Document 7MYe9r3YMe494Yx5pJ7D5Ow3B
T. H. Huffman
I lUVIft*
Date:
SutM.
D. C. Skokna May 25, 1990
ABERDEEN MONTHLY PROGRESS REPORT APRIL, 1990
There were five first aid and one recordable Injuries reported during April. The recordable case involved a Compound Operator who suffered a back sprain while charging the Line I blender. The annual insurance inspection was done on 4/24 and 4/25. At month's end, the Aberdeen plant's employees have worked 3952 days (5,250,925 manhours) since the last lost time injury.
PVC Production, MM Lbs. Reactor Stream Factor, % Resin Quality, % Prime VCM Efficiency, Lbs./Lb. Flexible Compound Production, MM Lbs. Flexible Compound Quality, % Prime Rigid Compound Production, MM Lbs. Rigid Compound Quality, % Prime Plasticizer Production, MM Lbs. Plasticizer Quality, % Prime Energy Use, (EUI, %) Fixed Cost Variance, $M Variable Cost Efficiency Variance, $M
April
40.0 93.2 98.1 0.99889
6.4 98.8
5.8 99.7
1.7 87.3 < 0.7> 173.8 87.5
Y.T.D.
259.8 87.3 96.9
1.0008 42.5 98.1 34.2 99.6 10.7 88.1
< 8.2> 309.7 535.3
*
Resin Flexible Compound Rigid Compound Plasticizer
109.4 81.6 98.6 77.1
100.5 77.7 81.5 72.6
A revised clean wall Injection system was tested on D745. A very slow buildup of contaminants occurred and the test was discon tinued. Based on our experience and EVC recommendations, a revised injection method with reactor vapor space cooling will be tested during May.
In the flexible compound unit, demand dropped slightly. Line V operated 18.5 days. PLENEX polymer trials were run on Line I for sixty-two hours. As part of the PLENEX polymers development, the Banbury rotors were modified co accept cooling water. PED con ducted a test run on Line V for rigid pellets.
VAB.0001190098
5/25/90 Abtrdetn Monthly Progress Report - April, 1990
r
Favorable raw material efficiencies in the resin and flexible compound units due primarily to lower than budgeted production of off-grade products, and favorable product mix variances in the resin and flexible compound units caused this month's overall favorable variance. These favorable variances were partially offset by an unfavorable product mix variance in the rigid compound unit. Off-grade production in the resin unit was fifty percent less than budget; and in the flexible compound unit, mill scrap was thirty-two percent below budget.
Fixed costs were favorable due to payroll being below budget and a favorable M. M. & C. variance due to less than budget activity. However, April's payroll costs were understated by $83M due to an error which will be corrected in May's fixed costs.
OMP
1. One hundred percent of the plant's natural teams met during April.
2. Prestolite (a flexible compound customer) performed an audit of our quality systems. We received a score of 77.8%, an improvement from last year's score of 69.7%. This put us into Prestolite's "Conforming Supplier" category.
3. Hi-Tech (a resin customer recently purchased by Southwire) visited the plant for a general informa tion exchange and tour.
4. The Newsletter Team published its first issue with an emphasis on people-related stories.
Doug Skokna Plant Superintendent
rah
\
i VAB.0001190099
Houston
J. D. Bums R. 7. Ferrell
I
T. H. Huffman C. J. Matson D. F. Harman
Austin
HflinmonH Blane Premiere
R. R. Smith
B. J. Bean
R. H. Gerlach
R. D. Gamblin
W. L. McClain
J. P. Stokes
R. L. Poe
X
H. J. Hall
H. D. Garrison
R. A. Conrad
J. Friend
J. V. Ware
X
L. R. Bauer
X
J. Pavao
X
C. R. Miller
P. L. Foote
RWS/DCS (File Copy), JEB, JME, SCH, MRK, JEL, DAM, RBN, JEN, JDO, REP, BLT
X X X X X X X X X X
X X X X
X X
A
*
VAB.0001190100
SAFETY - B. L. Trego
First Aid OSHA Recordable
Total Injuries Number of Restricted Workday Cases Number of Lost Workday Cases
Adi il
Fiscal
>
Fiscal YJ.D. 1989
5 12 10
1 Jk '
6 16 13
132 000
Vinyl Operations Compound Operations Maintenance Laboratory Receiving/Warehouse Office
Totals
00 35 39 01 00
6
2
3
6
1 0
Cuts and Abrasions Eye Injuries Burns Bruises S trains/Sprains Stings Other
Totals
35
3
0 10
13
4
12
2
112
02
0
-2 6 16
Jl
13
Lost Workday Cases Days Lost
03 0 84
2 42
Last lost time injury - 7/5/79
Days since -
3952
Employee hours since - 5,250,925
On April 30, 1990, the employees of the Aberdeen plant completed 3952 days with no lost time Injury.
