Document 6556Op0egegMap4KjE70X5k5m
\>
To: R. Do Gamblin
A
Interoffice
Communication
From: Dote:
Subject:
J. W. Ware April 18, 1985
ABERDEEN MONTHLY PROGRESS REPORT MARCH, 1985
Three first aid cases were reported in March. As of March 31, 1985, the plant had operated 2095 days without a lost time injury.
PVC resin production for March was 36.1MM pounds. Major downtime in the reactor area involved four agitator seal replacements, replacement of 745 condenser lid gasket, rewiring of 700 agitator motor, and drilling of 743 condenser tubes. Resin production year-to-date totaled 208.8MM pounds. The VCM efficiency for the month was 0.98268 pounds of VCM per pound of PVC versus the 1.00500 standard. Year-to-date VCM efficiency is 0.99985.
Compound production was 5.9MM pounds for March. This represents a new monthly production record for two-line operation. Year-to-date compound production totaled 23.8MM pounds. Major maintenance work accomplished during the month included repairs to the Banbury seals and FCM conveyor. Quality performance for flexible compounds was 1.4% off-grade of which 100% was due to mill scrap. "BC" production was 0.5%.
Dry blend production for March was 5.1MM pounds and 25.4MM pounds year-to-date. Dry blend production was limited by a shutdown to complete the Dry Blend Improvement Project and replacement of the #2 Welex bowl. Quality performance for the month was 99.89% customer grade.
The plasticizer unit operated 21 days during March to produce 1.3MM pounds. Year-to-date plasticizer production was 7.4MM pounds.
Total energy consumption for March was 121.822MMM BTUs. The energy consumption per pound of product was 2517 BTUs resulting in an adjusted CMA reduction of 53.8%.
The total plant variable cost variance for March was $411.0M favorable, resulting from an overall favorable price variance of $231.2M and a net favorable efficiency variance of $179.8M. VCM pricing contributed $80.1M to the favorable price variance. The total fixed cost variance for the month was $145.0M favorable.
J. W. Ware
VAB.0001184118
DISTRIBUTION HOUSTON
PONCA CITY
OKLAHOMA CITY LAKE CHARLES VCH PLANT LAKE CHARLES CHEMICAL PLANT BALTIMORE HAMMOND ABERDEEN
- J. D. BURNS - R. E. LEHMKUHL - R. D. GAMBLIN - J. J. LANGFORD - R. E. SWANTKOWSKI - G. G. DRAPER - D, F, HARMAN - H. R. FLAMMER - E. L. KIESCHNICK - S. K. SABORSKY - K. J. EGGERS
- D. H. SANDERS - S. E. MCGUIRE - R. L. POE - H. J. HALL - C. M. STARKS
- HARRY GARRISON
4
- DICK CONRAD
- R. T. FERRELL (COVER LETTER ONLY)
- J. A. DEBERNARDI (COVER LETTER AND SAFETY PORTION)
- T. H. HUFFMAN
- J. B. MAHER (SAFETY PORTION ONLY)
- JF, JWW, DWH, PJK, CRS, RAF, AHS, JRW, WFH, RAM, REP, VEM, VLT, CWT
h VAB.0001184119
SAFETY - A. H. Sather
Occupational Injuries
Month
First Aid OSHA Recordable
Total Injuries Number of Restricted Workday Cases
(RWC Rate) Number of Lost Workday Cases
(LWC Rate)
3 0 3 0 (0) 0 (0)
Injuries by Department
Vinyl Operations Compound Operations Maintenance Laboratory Receivlng/Warehouse Office
1 1 0 0 0 1
Fiscal Y.T.D. 1985
14 3
17 1
(0.83) 0
(0)
4 2 8 1 0 2
Calendar Y.T.D 1984
7 0 7 0 (0) 0 (0)
\
1 1 5 1 0 0
Cuts and Abrasions Eye Burns Bruises Strains/Sprains Stings Other
16 12 03 02 04 11 01
Non-Occupational Injuries
Lost Workday Cases Days Lost
08 7 251
Safety Record
Last lost time injury 7/5/79 Days since - 2095 Manhours since - 2,661,272
4 0 1 0 1 1 0
0 0
Safety meetings for the reporting period were conducted on the following
topics: 1985 Safety Program Planning, film "Gas Under Pressure"; Pro cedures for Working on Reactor Condenser; Chemical Handling-Material Safety Data Sheet video tape. Vinyl Job Safety Reviews; and Trackmobile Operations.
