
1 T 9 *+h i* *.* 1
I* '*
+1 *
D-70O
D-600
D- 500
D-40O
15-300
TO TP-SPo
TF-Atis
fi V A- A-VJ/ V
d/*/i>,; /V/mfiMfreR.
peessunk TR**tj$., r.iiFK
/*S/)5H/ &*tSE~. OAfrO 3 Oa
>? pf-lD-, /if/XfJ oMT &'
T Si Dr D-O Op ~ MnA?PA, uP'SFf-yi^JEiTStsT-SJ.i. OF T>-Soa
. Jf____ _________________________________
, Got D TP 6 * H3
JupC/}Ti0fi\z BTy/ /J TO-ifob 4 p-500
TO E>-40/>
5 opD TR/lpS-W'/Sr S.I
MAAy^a Y / &'** i
j n D Zoo r* fS/t'S$Sl4#f~ Mit4i>nrreK, M/itipMjfj-o
CAT/fMHOtSPfAPSt MR/CR_/H__S_t
*7lyEt Tp Ctmu.
- THnPS-Gt$ Mr .sspc Ui*
NF.-Lr'/ly Lf *-v: /.
sSTffln SaPpt.Y n//'sr ^factors
r&D7ot> C#,ti<s o n pipica fiAActF LiAES TO TTi-AhlSfil/TTR-TRAPS- EAST oEO-ybo AT TK`ftdr>.
io ry .loo /,;p S^j fins a
MiTTt R, SEA! Hl o Supm A;fit. -TXA Pi -WEST O P 0~S oo
To J5 4OP C.Ootid^ th.O ORiFiCtT
__ fJAdtuf. --O'AKj- ~Afrof- Is-3 Aa*.
TW D-7Dt VP.eShuZETfttk'.
Cutt) chem vPAsrt(RiA&f
pfitye to co4oe4so c.
<3t IAch s/cw vEsi r vA/tt. -TRfifa AT STAtlCbH Sourt*
EAST Of lt-00 0.
10 D-yoo ff/)At>HTtf *
PK t C s u ti e TRA MS. ` l . tic-)
CMKrit) ,,
,,,
/?r STAAc; on
South East of x>-7#*
>\
7o 0-50o Cooftkr //tbA ofrfic e fIaace .
-tta ps fas p gt t> soo-
Tp l -Cepo LiP SEA! FlffShfMtllA
Seat ti,9 Sophy Litie -TR^fiS WEST of U-* &o
TT> l>ioo Cpolif^C /V. o OPifice
E-lAti <SC~. T7?aPS- east of P-& go
10 D <lso JL/p SAf Ftwti
-rMrifEfST-*ftVs#errs/#ti Ift:>fyf Sr>u-p<ply
ft1 0 ^00 Aw Cpo//fii& *t,a wive ru -VfArj- 4H~ Lpc*t/pH
OEAO LB<*
TVaPS- SOurA
T>-Hoo>
r 3 >> l/rseAi F/x// mftstp
T*Z7-A /./*/t. 5or,lZ*lti<FZpfofj,rl tySfsr > F D3*Y
-TO O~3oo Cool-tis
iMUrrs
/- r'Kft PC,- Sj*ne /oca r/#u
, TO D-Jon C&oiSaJ *m Ft
f: F/Ad/iS^
l
DfAO LG 6, RA PS GAS r OF Vhfro
to t>-7oo cab;tier for L;p sea* Lilies i AETCR.
- TKAp-S- Ast of CAVitieT.
GOIDTflG *H3l LoCfiTioA-Sounl. PAS t S TAflCoti, D-700
w^
601 DTAG
-* HI LoCflTlOtlz OFF
SuZElZ
STEAK b^PPir TO~K5od
~5~fl CKF x rtf'# 5' J9he>re
grade.
AFE
& HO l DC/iluOM: OFF S FFA M
.Skmt
SuPFI Y To x> 4so Jacket, APR 7' Above GtPrtP.
--'1
i r :
1 i m .ij'.
j ft-
t
-1F%?
