Document DGR38GyJ5JbappVGQpv06VZp5

H. W. Hilgers CoiMMUflllCCMOII From: Dote: Subject: D. C. Skokna January 25, 1993 Auamm mqwthly mows bspcks DECEMBER, 1992 There wee one recordable case reported In December. A yard operator received second degree bums to bis left hand. As of December 31, the plant's 85 days <104,112 enployee hours) since FTP PVC Production, MM Lbs. Stream Factor, Frine Ills.A * % Energy Use, (XU1, %) Fixed Cost Variance, Cost 43.5 94.3 96.6 1.0382 6.0 98.4 1.6 89.8 < 9,l> <19.2> 33.4 118.1 92.5 97.2 1.0384 18.6 97.6 4.8 82.3 <n.5> 46.8 <71.3> The December production is a record month for the plant, sur passleg the reco rd of 42.6 million pounds est in Noveaber, 1990 Orders for Line 1 and LI a 111 products ware down. Line V orders held steady. Line [ was down nine days for an overhaul of the "Banbury" compoun? er. All lines were down for the Christmas holidays. le due to good energy i material use in resin and near >lasticizer units. Fixed costs were unfavorable due to payroll costs being above budget due to the holidays and heavy vacations. Operating supplies and outside professional services were favorable and partially offset the payroll variance. VAB.0001188737 H. V. Hilger* 01/25/93 Aberdeen Monthly Progress Report - December, 1992 Fmge 2 OMP Excel, a potential compound customer, visited the plant on December 15. They requested us to complete their "Quality System Survey" by January 15. The Vinyl "A* shift recommended changes to hose trans fer stations to reduce resin cross-contamination and Improve safety. u*. m The Senior Process Engineer's Team found a potential $100,000 per pest cost saving* using eentrate water to proheat reactor charge water. The M08Q sent us s draft permit of SOD limits for our new HDPES permit Chet btcamet effective on February 1, 1993 of 21 ppm in the vinter end 12*5 ppm in the summer, phis is -an improvement Delineation ef the VCM plum began during the month. Conoco sent itS' cone penetrometer unit: end tame to do the neoeaaary shallow ground mater monitoring. 1A Water use minimiratIon meetings were held with all employees. The response wae vary good with significant water use reduction realized. Projects Operating procedures for the new water plant ara plate. Upon complotion, operator training will problem with the mater proof coating system mss was improperly applied. Ve are working with the to problem was noted; out In the settling ponds. does not Wo are working with consultant to correct this problem. design The plasticizer unit steam ejector relocation project was completed. * /"""V VAB.0001188738 * B. V. Hilgers 01/25/93 Aberdeen Monthly Progress Report - December, 1992 Page 3 Procedure writing Is In progress using two vinyl operators and one shift supervisor. Drafting standards were developed for P&ID development. D. C. Sfcokna Plant Superintendent rah A VAB.0001188739 i DISTRIBUTION Houston Austin LSCP Plant LCLAB Flsnt ialtfsftrf JSdBBHftQSQUdl Premiere Aberdeen J. R. Ball X H. V. Hllgers B. M. Hyers C. J. Hatson H. R. Flamer R. R. Smith B. J. Bean R. H. Gerlach C. R. Hiller L. R. Kardos M. J. Schneider X H. G. Coleman H. D. Garrison J. V. Ware X J. Friend X F. J. Kober X P. E. Markey X J. Favao P. L. Foote X X J. B. Autrey J. E. Beall X T. L. Cunnings J. M. Edvards X S. C. Hillman C, M. Harkerson D. A. Miller J. E. Nickerson X J. D. Olson R. W. Seymour (File Copy) T e r X X