'y
*
A
VAB.0001184120
SAFETY - Continued
Fire Protection
Number four fire pump engine was taken off line for overhaul
Safety Action Requests (ESARS)
Y.T.D. Total Submitted
Current Year ESARs Completed
Total Previous Year's ESARs C leted
1984 1985
55 3
46 1
20 3
Health
Chemical
VCM Lead Total Particulates
4 Number
87
6
5
PEL Percent
100.0
85.7
100.0
dosimetry as noted below
> PEL
Numb er Percent
0 0.0
1 14.3
0 0.0
No VCM overexposures occurred during the reporting period, One lead overexposure occurred to a Line I Compound (Mill) Operator, This Job normally requires no respiratory protection. The operator wore a 3M dust mask during the sampling period.
VAB.0001184121
VINYL - D. W. Hollis/M. L. Nathan
Safety
The Vinyl and Yard Departments operated with one first aid type injury in March. The injury Involved a puncture wound from a frayed wire on a section of flexible conduit.
Shift safety meeting topic for the month was "Job Safety Analysis". Operators on each shift presented a step-by-step description of one part of their job including safety aspects.
Production
March Y.T.D. (Fiscal
1. Production, MM Lbs. 2. Daily Production Rate, M Lbs./C.D. 3. Total Charges 4. Charges, Reactor Batches/C.D. 5. Reactor Stream Factor 6. Dryer Rate, Average Lbs./Hr. 7. Dryer Stream Factor 8. Accounting Days
36.1 1163.3
907.0 29.3 93.1
8906.5 68.0 31.0
208.8 1147.5 5077.0
27.9 90.8 10315.1 59.1 182.0
Vinyl Department production for March was 36.0MM pounds which was 101% of the Business Area's targeted production level of 35.8MM pounds.
Reactors
The reactor stream factor was 93.1%. Downtime in the reactor area occurred as follows:
1) Operational Downtime: Accounted for 54.4% of the total downtime and was due to reactor scheduling conflicts and processing caustic con taminated VCM.
2) Maintenance Service Downtime: Accounted for 1.9% of the total down time and was due to cleaning reactor AMS injection ports.
3) Maintenance Repair/Revision Downtime: Accounted for 43.7% of the total downtime and was due to two reactor valve changeouts, agitator seal replacements on 500, 700, 741, and 743 reactors, 745 condenser lid gasket replacement, 700 agitator motor rewiring and drilling/ brushing of 743 condenser.
The dryer strea ) i factor was 68.0%. Downtime in the dryer area occurred as follows:
1) Reactor Limited Production: Accounted for 84% of the total down time. Dryers were shut down when possible for energy conservation purposes.
2) Operational Downtime: Accounted for 11.8% of the total downtime and was due to centrifuge plugging, burner flameouts, dryer clean ing, and transfer activator problems.
VINYL - Continued
Dryers - continued
3) Maintenance Repair/Revision Downtime: Accounted for 4.2% of the total downtime and was due to activator, centrifuge and screener repairs.
Product Quality Summa
Resin Type
Prime
mBC"
% of Total
*H Production
5265 5305 5385 5425 5465 Sifter Overflow Pond Resin
2,519,128 5,314,227 18,225,940 7,859,819 1,867,310
-
84,350 6,750
_________
28,284 428,460
6.9 14.9 50.2
21.6
5.1
0.1 1.2
Total
35,786,424
91,100
456,744
100.0
Quality performance for March was 98.5% customer grade with 0.2% "BC" production and 1.3% "H" grade.
A total of five railcars were shipped as "BM grade during the month which represented 3.5% of the 144 total resin hopper cars shipped.
Load Date Ship Date Car No.
Customer
Product
Reason
1/28/85
3/18/85 PTLX 41606 Vulcan
Resifted Sifter Overflow
Quality
2/8/85 2/13/85
3/18/85 PLCX 42374 3/28/85 PLCX 43706
Vulcan
Extrusion Techn.