L1ll.^1*,^llJl,- -h--
>^ "n- -:j'h i .
stfam Supply
-DE/UGE
/
StfED
GO ID ThG
ISU DATE ________ DESCEIPTION
V ckd|apo|
CONOCO CHEMICALS
ABERDEEN : CoihfLs
MISSISSIPPI
DID MODUIE
#i/4
STEAM TRACING TO
LocatioJ: flloRTt/ of rrhr^i^EfitTOR DPT Pi
S}W>-
appd: date:
No v/j/On In/D. a#T-FDU4S./S/9
36703
I P*
'
'* f-
:-
-:-l -
fe
-. '
'-
'.*
I , * -' '
V
4p
ih
* *
i -
Vi
__ *rr*
auto-
1 `out-d <J o Eu r'>'/ j'
re> Wfu/ AioDw/f
^Oltrij East- 'ivOlbR. 0<c
M6*s Mi>Du'e Cory-JS T/jii/ffi,
-TF^pJ- SAm? foC+rla.S.
____vT fneRFiedc y auto-
CooUaJ6 .9^0 SupP/9 rAtve to o/o mot>u\e dorri oF sJ/xh/ moouIE
&pfA>;o*l (Vfsr) Coot;*i6
Ty^/EO.
--rP'/VRS-
!gcj*XW<
"to ofZlf;< ffrttle.es 4 pzo
F/oi*> hereps, ad m o si/ff/f
Uj4E5
*- M c/xi ft 7* A*! ,5
MoRTri oF tj s/fcj~7Oq
TO/4/gtk
TJ^P^PS - f&Mfiz /0C/*r;0<i
n/^SOID T/i647
* IAiCJd &AT o/Z
Lo(LPiT;o/\ : ftFpzo' Alokj/i op 4e/pModule EapA./s-Dfl (ycr) Coo//fl<i Tov'tp.
A
Supply
to r/lt;4fpRToR
ftPP. W ft&OVt (iRWOt.
h r 4 - *-. |-u 1 . i -j( | i
I-' % i ': s
~> f/U'/t Hi n /./if
~rrj V/lXuH ZTrPf^F
Rttips.
rS01DT/!6- */if
- TRAPS' FT7ou> p.v, />,
,*)*'isF iT-ix.
pTO/AOofSftfrioC-'sf. 1 P!rtM>F
nT /i/5
Luis To Zc.guB8?
-TyzftF*'
of
yr//65^-
I"1 *
/>orj77Dhl-- TAC,; vf CjHC/UMJ>TET.fiTE
SHE l> EP-CT sS/l!f
P ??. /ft'AZo'E
G?.p(OE.
SWIM SupPlY To
WATER Ibl CfUGUM STfRETt
SHE D.
''-C*0WVPi*l5O
k>nrat;rl-- aIoFtP ;tt of /=7/v; D Ef'D, u ' C T of PlU'i f\au/ Elow/fP.
A
STEAM SuFFIY To
FlUi D
AFE
FlUiD BED TRYEP
b
STEAM TRftC idG
ISU DATE ________ DESCRIPTION
IY CKD APD
GOIDTflG
OID TAOmtE
CONOCO CHEMICALS
ABERDEEN y. Coii;,lz
MISSISSIPPI
Tw,
STEft M TRAGMS TOlSTF/IM Tf? To EMERGENCY fturo
OalC.iuM STERRTE
SHED- Go ID TAG % appd:
date:
Supply
No*(So
6704
5s>
GdlbTm
To 7VS tTuktAiOloKT*0
-traps at sewe*. rloKTtt esTrZ>*f7475VMj*aA.o nTBK
tT*essu*k.e r7**ls. (south')
-HroffxjttrhseAasrsteowFEihfts.
Jr fA Stixct.
to 744
SuPpli $ S/th Es 741
To 744
TREPS-EHsT oF 744,
5Am A 5 ~>4t.
TO 143 Supplies Same as n*ft
TO T4i
TKAPS- >sr op 7</3, SAM* A* 7VI
TO 74* SuppUes SehE as 74t
TO 74 X TF-APS AST OF 74
SAME AS 741.