X X X X X X X X X X X X X X X X VAB.0001188740 SAFETY - C. M. Markerson/J. V. Uptain First Aid OSHA Recordable Total Injuries Nuaber of Restricted Workday Cases Number of Lost Workday Cases 0 1 1 0 0 Vinyl Operations Compound Operations Maintenance Race iving/Warehous e Office Totals Injuries bv Type Cuts and Abrasions Eye Injuries Bruises S trains/Spra ins Stings Other Totals 1 0 0 0 0 0 1 0 0 1 0 0 0 ft 1 Fiscal -Ip 1 2 1 0 1 0 1 2 2 0 0 -ft 5 Fiscal 2 0 0 2 3 0 0 -ft 5 2 0 1 0 2 0 Lost Workday Cases Days Lost 0 7 First Aid Cases Medical Treatment Cases Lost Workday Cases 0 03 0 10 0 00 Last lost time injury Days since Employee hours since - 10/7/92 85 104,112 On December 31, 1992, the employees of the Aberdeen plant completed 85 days with no lost time injury. A VAB.0001188741 SAFILTI - Continued Topics for the plant safety nestings during the month included: General Safety Hazards, Personal Protective Equipmentt and Lifting Safety. Eaergency Response and Fire Protection: * Fuel for fire pumps and emergency generators was winterized. * Seni annual inspection on fixed systems. - Inspection of all smoke detectors. - All fire extinguieiiers were inspected. * All alr*paks were Inspected. - All safety showers and eyewashes were Inspected. Routine dosimetry results for the nenth were: VCH Lead Total Particulates < PEL yftlllfrtT Parcant 55 100.0 6 100.0 1 100.0 > PRL Bsottua 0 0 0 0 0 0 Second degree burns of loft hand. # VAB.0001188742 B. B. Smith Excel Hanufacturing Inc. , a potential customer, visited the Aberdeen Plant on Deca-ber 15. Th.y requested that we complete their "Quality System Survey Report" by January 15. A Senior Process Engineer's natural team evaluated the potential cost savings of using eefitrate water to pre-heat reactor charge water. They estimated a potential cost sawings of $10QH/year. A Vinyl "A" Shift natural team recommended some modifications to a hose transfer station to Improve safety and reduce resin crosscontamination potential. h r VAB.0001188743 cnsr VARTAWCgs - D. G. Skokna Product Total PVC Flexible Coapound(l) Plasticizer Total $51.8 < 7.6> <$350.0> 100.8 <$257.0> <$298.2> 93.2 <$223.6> PVC Resin High production rates t a record 43.5MN pounds, resulted in favorable utility consumption and raw material/by* products were also favorable. Overall efficiencies were near budget. Overall efficiencies were near budget. m Resin to Compound m Electricity m PackagingSupplies m Initiators VCM m Others Total $104.3 29.1 < 19.0> < 19.9> < 323.3> < 28.2> <$257.0> Payroll and Benefits MM&C Miscellaneous TI&D Clearances Payroll and Benefits Variance - SM Total <$85.7> 0.5 75.5 < 1.1> < 8.4> <$19.2> Operating and maintenance payrolls were high due to holidays, heavy vacations, and some extended absences. M&C * This category was essentially at budget. VAB.0001188744 COST VAttTANCES - Continued Miscellaneous Outside Professional Services m Operating Supplies $23.7M $31.8M Taxes and Insurance This category was essentially at budget. The unfavorable variance is a result of minimal activity in the old pond area #2 cleanout project. VAB.0001188745 VXHYL - J. D. Olsonv V. S. Carroll Safety The Vinyl Department had no Injuries in December. The monthly safety meetings were held on shift. 