Resifted Sifter
Overflow
A
Resifted Sifter Overflow
Quality Quality
2/12/85
3/29/85 PLCX 42666 Vulcan
Resifted Sifter Overflow
Quality
3/01/85
3/31/85 PTLX 41646 Silverline
5385
Particle Size
The Vinyl area received eight short lead time emergency type orders comprising 3.4% of the 237 Aberdeen resin shipments in March.
Monthly Variable Cost Performance
Variable costs for the month were favorable $266.3M with $154.4M due to price and $111.9M due to efficiency. Resin variable cost for the month was 20.139 <?/lb. versus the budgeted 20.887 $/lb.
The $154.4M favorable price variance was primarily attributed to lower than budgeted pricing for VCM, $80.1M; VCM freight, $29.4M; Lupersol 223 initiator, $19.2M; and utilities, $19.9M.
VINYL - Continued Monthly Variable Cost Performance - continued The $111.9M favorable efficiency variance can be attributed to lower than budgeted VCM efficiency, $141.2M and lower than budgeted usage in the utilities area, $29.9M. VCM efficiency for the month was 0.98268 lbs. VCM/lb. PVC versus the budgeted 1.00500 lbs. VCM/lb. PVC. Year-to-date VCM efficiency is 0.99985. Year-to-date variable cost efficiency variances in the Vinyl Department totaled $417.3M favorable. Ener Performance/Progress
consumption for the month totaled 2517 BTU/lb
.2 A total of thirty-nine steam leaks and twenty-two steam
repaired during the month. General 1. Packaging for the month totaled 336,024 pounds. 2. Resin raw material in the 0744 account totaled $163.4M at month end.
VAB.0001184124
COMPOUND - P. J. Kober
Compound Production
Month
#'s/Day
i
Y.T.D. (fiscal 1985)
Line I, M Pounds Line III, M Pounds Total, M Pounds Accounting Days
1908 3998 5906
31
64 129
8470 15290 23760
182
Line I operated 30 days during March at an average rate of 64M pounds per day. Major items affecting production efficiency were product changes 41.5 hours, Banbury housekeeping 32.5 hours, Banbury seal maintenance 31.5 hours, chiller repairs and delays 10.75 hours and lube oil system problems 6 hours. Three experimental products were produced in March, 1985; 0113-60 a reformulated version of 48562, 3934-130B a reformulation of 17461, and 0113-55 a formula designed for Precision Trim.
Line III operated 31 days during March at an average rate of 129M pounds per day. Line III production was hindered by product changes 53 hours, FCM conveyor problems 16 hours, orifice gate/hot oil system repairs 6 hours and mill oil pump maintenance 5 hours. One experimental product was produced for General Cable, V6003. The line ran well during the month. Quality performance for flexible compounds was 1.403% off-grade of which 100% was due to mill scrap. "BC" production was 0.5%.
The raw material requirement for flexible compounds was 1.00334 pounds of raw material per pound of compound versus a 1.01203 standard. (Y.T.D. is 1.01036).
The variable cost variance for compound was $6.8M unfavorable. The variance due to product mix was $11.0M unfavorable. The only significant raw material efficiency variance was 610F at $13.9M favorable. Total compound inventory decreased 0.3MM pounds to 6.9MM pounds. The 5.9MM pounds produced in March was a two-line total production record.
Dry Blend
Production, M Pounds Accounting Days
Month
5078 31
s/Day
195 -
Y.T.D. (fiscal 1985)
25429 182
Dry blend operated 26 days during March at an average rate of 195M pounds per day. Production included 80273G, 80174, 90171, 90172B, 90172C, RP-200T, XTRALIFE, RP-200 and 5426-129B. Dry blend production was hindered by shutdown for installation of Dry Blend Improvement Project 123 hours, replacement of #2 Welex bowl 75 hours, product changes 40 hours and Q.C. delays 21 hours. Quality performance for the month was 99.89% customer grade.
The raw material requirement for dry blend was 1.00374 pounds of raw
material per pound of dry blend versus a standard 1.00492. (Y.T.D. is 1.00372.)
COMPOUND - Continued
Dry Blend - continued
The variable cost variance for dry blend was $72.1M favorable with $4.2M
due to price and $67.9M due to efficiency. The efficiency variance due to product mix was $65.5M favorable. There were no major raw material efficiency variances.
The Dry Blend Improvement Project was completed on schedule and the unit was started up with minimal problems and Impact on customers.