/ii> 741 SWV HeA X> Ft$U
/F
iters
tKaps. EAST OF jH
rT.OH7s4EffMoAcaIoJMDEiTWF&iCAA.fH-pwr/rHsMf.
r^45.. FoHpEHS *A r*t*.
-Fast P LEp\
, To 7H CooKdS rt.t teats to \ctz;Fice f/ajlc a m*4s.,
5wfK MHCTA \Auro <ootiti& Ht,o otters.
EAfroFTAS. * TKaFS-SAHE iOCAT.tti
To 743 CeoitACf He.o
0X.flCE FMslC 7-JlihlS.. TO- Coo/,46 At r/Heiis.
TAPs- Sam* /oCATioti --
r 74S CeoHti& Aio
oVficr FtAMi, TXAtlS..
rt E * yout~~ ast f~AT s-r/*dca; 0s4
fAfT 0F 7<&' *1 Qfir. parS. TO 7<f</ SSM &,'/ lo>P iCr/uc&mo opt)
- r'PftFS- SAM4T ipc*t*~Ut
T
^ Steam Suppit
to 745 Jacket
V
^To 7 V* C)OUpI(* #*0
ttFic e F/Atfce, thaas^
farro. Coo h'tis
jL 7TAPS'*
nf o va*4*~s
/oc#TtG*\
To i*ft C>o{;4g HiO
OKIfile* &AdC,rt t*AJS.
Auto Co&l* dc, a fAlvs*.
~TTAP$-
/orjfr;#iJ-
Let/tL
SuppiH
fysr of 743-dofft
7Te/K<~?- TRAPS ft
$T*4;otf tf&fTH of 74i &1T*ktA S>rgi PKW <3 mm**
rpi *P <S*v/ oH 4oTi*i44.
TBfiPS S&Fi^T i*CAT;r<J
'1
fsr~&f ?4t- t C+r. p*r$ / (Ffoac.ec> off)
p#/ StAt oH/t>of> Pr* np -SAT ittCACi
Supp iv
To SiAi 0>! PRESS. 'COAtTfol MAlrE
HeitrA East of m/.
-TKAPS AT SEtetft
SAMf /OCAT.'oU.
7c AsrSu>i r
Sf*JCK F PbnFQ
TXAfJ w'ST *F
at* sr s/ure. r Fb*p
AFE
770 CHFf-l WASH 7>El TFcK; S*At
*4 o To "Both CAH
WSt* PHMftf~TTAf5 - $oohi*rrt/ft ifrsfojjTraatf Wisi CHEH wash nAiP'
mdlTBAM SUPP(9 TO HoDUk
GotvT/16 */Z4-
Co40E/iSfTT 'FETUKti
Coo SHY
/97?A
| ISU DATE __________ DESCRIPTION
BY CK0| APo|
CONOCO CHEMICALS
ABERDEEN TP. Coif this MISSISSIPPI
NEW MoT>u!E
STEAM TRACING TO
JtENC TOT PIPEA scAtcyAR
APPD: date:
I kiGoID 7"/?6i
I No.# /_ll 4 A2.S
36705
, *,*** \i ? , V `i . * .
1 p.%*Ti"i ^
>. .a t I i
1*
, * ' ' ' '
i H'll * *hJ J *
'>
I 1.
' *.v-
'>' r'*?,' &V * :.
. ; WW .vV. :* *
#
V
' -V -t *
r l * -v
*L
iJ
. 1.
f x - r": **> *
.-.. ? :j.* : .'
.->, ; .$'' *;
r -vt,
; :
- '
` *1 '- .