1. December production was 43.5 MM pounds. Tills is an Aberdeen Plant resin production record surpassing the old record of 42.6 MM pounds set in November, 1950. J* 2. Rellear empty hoppers were in short supply near the end of December. This has resulted in significant reactor downtime in early January. fttridtmr 2X0 Production, MM lbs. Daily Rata, M Lbe./C.D. Capacity Utilisation Factor, % Total Reactor Charges Charges/C.D. Raactor Stream Factor, % Rotary Dryer Stream Factor (#4-#8), Fluid Sod Dryer Stream Factor, % Resin Quality, % Prime % 43.5 1403.2 104.3 1001.0 32.3 94.3 96.6 95.7 96.6 118.1 1283.7 95.4 2753.0 29.9 92.5 92.0 94.3 97.2 Hours m Operational downtime (recovery scheduling conflicts, cherge/rinse water conflicts, D-600 rupture disc/PSV change, Q.C. data delays, dump conflicts, and no hlarnd tank spaca). 291.0 Maintenance downtime (D-400 seal replacement, cooling water line old module, D-700 rinse line repair, D-700 seal replacement, 0-744 recovery valve maintenance, D-745 sprayhead, and D-743 gearbox PM). 134.0 VAB.0001188746 Continued m Operational downtime (centrifuge plugs, dryer cleaning, flameouts). Maintenance downtime (activator problems asbestos removal). Reactor limited Total % of 68.8 31.2 0.0 i i Reactors 400 and 700 seals felled and were rebuilt for spares. Reactor 400 seal failed due to line pluggage, and reactor 700 seal failed due to overpressurlsation. The #1 bird centrifuge was ro|m*talled. The Bird had been sent out for refurbishing after several months in service. m. The north fluid bed Bird gearbox was changed out due to a seal leak. Two major valves were changed out of the Vinyl unit. i m Two power supplies were replaced in the Vinyl control room after they were found to be faulty. M The Gaitronies units in the Old and New Units were repaired to enhance communications. I I m The test run on the propane system was conducted in preparation for winter alert. The valves on #8 and #9 air compressors were repaired. The west bio-disc bearing on the north end was replaced due to weal. i VAB.0001188747 m mmmmmmrnmm CQMPCHJHD - S. G. Hillman, J. B. Hegwood The Compound Department had no OSHA recordable Injuries during the month General Orders were down for the month on Line I and steady for the month. Production for the month was down pounds from last month. This decrease in production can V production held 10GK attributed to the downtisie associated with the Christmas holidays and the Line 1 maintenance downtime. The line 1 Banbury was shut down for nine days during the month due to e gear failure. A complete overhaul of the Banbury was performed due to the condition of the Banbury, Line I was started back up on January 9, 1992. Operating Line I Line ill 21 30 Line V 28 fetal % Prime Capacity Utilization Factor Line I - Product Chens#t - Miscellaneous Maintenance Line 111 Product Changes - Miscellaneous Maintenance Quality Line V Product Changes - Quality - Miscellaneous Maintenance - Raw Material 1338 3486 1173 5**7 98.40 80.32 hfiMSd 63 116 42 221 id 273 3 104 41 28 23 11 26 17 4939 10314 3182 18437 97.42 82.21 i VAB.0001188748 f nnupomm - Continued Operating Month Ato./Pit Plasticizer Capacity Utilization Factor 1552 89.75 84.55 55 4813 82.30 84.25 J 8. Autrey/S. A. Truitt The agitator blades sere replaced in plasticizer reactor #1 after the blades broke during a charge. A plugged regulator urns removed from the eater return line on the inert gas generator. The regulator was restricting water flow to the condenser, which resulted in water condensing