Plasticizer
Month
s/Day
Y.T.D. (Fiscal 1985)
Production, M Pounds Accounting Days
1312 31
62 -
7,442 182
Plasticizer operated 21 days during March at an average rate of 62M pounds per day. Production included 610P, 810P and 108P.
The raw material requirement for plasticizer was 1.14948 pounds of raw
materials per pound of plasticizer versus a 1.10313 standard. (Y.T.D. is 1.09051).
The variable cost variance for plasticizer was $79.3M favorable
resulting from a favorable price variance of $83.7M and an unfavorable efficiency variance of $4.4M. Major price variances were Phthalic Anhydride at $51.1M favorable and Alfol 610 Alcohol at $23.7M favorable. There were no major efficiency variances. The variance due to product mix was $8.1M favorable.
Compound Dry Blend Plasticizer
Actual
1778.6 715.9
1541.1
Standard
1927.3 760.0
1642.1
A
VAB.0001184126
ft
MAINTENANCE - C. R. Snowden
Vinyl
Reactors
There were four reactor seal failures in this period. Two were in the new module (741 and 743 reactors) and two were in the old module (D-500 and D-700 reactors) The 743 reactor condenser was drilled and brushed and the jackets welded on 741 and 743 reactors. The condenser lid gasket was changed twice on the 745 reactor to eliminate leaks. The seal oil pumps were also replaced in the 600 and 700 dura-seal units.
Pump8 and Compressors
There were three seal failures to pumps In the vinyl areas in this period.
In the new module, both slurry dump tank pump seals were replaced and in the old module the seal was replaced in the south seal water pump. Two 407 blend tank pumps were repacked. One Corken compressor was changed out and rebuilt to control packing leaks.
Major Valves
Two major valves were replaced - a four-inch rinse and a six-inch slurry valve.
Projects
In the new module, the bases were rebuilt and the tank level alarms relocated on both dura-seal units. Piping revisions were made to improve safety when recovering and steaming fresh VCM filters.
A new sample platform was Installed to collect resin samples from the reactor dump line.
Other vinyl projects were to install 27 orifice plates in the blend tank aeration lines, install bleeder valves on resin transfer lines, strip down and clean the centrate heat exchanger and Install crank case vents on the Corken compressors.
Instrument and Electrical
Major work performed during this period was the repair or replacement of motors on the following equipment:
- Old unit south seal water pump - South Kason motor (fluid bed) - Hydroquinone pump - NaOH addition pump - D500/600 cooling tower fan
The 5KV wiring to the D-700 agitator motor was replaced.
Is.
VAB.0001184127
n
MAINTENANCE - Continued
Compound. Pry Blend, Plasticizer. Silo Storage
Compound Units I and III - Major repairs completed on compound Line I were to install built-up seals in the Banbury unit and replace sheaves on the skip hoist. Repairs on Line III were to change the FCM conveyor belt twice and to make repairs for process leaks.
The compound cooling tower fan gearbox was overhauled.
In the dry blend unit, seals were replaced in the #2 Welex unit and the outlet section of the intensive cooler was covered with stainless steel cladding due to mechanical wear. Modifications were completed on the Gump screeners for improved mechanical integrity.
Repairs in the plasticizer unit were to change the R-2 reactor seals and to change safety discs on R-3.
A new pump, motor and base were installed on the south catch tank. Repairs in the silo and storage area were to rebuild the feeder valve on the 282 silo and to install a new pump, motor and base at the 108F tank.
Instrument and Electrical
Construction and startup assistance were provided to support the Dry Blend Improvement Project. A remote alarm for Deltech air dryer failure was installed in the boiler house and the east Joy air compressor controller was repaired.
Utilities and Services
The #3 B.F.W. pump was pulled for overhaul and a new mechanical seal Installed.
A
VAB.0001184128
MECHANICAL ENGINEERING - R. E. Polk
Design
Design is in progress on the following projects:
- Old Module Rinse Meter - Line I Modernization - Rotary Dryer Optimization - Deluge System Revisions - Warehouse Lighting Revisions - Centrate Tank Exhauster - Vessel Entry Documentation
AFE Activity
a
Normal Kill Solution Addition System - K. S. Allen
Initial project checkout was made for the old reactor module. A modified "liquid-full" method of charging the kill solution was developed and approved. Checkout for the new reactor module will be complete by the end of May. Commission of the system will follow the checkout.