--?;tvy>vV,;9r.tr''V,,
-jHrsr Sofftf
SPA*ATJc>je-
h S^i
/WP*Wr*>J Jtvj*, CcvaJrrZteoir, tnePuftt iT>&H,
pw^rP h toK^at**d vdi?
i.*Te-
eTKFpc - ,-Joii.Vri Si> of MKTri 5f/|
>/$* yur-ip-
^tHS SuTP/fr Sounl Sa) SfTAKhToK - ftkH fan t;Je
Tii ir*>^ 1 cdHtTe>< Level t* utt'oiun4
CA.E t>ur/ft l`ti to yuFt p. 7*?ft R5 - StoTtf s; v of
r/t Serf Re PumF-
Q........__
Wr ,vJ Seevicf
_^oCKHFiAc*e6fflHAe^& fO/>H4f5
To rft*AsMirren
-tXaRS <SPMe level Asr
of MU A. CHAVaB TA<\K.
Of fieAdet yhavs GXAve !eei ft
staa&oA East of 5outA SAf Hgo pH Mp'
t
x*
a-. 4*
T/-/&ST ^ I T $05-*f0t- 'f&J ' <JOh\ PiZGjfoy.S
4 -/yt f
I'Ac- p'nHpe. ce/tt Ht-O SuPPtr
C,s'iot/iv'/i/'vr/ Y `ST#iOrYF ci\
/Cr
V/
4
jd/ /o/.ra* r/f%civiMrJ*7<^5G/?. ,S,
-Tffl?-_:-(.*) Wsr of 9os t^'esr of ^04
evlsT 4 wsr of 9<o^r SOHTI-)
>`-WD oK Cstsr S/}1 Hr o S.\CHAHtGR.
/ n TSFcoy frer YAtyf Tp
B/e>\*/ Oou/* TMRK Tf> ffFD
ETA'-> vv?(vr,
x
r-/'5-r y*f>ny rtoRTtit Couth
-X--
H 0 TAAV& RF-TJkc uMVYAA /- v i
OUT!, , , ,Hi 4 MflrWAf DKfl 1^1
//H.~3tSTf~AM Zi M.ff/HG Ea
chA *I C* C F. it tTe/
f yX ^
5k/, / <?-// Fo/( yrtc- F*ittii*s*,
t*Cii
l~r> //`W / ^ f ft r p 9J$
-- TRAPS -Of) Alt*RTti 4 SourH BHDs DP Sreei STH'Hr,UA, BxetfAHG&R BAST S'/? V7JPJ7.
a v TtertriKCv/AT/oJ F^hmh
Hti-ep> frj'Hxe.bHhAdHo&ff-yu. t-:-! sm
* * -- - - >
_v 7a ffasH ffap f,tJ~j id
tf.O'TH/JtvS Slfyir <5/ASSs,/v(r \ CoHrrois fPome&rjype -r*oAfPS5Mfct*jrPeH*st&HoeSfnrn^ei Snar eu*sH sfsreei I y
Utp AliTo, TM);J A F E
L',rlb F*btF
ofa'XTit t ScwrH
/s.p. nt4K5 ta ff9*> D*hul 7/vUTIMM /r
&wr* /tsrS:of
pe glen) Di*l 7*4*.
ISU DATE
STBA M S u FPIY
STcAm ~TRf\C SupM ibWf
Go/d TAG *//6>
\BJALSTocofaStoioubTit:l 7l^?TClce#uft
Ti
DESCRIPTION
CKD APD
CONOCO CHEMICALS
ABERDEEN T Foil id 5
MISSISSIPPI
NE\/ A/loT>u)f
steam
RtCOl/ERy
appd: date:
TO
fj -REA scale: T7J_AJI.0001
No.y0;D r6 nt,
6706
'.'tl : A- =*
4 ** * ._ V
. ' \ "'- i 9
1` :
1
1 -
t i.
ii
H
t!
.4
T^piceSuppIY ortuS
(So/PT/tG * //3 - LoCArt'ofJ AfoKrri I'rfl of -b/ou> douhI THAK,
fFpi___o_
6Rf\T>
n_____
TO Hit/H HtO t./itfrioKTtf <fW</ Of1 F/ou/ p/Jc/l TAM~*T<9 TToc6S3 CeolidG Hi * To nr.A M*re up r*/tK.
~~TRaT3 aIoKTH or ny.A. Mak up t#ak-
5"S?