Topics for the plant safety meetings during the month included First Aid Training and Contractor Safety.
An insurance inspection was held on April 24 and 25. Malcolm McMullen from
Houston accompanied the representatives of the insurance company on the inspection.
1
a
HMHM
mmmm
W P8M8
VAB.0001190101
A
SAFETY - Continued
Routine dosimetry results for the month wore:
Chemical
VCM Lead Total Particulates
Percent
79 100.0 20 100.0
8 100.0
0 0 0
Percent
0.0 0.0 0.0
Department-
FA RWC FA FA FA
Compound Compound Maintenance Compound Maintenance
Contusion to lower right leg.
Muscle strain to lower back.
Cut to right index finger.
Laceration to right middle finger.
First degree burn to lower back.
FA
Maintenance
Cut to right forearm.
A Compound Department employee pulled a back muscle picking up a fiftypound bag while charging a blender on Line I.
VAB.0001190102
April marked the first roith in which all plant natural teams met. The facilitator team continues to teach team techniques to each natural team as the teams work through their Initial projects. Several teams are meeting more than, once per month with .the ratio of the number of team meetings to the total number of teams being 1.13. The Newsletter Team began during the month with the first issue using the team approach published in early May. The format was changed to include more people-related stories. The team is com posed of employees from many areas of the plant. R. V. Seymour made three customer MBWA visits in April. Visits were to Southwlre in Carrollton, GA (4/5/90) with Mark Eramo; Nibco in Greensboro, GA (4/18/90) with Nick Forsa; and Gold Bond in Charlotte, NC (4/19/90) with Nick Forsa. All these visits were very positive. The discussion was focused on projects we have done and are doing in the plant to improve reliability of our operation and the quality of our products.
VAB.0001190103
D. C. Skoknt
-i
PVC Flexible Compound Rigid Compound Plasticizer
$101.2
19.9 ( 48.3)
$ 87.5
$100.4 124.8 107.7
$371.0
$201.6
144.7 59.4
$458.5
PVC -
Raw material consumption was $103.8M favorable, the product mix was $31.2M favorable, partially offset by an unfavorable $78.1M variance due to producing less than budgeted amounts of off-grade resin. Note: Off-grade resin production in April was 0.01855 lbs./lb. versus the budget of 0.03719 lbs./lb. - a 50% reduction!
Raw material use was $19.8M unfavorable, product mix was $29.3M favorable, and off-grade was $7.6M favorable. Millscrap production was 0.0098 lbs./lb. versus the 0.0145 budget - a 32% reduction!
- The overall variance was essentially all due to the product mix.
Favorable raw material efficiencies of $15.0M were the primary reason for the overall variance.
- Resin to Rigid Compound - Resin to Flexible Compound - Natural Gas - Alfol 610* Alcohols 610P to Flexible Compound - VCM - Other Price Variances
Total
102.0
70.8 64.6 33.7 24.6 15.2
$371.0
Payrolland Benefits - MM&C
- Miscellaneous - TI&D - Clearances
Total
$119.9 53.1
( 4.3) 5.1 O
$173.8
Continued
1
A?* $3M error was made (wc did not accrue one week of operating payroll) and a $37.1M favorable benefits variance were the reasons for the variance. The error will be corrected in May.
Lower than budgeted activity caused the favorable variance.
: Major variances in this category were:
* $47.1M unfavorable, The physicals budgeted for the second quarter cleared in April.
$26.OM favorable.
favorable the lab-vinvl team
see savings from the
VAB.0001190105
A
VINYL - J. D. Olson, J. M. Vlnoskl
Safety The Vinyl Department had no first aid or OSHA recordable injuries during the month of April. The monthly safety meeting topic was "Heart Attacks and Safety Attitudes".
1. A revised BUS-80 injection system was tested on D74S during the April 5305 resin run. A very slow buildup of contami nants occurred and the test was discontinued. Process engineering is investigating BUS-80 charge amounts and reactor vapor space cooling, and future tests are planned for May.
2. A test of a resin wetcake dewatering agent was conducted on 5305 resin this month. Initial results are good with a twenty percent overall reduction in centrifuge wetcake moisture content. Properties of the dried resin were normal. More complete test results are expected next month.