Line I Modernization - K. S. Allen/S. K. Glanchandanl
The Banbury rebuild estimate has been completed and issued to GED. The pre-shutdown tle-ln list has been reviewed and a preliminary outage plan approved. The plant will be responsible for all pre shutdown tie-ins except the plasticizer lines. These will be made by the piping contractor once he has moved on site. A project status meeting was held with GED and plant personnel. The proposed shutdown schedule, revised estimate, equipment storage and plasticizer charging system were reviewed.
Centrate Heat Tank Exhaust Fan - K. S. Allen
Bids have been received and contracts awarded. Construction is scheduled for completion in April.
Dry Blend Improvements Phase II - J. L. White/S. K. Gianchandani
Construction is complete and the system is operational. Agreements with Conoco to modify Orbitran software for the TiO addition system proved to be unacceptable. MIT Services of San Diego has been con tacted to determine if they can modify the Orbitran program. A quo tation is expected by the end of April.
Automatic Bagger Air Compressor - K. S. Allen
Construction is complete except for punchlist items. The system will be operational by the end of April.
MECHANICAL ENGINEERING - Continued
AFE Activity - continued
Ring Seal Water Filter Replacement - J. L. White
A contract for installation of the new filters has been awarded. Completion of the system is scheduled for mid-May.
- J. L. White
Insulation work on dryers 4, 5# and 6 is complete. Fabrication of
the hopper for dryer #4 is complete and is being Teflon coated at
Pfaudler/Eldon. Hoppers and the screw conveyor for #6 dryer have
been placed on order with delivery expected within ten weeks. A shutdown for #4 dryer is planned for mid-April.
Plasticizer Catch Tank Pump - K. S. Allen
Funds were approved to replace the canned pump for the north catch tank. A centrifugal replacement was placed on order and expected to be delivered in April.
~ "^visions - K. S. Allen
Materials have been ordered to revise the conveying system on Line III in order to provide improved performance for low fusion delay material. Completion is planned for the end of April.
Catalyst Freezer Alarms - S. K. Gianchandani
Construction is complete and the system operational.
*
Air Dryer Power Failure Alarm - S. K. Gianchandani
Construction is complete and the system operational.
Heat Tracing Revisions - J. L. White
Installation of remaining pilot lights is complete. The original scope of work is complete and operational.
February, 1965 Actual Accounting
. + r.
ABERDEEN AIHH0RIZATICN5 REPORT
ALTTH. NO.
CAPITAL DESCRIPTION
DATE APPROVED
AUIH. AFE AMT.
9630 9730 9740 9760 9770 9591 9651 9661 9731 9751 9771 9791 9851 R5E2 D5H2 B5K2 A5L2 A5M2 A5N2 D5B3 B5D3 D5E3 D5H3 H5K3 C5G3 A5L3 D5M3 D5P3 G5N3 A5Q3 C5R3 H5A4 G5B4 H5G4 H5F4
H5E4
Water Stripping
04/03/80
Qqp. line 111 Debottlenecking 10/16/80
Mod. To Hake Profile D.B.
10/27/80
Bnergency AMS Kill System
11/15/80
Reactor Pressure Relief Mod.
11/25/80
Sifter Overflow Reclaim Sys.
03/20/81
Safety Equipment
06/06/81
Waste Water Treatment Rev.
06/19/81
Normal Kill Solution Addn. Sys. 09/01/81
Fire Protection Phase IV
10/07/81
Recovery System Revisions
10/21/BI
Compound line 1 Modernization 11/24/81
VCM Pump Pressure Relief
12/09/81
Plast. Area Cand. Col lection 05/Q5/B2
Bulk Storage & Handling of CIA 09/29/82
Energy Mon. Instrumentation
11/22/82
Plast. ModernizatlonrPhase 1
12/14/82
Dry Blend Improvements
12/16/82
Improved Dry Blend Screening
12/16/82
Safety Shower Revisions
03/08/83
Recovery System Revisions
06/06/83
Vinyl Reactor Interlock Rev.