Ifi PKaCtSS ft* SufF/f TO /tetTO- f/US/t
Oil B/0U1 Ovujti TAM T'KfitlsF'r- /J To
-TPf\pS - AT STOiiCipJ iourti (zpST oF Fs-rt- AfAAF Up 1AM-.
To $/t/ f^o !;4i to deg. rti /SmrP
FWUfHi*>p P4/<i4tIt|4lHTAOMaKJ T>5K7/ttTisFTATO/j;Ft*.
//ti TO p.w>. ?. ."R*pj-6iJ t>4 /tr SotrrA ujT Of&!ou> Uowtl TA<4K - Oiie Air SfT
OP TKAPS tt'n r~ */r tlf*., MOOulC Mcc
T*~ atr~ w/tP-
TO /Di`&cJa*-o of /J*TA 'B/eiti 1>OUrl 1f> il* T V*AjF*r Fuai? f M*tr oA iTOST TRA*SfK S.-tle To 'B.ui. 3.
FRFSSutZ TFAtlO HITU T>Otod TA4 X.
*1%
-TTCrtPS/Jr SfT of TRAPS Wsr of Atu> neVuif ncc.
u;,os *J*; tmt cast rftap.
-7it*p$ - S>outa Fast f*ie>
to ie/ei
Hi-neft-Jm/ ilotirPio. ffhSe* *,
ierei cotjrfioiSf g/zo Jitter To ur;/;rt s Vo d SCXSTT*
I - 40 PA &ic>ui -ppivii 77*/4*-
-- 7~R.AY&- SourH SAJT Ao OF ii/OiO z}0U>*J TA*tX,
i
TO T'fsr ~rr+tiSPfX- t. Af T- V,i. S,
iJTtAPj-lirser *Fnc*rs wftrFnn to Fast tka/1$f*. l;Ae f^om b//>u> d*<*j tam to kw.s,
Vitt> MWK, tltXrp *f f.,s, ' TfZ/tn AltPTii OF fiu> Mo&Hie CooIUa Toh/SFy idePTH TPa?, fAsr TRop>
TO i</oT / KAiFH. /'*i FPoH ti*tJ t3***J T7t*4C To T9.v>. s.
- 7~KAPi fJczr* oF aItv MpVUI S' C*otfJ A T* ****' *o*m VW.
/intro
^TAM SuFVtV- OtD MOUu if To TAclA 6K To? *
GolD TAQ m JSLh
G^o--t-d--- - " *
to South 7~Z*HsFFR //Je FFom b/oio
T4*jk To &.u..
--TRAPS- Z.* S&T OF i
WFSr Of Afw MPDulF HCC. 'BuiiViA^, wesr
To MofCrrt TFaAsFK /,Wf Fftoti
TFaPs ' t*F ST OF TTAPi U'TST A F E
OF*Ta!GshT>
MoPt/ir /ice.
TRAP-
BuOOtAA.
z&uttl 77tHK To ~B,U/. s.
(So/D 77)6 7^o
*
ISU DATE
DESCRIPTION
7"JPAB
Y |CK0
APU
Go/o T/z&s '/i`T4f*o
CONOCO CHEMICALS
LoC-ATloth fAST Of 0/0 McT>Utf
S/iMf Surety Sou-zee /?s ~ /& * /tee, <2.o' ftbc>vg- GZ/t T>e.
V/u6f S/460, &-
JLocRr/od - /^OfTtt of /4fu> Coo/;4$ To 'r/ Buffties ofF
ABERDEEN K Conids
MISSISSIPPI
NE\/ A1 ovaiE
l* STf/tM ittie T~o t4 c.fITFAToFS,
STEAK TR/lC' /Gi a/fpp. czo' Ahorf GxernT>.
Bhu/VoknlTflMK ftREfi scale:
136707
1
aped: date:
No
rto-^
4V> ~f~/
1. . . . . . . . . `J .id* i
1 i i - a -i- f i......... - ir
m,.
, *? i
*,* V'--- '
- -r?'{ ft 1
' '
' .
\ * v.