The resin raw aterials in the 744 account were valued at $300.2M.
- Production, MM Lbs. - Daily Rate, M Lbs./C.D. Capacity Utilization Factor, % - Total Reactor Charges - Charges/C.D. - Reactor Stream Factor, % Rotary Dryer Stream Factor (#4-#8), - Fluid Bed Dryer Stream Factor, % - Resin Quality, % Prime
%
April
40.0 1333.3
109.4 935.0
31.2 93.2 94.0 93.4 98.1
YTD
259.7 1225.0
100.5 6094.0
28.7 87.3 78.1 90.7 96.9
Operational downtime (recovery scheduling conflicts, New Module rinse/charge water conflicts, waiting for Q.C. data before charging, 0-ring leaks, no place to dump, rinsing chem wash tanks).
Hours 319.2
Maintenance downtime (D745 reactor hydroblasting and condenser drilling, D400 condenser drilling, 0745 agitator seal flush line repair, miscellaneous valve and instrument repairs).
172.5
VAB.0001190106
VINYL - Continued
Reactor Halted production.
Operational downtime (centrifuge plugs dryer cleaning, and flaaeouts).
Haintenance downtime (screw feeder repair, baghouse maintenance, screener repair, centrifuge repairs, shear pin replacement).
* <r*f
68.5 17.3
14.2
- J. B. Autrey, J. B. Hegwood
Reactors D300 and D400 were shut down for condenser inspection because of cooling control problems. A normal amount of soft residue was found on the shell side of both condensers. The condenser tubes on reactor D400 were drilled during this time.
Number 1 Bird centrifuge was shut down during the month for repairs. The bushings and bearings were replaced and the scroll was sent out for balancing. The centrifuge was rebuilt and put back in service. Representatives from the Bird manufacturer are scheduled to arrive at the plant next month to discuss our continuing problems with these centrifuges.
The boots on #7 Bird hopper were replaced due to their deteriorated condition.
The fluid bed dryer was shut down during the month for repairs to the fluid bed scrubber. The demister pads in the scrubber were changed out because of pluggage.
Reactor 0745 was shut down during the month for condenser drilling and hydroblasting as part of the contamination control program.
The west blower on the 282 transfer system was changed out during the month because of a bearing failure.
There were six major valves changed out in the reactor area during the month.
**
CQMPOtnm - j. e. Nickerson, K. 6. Akins
The Compound Department suffered three injuries in April. A restricted workday case was incurred when an Operator strained a back muscle while charging a blender. There were also two first aid cases in April. One Mill Operator received a small cut to her finger and another Mill Operator tripped on a step and skinned his knee.
The topic of the safety meeting was "First Aid Training".
Flexible compound demand eased slightly in April. Inventories rose from 6.86MM pounds to 7.27MM pounds during the month. Line V only operated 18.5 days this month due to pelletizer maintenance and lower orders. Line I dedicated sixty-two hours for PLENEX polymer testing and modifications to facilitate PLENEX polymer production. This month the Banbury rotors were modified to accept cooling water and work continued to modify the PLC logic to accept operator input for parameters particular to PLENEX production. PED conducted a test run on Line V to optimize twin screw configurations for rigid compound production.
Demand for rigid compound remained strong in April despite lower tolled volume. Production rates were limited during the month by mechanical problems with scales. Extra precautions were taken in finished product testing as well as equipment testing to minimize impact on the customer. The scale problems were eventually traced to a fatigued support beam that has since been replaced.
Operating
Month
Avg./Dav
Line I
30
Line III
30
Line V
18.5
Total
% Prime
Capacity Utilization Factor
2053
68
3666
122
656
6375
225
98.8
.816
Downtime
Hours
14053 23582
4839 42474
98.1 .777
- Product Changes - PLENEX Polymer Testing - Quality Problems & Control - Dicer Problems & Maintenance - Miscellaneous Maintenance
98 62 19
5
22
VAB.0001190108
COMPOUND - Continued
- Product Changes - Miscellaneous Maintenance - Quality Problems & Control
Hours
91 17 10
- Product Changes * Quality Problems & Control - Miscellaneous Maintenance - Startup/Shutdown - We lex Maintenance
Operating Month
Rigid Compound
30
% Prime
Capacity Utilization Factor
5812 99.7 .986
48 38 14
9 9
194
34081 99.6 .815
- Product Changes - Quality Problems 6i Control - Miscellaneous Maintenance - Scales Maintenance
60 58 30 17
Operating
Davs
Month
Avg. /Dav
Plasticizer
30
% Prime
Capacity Utilization Factor
1663 87.3 .771
10687
88.1
.726
J. B. Autrey, J. B. Hegwood
- The Line V Welex was shut down for repairs to its gate
during the month. The gate was removedt rebuilt and
realigned because of a sticking problem.