into the compressor oil. m The #6 dicer motor had bad windings. A i VAB.0001188749 - J. K. Nickerson, T. &. Xtckay, R. H. Sneed, X. L. Carter i Bkfcnr Flenfc Operating procedures for the water plant are near completion. Final approval is expected within the next few weeks. Operator training will take place after the operating procedures are approved. Construction on the chemical feed system will begin in February, the boiler bid package was awarded te Nebraska.Boiler Company. The boiler design will be completed in January. Wasteweter test run conferencs sail was held with FED, A final report la expected from FED seen. Operator training ia almost senplate. Operator training will be finished in the first part of January. Relocation end startup of the ejectors for R1 and R2 were completed during December. The ejectors were relocated to provide eesy main tenance access. Additional goals of the project were to reduce noise from tho ejector exhaust and eliminate the slipping hazard caused by the liquid in the exhaust. All goals were met by the project. A miscellaneous capital project was submitted to install valves an the stema/weter lines to ejectors. These valves allow the ejectors to be "turned off" when vacuum is not required on the reactors. Justification ineludea $40M in amuital steam savings, reduced fouling in tho ejector secondary jets, and reduced process water use. A draft of the Aberdeen Plant CAD standards has been prepared by Project Associates. These GAD standards will be used in P&ID development required by OSHA Process Safety. A report was issued which highlights areas of potential water use reduction. Assignments were given for each item identified and the Water Use Minimization Team is working to inform all plant employees of the study and encourage their participation and help. Meetings were for all plant employees. r 4 VAB.0001188750 EHGIHEKRIMC - Contlnuod A test run has been performed on reactor R-l using both coils for heating and cooling. Preliminary results indicate a decrease in batch cycle tine of about two hours. The test run will be extended into January to collect more data. Construction has begun on the aeration project. Water samples of pond 3 inlet and effluent will be taken before project startup and after it is running. This will quantify benefits gained by the A chemical feed and automatic design is near complex tion. Work continues on identifying and quantifying blowdown fron each cooling tower. Several air modeling programs word ovaluated fog with Responsible Care goals and for future use in mooting clean air The SPILLS model was selected due to its and ability to handle the chemicals we use at this mation is being collected for s base case sample modsl A wmmmmmmmmm VAB.0001188751 ABERDEEN CHEMICAL PLANT M.L. CARTER DECEMBER REPORT Month 1st QtTf YTD ACTUAL 73.4 374*5 374.5 94.0 330.0 3435.0 lift - 20.6 <4* 44.5 -3360 5 ....%.... --21.9% +13.5% -49 .1% Actual : than in December ware November FY93. 6 K lower in the more the - Dec . 