. -
` -
. '' ' -
' *;
vi
"
i'
fe
To &Jr Ji,p.c.n. CApfZ6,e J%<+tf>-
- tHaPJ *'jri>f ajr P,v,c.m-
&Me&e ?hp-
TTO "RCt>l': LAt /HOM Ji.i/.C.H
YftCKj To /i^o f-tle #1-
,UT.'iTTT SrjtTlotJ a/*?t** >f F-v.c.m. pr.'trfU
CV***/" 4 S*l ttzf> T+ JAM-
tt,
^ V c^ -r jt
i* -r
To luetr < M-
A
-TVfi?S 0GU>u> etrr&rf
to <5*5 r f hffST FIkc m. Cjtfi*G Vanes 4
mnrni, /r sprats,
At jo &ipr of a/fsr
$*t Jfa.** SupH y r*> sahs.
firf crtfKGepkHf^TViApj. Asr *T K&rwffY l;d Ffrorx /J*xth 4 Svurti
of f+-
f'/TeK Tf*cks4 To it****--m* Pack,
' " "Pane s'-ATiRSDAPIaS/J- TT?>Pf 5S&*)iAToSMT- ^PeStiT4 fiZFUFAtCcj*c. ~P*CKt
* <* - '-t
im
t-*
to perron of Fflsr
7<p BorrpM of Wzrr
ftlt.C M> ~tti Of <
1?C;*?
-h7te*r rpBt*e?j.pu> 'Ktcewt *rr re*p
B*TT5m op
y,c.M`'kc'nt*K, xaUT ftft r* 5/*aic.
'Tr/vps WSr ;&cr >T
fpesa Kt-n Kce;*>K,
H S;of of- tfcoveny area
H1 " h
si I
in I : *1`
To T)KAiti JtvJ^ FKotA
ast i u>$r
7^/jr
To
-TTe^ps.^r riAp
til*/
^4^ r if,*i. - m. i<; fn fi a* ^ u^^/r
C?ihp
UtfJT
KecfUMf-*
steam trrceSLt??^ Goi> tag *//7
L LoC/!Tio*Il St V SiO Of ttcoOer Y fifeA ~Pncxs.
AFE
r/> ur;l;rYsrtrioA
1 y> 4 4n> tfOT Co/d itto H4KFQF}{JjiA/ll*J /JMTfK
TO F'-y.jf. MKf up ta*k.
-- TRAPS - Ar 574C*o*l SOUTH OP p.M-P-
MOKf up
Top neop.
GO I DTAG *12.7
S reAn SuFP/y
/'OCrfTi Otl- Sou Tfi Si DE OF
KEC0V6W ARtA /VoPTH OF
FKC.M. FUTFR P#^KS, AFP3' ABOVE &FADZ
OATE
DESCRIPTION
CRD APD
CONOCO CHEMICALS
ABERDEEN K. com
MISSISSIPPI
AlEW M
STm T R/t C W6 TO VCft CHhRG E
WEMfVAMAKE-UPftOLi/lfS xAit;.vm
appd: date:
No.
6708
< *;.. *i
4. i -r i-
L . L *
' V: k.
* ,-.
.J
, . .
., : '.Jr ?-:. '- ' ..
Ii
-:-
. **I5JmT-*L :* # vta # * \i* *V k'i *., .
4* ^ .-/* "
-
j
^
'T''S''ti&a*A> #':*..
i
,.
.v. ';y
.<
tr
!;
i
>,
J r.
*
I U1
'U
ti** 4 *h '
*
E
* l/
I&
Ift v ttii'; ii*
i
1i
-i ! *-r if- -n; '*
4-|r
-
ISU DATE _______ DESCRIPTION
Y CKD APO
36709
I
^
2*
Electric/heat tracing locations for old module, new module, and dryer areas are included in the following pages.
VAB.0001136710
A
TRACING PANEL Located in Refrig. Bldg. 1st Fir.
Thermo.
Thermo
1. Thermostat Control for circuits 3 5 below.
#1
2. Calcium Sterate meter pump disch. lines, old mod.
3. Air lines to silos 685-680.
n
4. HPSW flush for fluid bed
#3
dryer centrifuge.