VAB.0001190109
COMPOPHD - Continued
- continued
The vacuun j removed for
xs on plasticizer reactor R-l and R-2 were cleaning because of a calcium carbonate
but ldup.
*
The compound cooling tower was shut down foi
to coupling"ha ft with
during
the
month. The
The shaft shaft was
^rinrrther^,,TMWaS Perfor"d * the -internee
The Topaz unit in the compound c down for repairs during the month. board was
The sy system
VAB.0001190110
macTmnaiTHQ . r. e. Polk, S. C. Hillman, M. R. Kano
*
Problems with low molecular weight resin due to wall scale
contamination recurred with the April trial o BUS-80 application
in 745 using the closed reactor addition system.
Based on
recommendations by EVC, modifications have been made to 745 reactor
jacket to allow cooling to the reactor vapor space all the time.
The cooler surface is supposed to improve resistance to wall scale.
The BUS-80 application began again on May 9.
Testing is being planned to evaluate alternative nozzles for better washing of the reactor walls as another way to address 5305/5265 contamination.
Plant testing of a Nalco dewatering agent on 5305 has been completed. Initial testing indicates a ten to fifteen percent reduction in wetcalce moisture can be achieved. Nalco representa tives are preparing a report on test results.
A meeting was held at the plant to review 5305 RVGM reduction
options for this winter and longer. Results were presented from
testing conducted through last winter by FED and plant engineering
to determine ways to meet American Mirrex Corporations * s 250 ppb VCM
requirement.
The Business Area, Marketing, PED, R&D, plant
engineering and operations were represented. One action step is to
have a project in the 4FQ90 capital budget to prepare for the coming
winter.
Low calcium resin was shipped to Klockner and American Mirrex for trial runs in film applications. American Mirrex was satisfied with the results and Klockner has reported that the resin is adequate for their thin film application. Orders for more trial shipments are anticipated.
A design was completed to add a small amount of cooling water to the reactor condenser thereby forcing steam stripping to continue for a longer period of time. RVCM levels are expected to be reduced by 40%.
VAB.0001190111
*1
oc
i
Ui
a
s!
13
8
A
a a?
8
U. cn
51
33
cn
at 25
cn
i cn 8
si >-*i* E*** C3
IS S
I
u. 5
*"* um
3 ST 8
cn
8 s!
cn
QB 3E CO p-
cn
3 1s!
sl|s8C
s iii 3 3 82 8 ccnn
Ii
UJ
&
I tI
cn
M- St cn
8 cn
A
8
8* uj 8
3 cn cV
i-- cn cn
isiilii
CS cn IS S S C UI UJ
cn
cr
s
si
ss3
.
cn I
s ~
ssU> H
% I ;3 cn A
38
B mm cn uj cn
ss
si si
cn
w
S cn
iU u
a M3 3 ccnn UJ A .I
cn
cn
8a!SS33 3388
UJ
si
a*
11
si
X*1|3=
!(> S m
x3 8 8 m
8mm 8 M|npl
2=
-- --
si
" G3 5 25 Eu 8si 3 *338 8a 8
a2 at
a s sss3ss sliiaisisisiisiSllisiliicn S
cn 0cn1 "*1 8 9 r * 8I--5S:
2
5 cn
cn *
8an SmT
3 A cn
A
13 n! * c!
srcsgcc s
e ww'tS-fet-*--1* A-- A-- A-- *-- - A-- **--"* A
82S------ p-3
83CiCS88S^i-ijj
3
AA3A
S
'mimiN M'S ` lKM T * - MM19I3
is g
S&
II IfII
X
i
i
I
|
3
mm
JJj
s
\ III 1 wiX
A
s! Ias
-
m
m
a
B
i
Sm nB Sr Vm lCilnSl ^
slssils iia88aa8
e -* " B * -*
8
8 s
2"
tSsias
_J A A UJ
a s ssSliSS
*T
Is *xiX $m
=}*M
S
3
II
II
a i & S ill ii ssI
aUJ I
3
c
c
^
a
A
cw St
IS
C
&
^ JC 3 3 Ri
as
VAB.0001190112
#w
HTHI*
fHp
F. 6. Jeanson
Vater
All wastewater discharge parameters were met for the month of April.