1 Fir were $44.5 M - Current Quarter Expenditure Forecast as submitted the current capital budget. budgets - Total of current and previous quarter approved - Total Expenditures for the Second Quarter FY93 are forecasted at $775 M while January expenditures forecasted at $130 H. VAB.0001188752 KHVIftOWMEHTAT. - I. G. Aldns Veter All wastewater discharge parameters were met for the month of December. A draft permit was received in December modifying the permit limitations that were to go into effect February 1, 1993. Vinter limits are 22 ppm BOD and summer limits are 12.5 ppm BOD. Hie dissolved oxygen limit was raised to 7 ppm. Horizontal delineation of the VCM plume in the shallow groundwater began in December. this work is expected to be completed in January. Waste Waste shipments during the month included: A bulk shipment of API Sludge to Laldlaw Environmental Services in Chattanooga, TV. VAB.0001188753 ENERGY CONSERVATION J. A. Bodron A Unadjuatcd BUI B. Admitted BUI C. BtuAb. ftoduct D. Total EnergyCootumptioo MMM Btu IL Boiler Operation Haul No. 2 Nfc.3 December 15192 (98%) (9.1%) 29249 150J8 Fiscal Y.T.D. (12.1%) (113%) 29705 4265 - -U 83.7% 829% 839% BOBciaosjr % fflWtf TiTr*> 835% 829% 83.1% 1 Mvt mn xahm tn.m ui m. mhn ivlm MONTH mmm mn mrr VAB.0001188754 * % A MMOMBK. - J. E. Beall None. Heme. Hone. Hone. R. Danny FI ippo - Vinyl Department - Union Leave of Abeence. Holli Harris - Engineering Department - Educational Leave of Absence. nwmvpMgj Ml VAB.0001188755 HAftSaOCISE I GENERAL PLANT 1 MMmmc* | laboratory COMPOUND VINYL PLASTICIZER I I 1 SUB TOTAL SALARIED 13 I 7 13 7 34 7 IS 3 30 22 31 10 5 12 145 59 78 6 0 53.8% 0 0 1 53.8% 0 0 20.6% 0 1 16.6% 5.5% 1 I 73.3% 1 3.3% 2 1 32.2% 6.5% 0 I 40% 0 4 41% 2.8% is 7.7% 23.1% VAB.0001188756 n\ FAMMUtt rd Mttl Mpcri TOTAL 0/T L, 15,575*75 r ira.oo TOTAL non ino.ro 10.75 Ultp I.NI.IS 1101*00 son.oo C* tab 10,454*40 anus nlMr* .N tabmaaa UrlH.79 1115.00 l.m.N 44.75 MlOMtOt tab 0,110.00 750*50 f liad f,110.10 450*50 VMl M.l*t.*S mh.i Rorl mm. n#R 1 --I-Y|-PP- '.' 'I-I- 7-T .N 0,41.00 |; , 1 V X 14^ .. I l 1 U^.H 1074*15 1 n,m*n htM kHm Puwitff 17, 1,01. 0*T. x or It 11.04 7*45 ! M. .Mfc 00UMT MU MQf ... 0MW ooo.ai 10*0.00 0*00 0.00 MUMP 9WM 1U.N 0.00 ( amki 1 t or im 1 t,Tf s o.oo tt.ii tt-H . t.u IS. Ml i.ao no.oo i fVwiM -i *7. 0.00 ' Mtt.M 08*0.00 ' 000*00 100.00 4WM* 0*0^00' ' U.15 1 itt.il *tt.n 1 I 1 1 '..J*s"L [ o.n **7t *.i* 0.40 t,*t t.7 I.H u.ti 11.10 *11*5# ' IM.tt i . Mt.M /l tt,n * 4. | '04.0.|0L N.tl ' 4000.00 owpw o-pno 1 . 1 0. 00 I .00 50.00 1*04.00 0004*15 1 *.* _.**. .^ : / r I m.ts S 1i 1*.? 1 WMt fM.M . ltt>Tf f ^' f .r 17M*.* .`.-.J*. 1 : lio.tt I > I s. . si 10.00 0.00 0.00 544.00 H.M ttttt 0.00 4.M 0*00 ' M.M m.M 0.00 li ' 1 i i' * h r 004^4# UfHHAL OOMW 0.00 0.00 0*00 00.00 004.00 0.00 0.00 0*00 0*00 100*00 100.00 ato.oo 4.00 I m**m PtATW n WMOX 00*00 0*00 04*00 UI.M 100.00 0.00 *1.00 0.00 0.00 10.00 400.00 UO.OO **,00 MSMSLm 0,00 0*04 0*00 054.00 400.00 H.M J 1*4. N 0.00 0.00 400*00 1454*00 7000.00 UH.tt 1 mm*m ^ TOTAL Alt. s or ft 1*40 VACATI0* 1500 0.00 0 14 1.54 11,014 5*00 4,400 1*45 014 1.40 1754 1.40 044 .11 11*0 0*01 1000 5.01 7000 14.41 401 11.00 1010 j 4101 / VAB.0001188757 i?, im. I > :....................^ , tm jm l ,ii tv* 1. . t*00 1 1 [ ** 1. * [ ***, i, 1 [ I.1N 1 1[ .1 1I l E *.* 1 B. O' ' 1 --fj [ .* [' it 0*00 0.00 *** I.N -* I.M i3i ,i Ml " MTIOtil tww | ; o.oo n*n n KMStY 9.00 uam-mx Kioitm 0.00 TOTAL A1S. x or ft/T 0.00 0*00 o.oo 0.00 0.00 0.90 1[ 0.00 1| 0.00 N.M 1 [ B.M j 1 I.H o* oo ri^ j . 9.00 j 1 . 00.00 0.00 1 ][ _ .. 0.00 0.00 1.00 .05 0.00 1.59 9.99 0.00 0.90 9.99 999.90 j [ 0*09 J I 0,99 1 o.oo I 9.M 1'- 1 ^ E .. I.M l|K ... -ii1. [ 1:j I:.. .J 0.00 .r K j(; .