5. Air lines to silos 684-677.
n 6. Safety shower @ Blowers
for f. b. dryer.
7. Methocol OMS lines, CRD.
#4
8.
9. Methocol makeup pump suction disch. lines,
CRD.
#4
10.
11. Methocol Charge Line #4 12. to Rxs1, CRD.
13. Thermostat control for
#4
circuits 7, 9, 6 11 above.
14.
15. VCM lines from Recovery condensers to bottom of
RVCM tanks CRD.
#5
16.
17. VCM Charge Line CRD.
19. Light glass on vertical VCM tanks CRD.
#6
18.
+
20.
21.
22.
-4
23. 24.
25. 26.
i
27. 28.
29. 30.
53
VAB.0001136711
A
1. spare
HEAT TRACING PANEL #102
Located in New Module M C C Thermo. 2. Breathing air line top of condenser RX D-745.
Thermo. #9
3. Deltec Compressor 6 Drain Line.
5. Hydroquinone meter pump suction disch.
#12
4. Breathing Airline top of RX D-745.
#10
6. Safety showers for D-745, #11
7 Safety showers in New Module.
9. Spare
11. Spare
17. 18.
.19. 20
21. 22.
23. 24. 25. 26. 27. 28. 29. 30.
VAB.0001136712
t. J
HEAT TRACING PANEL #103
Located in D- 700 M C C
Therrao.
1. Methocel cTTarge line,
Old Mod.
#14
2. Control thermostat for circuits 4 8 below.
Thermo. #15
3. D 0 P Line to D600 RX. #13
4. RVCM collect tank lines. Old Mod.
#15
5. D 0 P Line to D500 RX. #13
7. D 0 P Line to D700 RX. #13
9.
Control thermostat for #13
circuits 3,5,7,11, 13 *
6. V-ll Fire Valve House
top walkway V-ll 17A.
#17
8. RVCM Line to storage tanks . #15
10.
11. D 0 P Line to D300 RX. #13
13. D 0 P Line to D400 RX. #13
15. Methocel Charge line. Old Mod.
#16
12. 14. 16.
17. 19. 21. 23. 25. 27. 29.
i
18. 20. 22. 24.
26. 28. 30.
55
j....................
h
-...............
lh-
VAB.0001136713
HEAT TRACING PANEL #10
Located in D-700 M C C
1
Thermo.
2 Safety showers. Old Mod
Thermo. #22 6 22A
3
4. Fresh air line to bottom
#23
of D-700.
5
7.
9.
11. RVCM vent lines, Old Mod
13.
15
17 Flame arrestor for incinerator.
19. Water from Cooling Tower 4 to incin.
21. WateT from Cooling Tower 4 to incin.
#19
#25 #27 #27
6. Safety shower on top of D-700.
#24
.8 Fresh air line at slurry
tanks 502 747.
#21
.10 Caustic tank eyewash
shower Old Mod.
#20
.12 Cooling Tower water line flow inst. for incinerator
#26-26A 26B
14. Inert vent Old Unit.
16, Spare
18. Inert vent line to incinerator.
20.
#18 #28
,22
23 24. 25 26. 27 28.
29 30.
56
VAB.0001136714
I--.i-
' : It
P"
XII. PERSONNEL POLICY DURING WINTER COVERAGE In the event hazardous weather conditions exist that would require implementing emergency measures to keep the plant in operation, the Company may require employees as necessary to stay at a local motel to ensure that they are able to report for their scheduled shifts. Should employees be required to stay at a motel the Company would pay for meals and lodging. Employees would not be compensated for time spent at the motel which is consistent with current wage and hour law requirements. Separate from the above, the Company may at its discretion offer lodging to employees who do not feel they can return home safely due to hazardous road conditions. The Company's offer in this situation would be optional to the employee. Employees who accept such an offer will do so with the understanding that they will not be entitled to any compensation while staying at the motel. Should it become necessary to call employees at the motel to have them report to work outside of their regular shifts they would be compensated according to the call-in pay procedure outlined in Article XII of our collective bargaining agreement.
VAB.0001136715