* V
The Mississippi Department of Environmental Quality (MDEQ) collected samples from our wastewater and storm water outfalls during March. Results from this audit were favorable. We were in full compliance.
I attended a water toxics course in preparation for applying for an updated NPDES permit which has to be submitted this summer.
Waste
Waste shipments for the month included:
- One bulk load of floor sweepings to Chemical Waste Management in Lake Charles, LA.
Worked on finding customers for vacuum/vent dust and pits #1 and #2.
Plasticizer filter cake was reapproved at CWM in Emelle, AL.
f
a
Permitting for the VCSM project and minor source status has reached another roadblock. The MDEQ is requiring us to redo modeling of VCM air emissions from the plant. The modeling study done in 1988 was unaccept able to them. A contractor was commissioned to redo the modeling with all the new UFA requirements. Emissions data was submitted to the contractor. In addition, building wake effects will have to be used on this modeling. A survey was completed measuring all buildings and vessels in the plant and the data was given to the contractor.
i
The contractor expects to have the modeling complete in mid-May. Once this is submitted to the State, they will issue a public notice. Thirty days later if there are no severe objections from the public, the State will review our permit. Hopefully, we will have a new operating permit as a minor source and a construction permit for VCSM by the end of June.
A meeting was held with Conoco to further discuss the five sites and cost allocation. Conoco Initiated a contractor to propose a plan for a thorough investigation of the sites.
meeting was also held with Sun Polymers to discuss pond #2 reclaii 11 visit their plant in Canada where they are currently reclaiming r BFG in May. There are 20MM pounds of PVC resin in pond #2.
We
mmrnmmmmtmmmm
VAB.0001190113
Continued
A
4
I visited HiTech Cable (Southwire) In StarkvlUe, MS, a resin custoner,
to help then apply for an air perait with the State.
!p'
We sold $11M worth of used equipment to Louisiana Chemical Equipment Company.
Environmental projects and costs for 1988 and 1989 were calculated as well
as an estimate for future environmental projects and the last five year environmental costs.
A day of environmental training for plant operations and engineering personnel was set up for Hay 18, 1990.
I visited Evans Cooperage in New Orleans, Louisiana drums. The plant is in need of another drum recycli current recycler have gone up dramatically.
Evans recycles empty since costs from the
VAB.0001190114
Apr-90
HASTE BEBUCTIQK IHSEX SHEET
MULL EUUMM 'TITIt IMIE MTB* HHr'nBbfQB flNBSs 8ECTCLE1/88LI 8A8IE
3 H0KTH 90 YT8 1989FY
ti.m 52.401 102.531
85.831 70.811 94.341
195.5a:
94.941
109.511
i. Qffsit*. Haiardous Hastts
49.341 100.091 100.4BX
a. Land Ban Hastos b. Haiardous Solids c. Non-Haiardous Trtatid as Hazardoss
80.891 89.401 35.851
34.341 88.101 104.481
244.741 111.191
93.77X
11. Rocyclod Haiardous Hasttf
71.541 45.501 103.511
III. Offfit*.* Nun-Hazardous Hast*
a. Rtc*vcltd b. Noo-tecv clcd
54.441 49.231 95.371
88.821 50.571
99.941 45.741
98.391 95.031
IV. VinarabU B*y- -Products V. Total Haste Hatar
109.101 101.491 111.301
185.921
.i 111.291
T. '
95.011
VI. Air 1 Hator
a. SAM - Air b. SAM - Hator c. Hos-SAM - Air d. Hos-SAM - HaUr
41.081 73.321 91.901
74.501 355.491 28.221 85.471
81.701
798.181
34.051 h
103.041
88.051
I ..
592.121
98.301
87.241
Apr-90
HASTE SESBCTIOK 1HSE1 SHEET
OVERALL EICUJBIA6 TOTAL HASTE HATER* 88H-8ESYCLEI HASTE RECTQJEO/SQLI HASTE
Offsite. Kazardeut iattn *
a. Land Ban Hattas b. Hazardaut Solids c. Haa-Hazardout Trtattd at Hazardout
19B8FY
7648138 3150255 4497B83
19S9FY
B056439 3044204 5012236
90 YTO
3817953 1297508 2520445
3 RaatH
1638973 433260 1205712
321409
329304 187116
41481
2412 79068 239930
6006 B946S 233833
510 40517 146090
510 18480 22491
II. Racvciad Hazardout Hasttt
III. Qfftita. Hoa-Hazardout Hast* a. Racvciad b. Haa-Rtevdad
*
653226
*
688080 248863
122178
2429430 2357718 978334 345919
247201 21B2229
247500
o
2110218
143699 834635
57404 288515
IV. Vanarafcla Bv-Prnduett *
3597456 4076656 2127884 1026131
V, Total Hast* Hatar
4424987560 4271245861 2864282394 1225351498
VI. Air 1 Hatar
a. SARA - Air b. SARA - Hatar c. Hoa-SARA - Air d. Hoa-SARA - Hatar
646617
604682 275756 103265
73316 55
264206 309040
65694 333
264290 274364
34841 257
55398 185260
14664 51
19493 69056
j
i
^
- `.'I
r
VAB.0001190116
April. 1990
to
A. Unadjusted UI
<0.6%>
B. Adjusted EUI
<0.7%>
C. BTU/Lb. Product
2451.0
D. Total Energy Consumption MMM BTU 132.00
< 7.9%> < 8.2%>
2649.0 917.89
A.