^*tt , i I M* " : I 419*09 hi-' 7.59 0.70 Ml i I t.M VACATION 100 110 700 204 00 100 40 m 990 000 50 [0* 9000 ] i t 4 * VAB.0OO1188758 i 4 I ACCOPTIBG - T. L. Caaalags There were no reportable safety instances this month. .' * The Accounting Natural Team met once in December for a safety meet ing and an audit. 07 *005 07-006 AFK/MRO Dlai<ount;a 07-005 AFE/lffiO LTL Month 176 126 542 YTD 638 452 1341 $405 $5 $2059 $2565 $26,90 A VAB.0001188759 J M. A. Swierc There were no reportable safety instances this month. All teams met in December to review progress on their projects. Natural Gas KTD $0 Processed Cost Savings Through Bid Process MRO/AFE Purchase Parts Purchase Orders Issued no Calm/(Loss! J* $0 FT93 $384.34 154 178 $6,486.60 517 520 Compound "A" Grade FLBKSX Compound Off-Grade (BC) Compound Off-Grade (H) Millscrap Dry Blend "A* Grade Dry Blend Offgrade Resin Type I Resin Type *BC* Vacuum Dust Total Packaged W/house 4,857,628 212,176 467618 167,395 120,694 430,931 87,092 1,429,450 100 7,978,473 Dec.*91 (Decrease) /Tfio.r^aee % 5,324,822 202,596 501,508* 160,2620* 67,073 253,694 45,423 1,583,200 100 8,270,193 467,194 < 9,580> 33,890 < 7,133> < 53,621> <177,237> < 41,669> 153,750 0 291,720 9.62 < 4.52> 7.25 < 4.26> <44.43> <41.13> <47.84> 10.76 0 <3f .97> 3.66 Compound MA" Grade Compound Offgrade Rigid "A" Grade Rigid Offgrade Resin Type I Resin Offgrade Total 2,080,528 0 212,552 0 10,268,050 13,458,930 1,194,146 0 172,700 0 15,671,627 19,015,723 (Decrease) % /Increase JBttgi <166,382> 0 < 39,852> 0 5,403,577 5,556,793 < 8.00> 0 <18.75> 0 52.63 40.04 41.29 * Includes PLENEX (BC) ** Includes PLENEX (H) VAB.0001188760 mm wmmmmm mmmm ABERDEEN CHEMICAL PLANT SNIPPING ANALYSIS DECEMBER 1992 'SHIPMENTS BY PRODUCTS- RESIN'BULK RESIN-PACKAGED FLEXIBLE COMPOUND-BULK FLEXIBLE COMPOUND-PACKAGED NEU BUSINESS RIGID COMPOUND'BULK RIGID COMPOUND-PACKAGED RIGID CGMPOUMD-PELLETS AUTOMOTIVE - BULK Atmuoirm - packaged PLASTICIZER TOTAL TOTAL MONTH SHIPMENTS 33,883,230 758,790 2,810,230 2,354,931 9,530 62,540 218,906 0 780,370 71,450 mooe 41,478,777 'Pi 12:09 PM 14-Jan-93 YTD SHIPMENTS 102,117,940 2,292,141 7,300,026 8,396,020 36,868 491,230 517,491 0 1,467,178 252,866 * * .* 4 * #-* 124,421,214 'SHIPMENTS BY MODE BULK: ******** DECEMBER* RESIN FLEXIBLE COMPOUND RIGID COMPOUND PLASTICIZER TOTAL OECtMRCn BASLCAR 185 17 0 3 205 CMMONRR'. SAMliiR 8 14 0 12 02 00 8 28 1i t TOTAL 207 29 2 3 141 YTD* RESIN FLEXIBLE IlOMFININD RIGID GQMfttJND PLASTICIZER TOTAL YTD PACKAGED: RESIN FLEXIBLE COMPOUND BIGIB COMPOUNO PLASTICIZER TOTAL DECB4KR 548 43 1 9 CtlPSNBI 4 14 4 0 22 37 59 0 28 08 02 *** 22 74 4 0 MO TMPC MPiMN a* ***** AtR/UPt ****** ****** 00 00 00 00 1 3 0 0 ********** ******* *;* * * * * -m m m m * * w B0 4 444 71 9 11 27 91 8 0 126 YTD* RESIB FLEXIBLE COMPOUND RIGID COMPOUND PLASTICIZER TOTAL YTD m'-mm + m* 6 40 7 0 + 13 ***** 76 260 10 i 2 348 1 0 0 0 0 0 0 0 0 0 0 4 6 0 0 .. ! to 86 306 17 2 411 CC: TLC,MAS,AEV,JRF N VAB.0001188761 * VAB.0001188762 ft LABORATORY - J. M. Edwards, J. &. Williams A. SafetY There were no safety incidents in the Laboratory during December. Sandy Joiner, David Hawks and Donna Parrish of Excel visited the Aberdeen Plant on December 16, 1992, to tour and audit the processes. The customer complained of high gel count In 52,000 remaining pounds of 5415 In their silo. were faxed to the customer. Closer in i spection of the resin showed it to be better than the competition's. 12/10 The customer complained of rough surface on the wire Jacket made with 38552 Natural compound. The bumps were caused bp 400-500 micron calcium carbonate crystals. This raw mate riel should be lees than 5 microns particle site. 12/22 i- The customer complained of white pellets mixed In with 48451 Black compound. Samples were never re ceived from the customer end all remaining boxes in inventory were inspected. The customer used the compound. 