There were five energy related items completed in April, 1990. Three of these items were steam leak repairs. The remaining two were steam trap repairs.
No. 1 No. 2 No. 3
83.5%
(1)
82.9%
83.4% 83.3% 83.0%
(1) Boiler number two was not operated during the month.
h
VAB.0001190117
None
Gordon Ostrovski - Promoted to Storekeeper nAN from StorvkMpcr "B".
Robert D. Roberts - Transferred to Electrician MBH from General Mechanic "A".
Donald Whatley Compound U
Promoted to Compound Operator from
Charles Holcomb * Promoted to General Mechanic General Mechanic *m.
from
Freddie Franks - Promoted to General Mechanic "A" from General Mechanic "B".
Daniel E. Johnson - Promoted to Mechanical Engineer-- Aberdeen from Construction Engineer-GBD.
None
None
None
VAB.0001190118
* Vu?: ap-; *3
p t:
IV
StUritd hploym
Hourly Kaployaas Total Eaployaaa
76*
172
248
Varthornsa 16 Qan. Plant 13
ttm 41
Laboratory 24
40
Vinyl
33
Plastitisar 5
16
il
33
2
m l
M
Hubor of Applicant*:
J I'
Month
Tsar To Data
APFLZCAHT BB1AKD0HM:
# Minority
% Minority
# Faaala
% Faaala
Includes 1 Co-Op.
K1PQKI
MtBodtjr Idioms # t %
gf] h fd
6 66
82
38Z
Total
72 29Z
Hourly Mia. Hlrad % Mia. Hlrad
Hourly Kla. Tara % Xla. Tara
,-A*1 * ,.
xf .Nv
tfc.
a
kh
*' i
`l,,1a.
1
i-
.r
Hiraa
(Hourly)
To Data
Month
(Hourly) Taar To Data
Ovorall Turaovar _jQ Prolaatad Animal Turnoaar
\-K.
t* -
i:W-i^! r * sTrj
i AWi-
r
''ji
: ! . *fc(Sf&J: :-"p
i ? cij'ViL h s
1 if`V '>'
aK-I S"
I
-I t
T " ^
IP HU
mrnmmmmmmmmmmmmmmm
VAB.0001190119
m
KPWT 'UAL HOWS ANALYSIS REPORT
I t /DISTS. Aon list rhs, jfc, jvu, kpaathent heads, file 2/8? THRU 4/29/90
4 v -fc -7
3 m
k
o H
*W'. Hf ^ +. -
COOMO
4-- w ;V 1
1 'A
*
i-
,i . ri.
j?;- 1U-'-
U, 1 * T pi*
%. 'i:
VAB.OOOl 190120
IS
U
IS Itn
N
' "^7 +
I -i
h.-' <*
C - i.
DEPARTMENTAL HOURS ANALYSIS REPORT
DISTRIMTION LIST RHS, JFC, JVU, DEPARTMENT HEADS, F1L
4/ 2/9$ THRU 4/29/9$
CM
rI
i
is
-1
*I
h
isu
j I
ititt*o
I CM
I
ICI
O
CoT\\
i-4
$4
, *\
tIt OTO>
I I
i -.j
*MPM
^mrnmmmrnm
si VI
it
r
i
l;
T
VAB.0001190121
- *
*
J. E. Little
Safety There were no safety instances this month. Judy Frossard presented a video and literature on tornado safety. Ginny Balk presented first aid training for heart attacks.
Savings due to competitive bidding were $2589 for April, and $74,944 for FY1990.
Savings due to prompt payment discounts were $1258 for April, and $14,075 for FY1990.
Savings due to using excess materials (AFE and work order stores) were $2223 for April, and $16,529 for FY1990.
Slow moving and off-grade inventories are a continual concern. Slowmoving compounds increased 34% to 1429M pounds. Also, vent dust has increased to 140M pounds.
We are still working with Fred Williams regarding disposition of material.
Preparation for MMS conversion to VMS is in progress. Sharon Palmer is working on inventory cross-references to equipment. Lane Johnson and Gerald Burzynski were in Aberdeen 4/18/90 to discuss project tasks.
Representatives from Price Waterhouse were in Aberdeen April 24-26 to review/collect data for activity-based cost accounting.
Meetings
4/02
Pre-meeting on Prestolite audit.
4/Q5 4/09
Post-meeting on OASIS presentation (Houston - 3/27 and 3/28) ; attendees Fred Williams, Ted Nickerson, Linda Michels, Amy Bagwell, and Jack Little.
VMS - Hardware plan.
4/11
Mike Swierc and Charles Worlow met with Bill Arket
from Union Camp to discuss optimal box require ments .
VAB.0001190122
Continued
Meetings - continued
4/16
Mike Svierc met with Lynn Weed of ECC America, a calcium carbonate supplier.
4/17
Activity based cost accounting meeting.
4/18
Prestolite audit.
4/20
VMS meeting update with Bob Seymour and Doug Skokna on implementation plan.
4/23
Meeting with Administrative Services personnel to discuss the environmental policy.
We had four "Shadowing" participants visit our department during April.
i
VAB.0001190123
LABORATORY - j. H. Edwards, Jr.
*
pi
A. Safety - There was one safety incident in the Laboratory for April. A wasp somehow got under Eddie Smith's shirt sleeve stinging him which resulted In a. first aid case. The monthly safety meeting topic was first aid treatment for heart attacks taught by Ginny Belk.
B. Customer Contacts - There were four customer contacts during April.
1. ElPaso, a PVC division of Group Dekko, made a plant visit and tour of the lab.
2. Jim Edwards, accompanied by Eric Stouder and Eric Ingram, visited Twitchell in Dothan, Alabama. The performance of 5385 was discussed. A plant tour was also given.
3. HiTech made two plant visits. Larry Miley, an engineer with HiTech, made a plant visit April 17 to learn about the storage and containment of plasticizers. On April 27, people from Southwire and HiTech made a plant visit and tour of the lab. A Syntron contamination analyzer was presented to HiTech during this visit.
4. A quality audit was conducted by Prestolite. Jim Edwards, Richard Williams and Billy Paul Sizemore participated in answering questions and presenting lab procedures.
4/23 4/25
High moisture content was found in a
5415 truck shipment. Samples were
received from Athol and confirmed to
be 1.71 and 1.62 percent moisture
(0.3% maximum specification).
The
fluid bed dryer had made some high
moisture content 5415 at the time of
this shipment. A team Is being formed
to solve the problem of "special
handling" silos which should help
prevent known quality problem resin
from being shipped to sensitive
customers.
AT&T reported finding fiber contam ination in lot 30S03 of 34862 BGE 10 compound. This was the same type of contamination found in lot 39K04 which they complained about in February.
VAB.0001190124
TAifliUTOtY - Continued
continued
The source of the fiber contamination was determined to be from our geylord boxes and the method used by AT&T to dump the boxes into their system. Beth Vista and AT&T have action steps to resolve this problem now that the contamination source is known.
4/25
The customer rejected the railcar of
5385 because of the high number of
glassies larger than the 40 mesh.
5385 made in 700 and 745 has a high
glassy count and the vinyl plant
usually is able to segregate this
material from normal 5385.
This
segregation is not possible when the
plant is required to make four
products at the same time (like when
5395 is made).
Also, the rotary
dryers are not equipped with 44 mesh
screens to classify out the larger
glassies.
4/30
4/30
The customer reported finding "sand" in the RP-151 WHT 145 dry blend loaded in railcars. Tpd Nickerson visited the plant and samples of this "sand-like" materiel are in Austin being tested. Test results should be available the week of 5/14/90. No "sand" was found in the retain samples. The Investi gation continues.
Customer reports cold spots In the
melt which usually disappear when the
extruder temperature is Increased.
The compound, 48451 BIX lot 30S21, has
stability problems at the increased
temperature.
Alan Butler visited
Donnelly and samples of rejected
windows made from the suspect lot were
brought to the plant.
Donnelly
reports that the next lot, 30T08,
processed better but it is not known
why.
The Investigation continues.