12/23 The customer complained of resin cross contamination In a 5385 railcar. Their torque rheometry testing of the resin showed a lower molecular weight contamination. The Aberdeen lab confirmed their suspi cion. Operations is working on the resolution. A VAB.0001188763 LABORATORY - Continued D. Product Waivers Issued There were no waivers for the month. E. RVCM of In-Process Samples The following is a summary of residual VCM results on inprocess samples. Rone of the reactor daily averages exceeded 400 ppm RVCM during the month of December, 1992. Reactor .^^r^porr Number of Samples Average RVCM, ppm 1001 64 60 0.372 51 0.331 The following is a summary of the residual VCM analysis of shipment samples for the month of December, 1992. JCvGisflBBSuE 5225 5265 5305 5325 5365 5395 5415 5416 5465 Debox Pond 0 116 117 0 61 12 63 0 0 16 0 0.141 0.147 0 0.207 0.026 0.059 0 0 0.420 0 4 Hardness Color Hard Particles Heat Stability Contamination Dicing Streamers Klscharge METS-1R Totals mmntt LUb. _i_ 12.5 14.5 -- 7.5 , -- -- ... - ---- 34.5 <0.21> <0.24> <0.12> <0.57> l.tgHnn M U>. m 4.5 56.5 27.0 4.5 6.3 8.4 4.5 3.2 7.5 124.4 <0.07> <0.94> <0.45> <0.07> <0.14> <0.14> <0.07> <0.05> <0-12> <2.07> 'I VAB.0001188764 SAMPLE SHIPMENTS DECEMBER 1992 A Ship Dale 12/07/92 12/10/92 12/16/92 12/18/92 12/28/92 12/28/92 Product 5416 5385 5265 5305 5385 5415 5465 5265 5305 Pond 5265 I COMPOUND Ship Date 12/02/92 12/03/92 12/03/92 12/03/92 12/03/92 12/07/92 12/09/92 12/10/92 ~N 12/11/92 12/16/92 12/29/92 Product 38561 BLK 58031 WC 328 58033 CB 50 801424A CL 606)5 BLK 568i|l NAT 57462 NAT 34642 NAT 811-53-A 34642 NAT 34431 NAT 48451 BLK Amount 100 lbs. 150 lbs. 50 lbs. 50 tbs. 50 lbs. 50 lbs. 50 lbs. 2 lbs. 2 lbs. 5 lbs. lOtbs. Amount 5 lbs. 700 lbs 3200 lbs 1500 lbs 50 lbs. 100 lbs. 100 lbs. 200 lbs 50 lbs. 200 lbs 50 lbs 50 lbs Customer BAERLOCHER GMBH VISTA Chemical Europe NALCO Chemical Ship Mode Airborne Airborne Airborne Keysor-Century Corp. Heritage Plastics OTEXCo. Airborne Airborne UPS Customer Connect All, Inc. FIberchem Inc. Tenex Corp Flexible Technologies ENTERPLAST Inc. Macklanburg-Duncan CENTRIUFT Berk-Tek FACOMEC S A (Columbia) Vista Chemical - Austin Brock Plastics Mode UPS CC CC CC Airborne Airborne UPS UPS Airborne UPS UPS VAB.0001188765 Resin Process Capabilities Bulk Density Inherent Viscosity (vs. 0.64 >0.67) (vs. 0.715-0.744) "L" Color 'a* Color "b" Color % on Pan (vs. 2% max.) % thru 140 Hard Particles, Average 5 minutes 7 minutes MET8IR (vs. 99% of Control) Average Particle Size, Microns (based on dryer "regulars") 5225 5255 5305 1.93 1.67 1.21 0.07 1.37 0.30 0.63 0.63 4.44 3.50 3.89 4.87 3.83 8.00 4.33 2.83 6.00 0.23 1.72 1.25 0.26 0.54 0.61 5385 2.30 1.24 3.67 2.00 2.67 1.72 16 3 December 1992 9395 1.10 0.96 5415 1.21 0.55 5416 11.00 0.57 3.08 6.17 12.33 2.17 5.33 14.17 0.88 3.78 2.78 0.44 0.61 3.21 0.77 b 13 6 3 621 5.52 5.55 3.18 132 132 141 152 140 171 132 IP W HUP VAB.0001.188766