Alan Butler has scheduled a trip to
Aberdeen on 5/15/90.
mmm
MfpMMMM
m
VAB.0001190125
laboratory . Continued
There were no requests for corrective action during the month of April.
Cus tomer Blane Dayton
Product 5395
RP-151 WHT 145
Reason Bulk Density Color
No. 1 R/C 1 R/C
A
The following is a summary of residual VGM results on inprocess samples. None of the reactor daily averages exceeded 400 ppm RVCM during the month of April, 1990.
Number of Samples Average RVGMf ppm
Reactor
Slurrigg
933 132
________Drier
5265
5305
33 0.345
54 0.367
The following is a summary of the residual VGM analysis of shipment samples for the month of April, 1990.
5265 5305 5385 5395 5415
Dry Blend Debox Pond
Bulk Density Inherent Viscosity
(vs. 0.715 - 0.744) L Color A Color B Color
51 57 58 5 51 57 4
0.101 o.m 0.709 0.083 0.028 0.083 0.304
7 1.226
(based on dryer "regulars")
5265
2101
5385
5395
5415
2.13 2.33
----
3.947 6.33 3.00
0.89 1.40 0.73 3.08 8.00 3.17
1.64 0.59
3.08
2.50
0.16 1.73
4.56
6.33
1.52 0.81
3.42
6.67
VAB.0001190126
LABORATORY - Continued
(based on dryer "regulars") - cont.
ms
% on Pan (vs. 2%, max.)
% thru 140 Mesh Drytime Mets I.R.
(vs. 95% of control) Hard Particles, (% > 10) Average particle site,
microns
1.43
--
0.72
-- -- -- --
133
5305
0.67
--
0.55
-- -- -- --
135
338$
1.43
----
2.31 2.33
-----
31.2
158
1392
1.14
--
1.50 2.33 2.61
--
0
145
5415
2.92 0.42 6.17 2.00 2.34 1.58 2.6
170
Hardness Color Hard Particles Contamination
Dicing Totals
M Lbs. Ill
26.0 --
-----
-- 26.0
<0.405> -- -- --
<0.40>
M Lbs. (%)
15.8 50.9 49.8 14.2
JLk*l
130.7
<0.24> <0.78> <0.77> <0.22> <0.22> <2.01>
Torque Rheome try Color
Total
3.3 <0.06> 7.9 <Q.14>
11.2 <0.20>
1. The raw netrials specifications book was brought up to date.
2. The Hunter colorimeter required two visits from the service nan to repair a memory loss problem in the colorimeter. The problem did not affect the measured color results.
3. Three Aberdeen High School seniors visited Vista in April to learn about the use of computers as part of the Shadow Program.
4. All six natural teams met once during the month. Half of them have picked problems to solve and the other half are close to choosing a project.
SAMPLE SHIPMENTS APRIL 1990
RESIN Ship Date 4/05/90
4/10/90
4/11/90
4/11/90 4/11/90 4/12/90 4/12/90 4/12/90 4/17/90 4/20/90 4/23/90
Product
5265 5305 5385 5415
5305 5385
5305 5385 5415
5415
5395
5415
5415
5385
5265
5305(Clean Wall)
5265
Amount
50 lbs. 50 lbs. 50 lbs. 50 lbs.
5 lbs. 5 lbs.
50 lbs. 50 lbs. 50 lbs.
50 lbs.
2250 lbs
2X50 lbs,
150 lbs.
1000 lbs.
200 lbs.
50 lbs.
100 lbs.
Customer CHISSO PETROCHEMICAL CORP.
CANADIAN GENERAL TOWER
Leon Plastics Inc.
Dupont Polymer Products Twitchell Company Vista - Austin RID Holm Industries LaGrange Molded Products VCE - BELGIUM CHISSO PETROCHEMICAL CORP. Kappus Plastics Co., Inc.
COMPOUND Ship Date 4/04/90 4/20/90 4/24/90
Product
38525 BLK
38525 BGE 10
150-6A NAT 160-6C NAT
Amount
250 lbs.
500 lbs.
50 lbs. 60 lbs.
Customer Marine Industrial Superior Cable Corp. Vista - Austin
#
VAB.0001190128
ABERDEEN CHEMICAL PLANT INJURIES
40
jrmw MAM J JASON UW M AM J JASON UTWBF M AM J J ASON MOP U A
a tom. MAMS
turn nfmnrwnir
4
1.
.1-.
%
.-i 4-
J
i
1
L/:
VAB.0001190129
ABERDEEN ENERGY CONSUMPTION
si/nue
VAB.0001190130
A