04/22/83
V-ll Roof Replacement
05/18/83
Dryer Centrifuge Conveyor Assy. 06/16/83
Instilment Air Dryer
06/02/83
Plasticizer Modenxizatlon-Ph II 09/28/83
Remote Operating Valves & Inst. 10/07/83
1AM Exposure Reduction
12/02/83
Imp. Ccnpliance With EPA VCM Std 11/30/83 Dry Blend IoprOTements--Phase II 12/08/83
Bulk Storage & Handling of AMS 12/08/83
Miscellaneous AFE
01/26/84
Plant Seuer Revisions
01/26/84
Miscellaneous AFE
Fluid Bed Dryer Heating
06/06/84
Panle Bundles
05/18/84
Dryer Centr ^e Conveyor
Assenblik^
03/20/84
810,000 1,350,000
200,000 335,000 560,000 200,000 106,000 560,000
93,000 160,000 402,000 1,800,000 58,000 55,000 160,000 80,000 240,000 41,000 74,000 50,000 147,000 44,000 221,000 47,000 90,000 20,000 130,000 100,000 103,000 200,000 75,000 . 200,000 180,000 195,000
210,000
150,000
oowrrrED TO DATE TO DATE
813,977 588,310 202,313 282,229 462,639 131,484 106,880 561,116
97,312 144,327 404,245 406,996 11,846 28,656 31,509 86,855 201,039 39,877 76,003 58,006 145,334
39,990 230,890 49,150
92,080 20,577 57,944 ' 13,096
0 118,559
0 175,075 186,509 125,172
814,065 589,484 201,768 282,136 465,436 133,095 109,545 573,097
97,983 148,881 403,783 491,688 11,846 32,805 31,509 89,441 216,584 41,310 77,003 60,086 146,242
40,025 230,890 49,150
92,022 20,577 64,163 13,096
0 133,735
0 175,164 187,373 137,634
198,374 0
198,656
FINAL TOTAL ESI. COST COMP.
UOER EST. (OVER) OCMP. AUIH. AMT. DATE
EST. CL0S. DATE
REMARKS
815,000 705,000 203,000 285,000
560,000 131,000 109,500 573,000 98,000 149,000 404,000 1,800,000 58,000 32,000 32,000 89,000 240,000 44,000 77,000 58,000 147,000 44,000 230,000 49,000 91,000 21,000 130,000 32,000 103,000 200,000
0 176,436 187,000 110,000
( 5,000) 645,000 ( 3,000)
50,000 0
69,000 < 3,500) (13,000) ( 5,000)
11,000 ( 2,000)
0 0 23,000 128,000 ( 9,000) 0 ( 3,000) ( 3,000) ( 8,000) 0 0 (9,000) (2,000) (1,000) ( 577) 0 87,000 0 0 0 25,000 (7,000) 95,000
06/84 12/85 08/84 09/84 09/84 09/84 02/84 04/84 04/85 07/84 10/84 09/86 09/85 06/84
10/84 07/84 09/85 09/84 09/84 04/84 12/84 09/85 03/84 04/84 02/84 03/84 09/85 12/85 09/85 06/85 05/85 12/84 12/84 12/84
04/85 dosed to field charges. 02/85 Construction on hold.
04/85 Closed to field charges. 05/85 Closed to field charges. 04/85 Closed to field charges.
04/85 Closed to field charges. 04/85 Closed to field charges. 04/85 Closed to field charges. 07/85 Closed to field charges. 05/85 Closed to field charges. 05/85 Closed to field charges. 12/86 Engineering in progress. 12/85 Engineering in progress. 04/85 Closed to field charges 04/85 Closed to field charges. 04/85 Closed to field charges. 04/85 Revisions in progress. 04/85 Cloaed to field charges. 04/85 Closed to field charges. 05/85 Closed to field charges. 05/85 Closed to field charges. 12/85 Revisions in progress. 05/85 Cloaed to field charges. 05/85 Closed to field charges. 05/85 Cloaed to field charges. 05/85 Clbaed to field charges. 12/85
03/85 Closed to field charges. 12/85 Engineering scheduled. 08/85 Construction in progress 08/85 Closed to field charges. 03/85 Closed to field charges. 03/85 Closed to field charges. 05/85 Closed to field charges.
210,000 150,000
0 12/84 05/85 Construction in ness. VAB.0001184131
0 12/86 03/87 Engineering sch
e*
*
H5A5 F5C5
B5D5 H5B5 H5G5
Miscellaneous AEE Low Rislon Delay Manufacture -
Phase I
Rotary Dryer Optimization Lab Equipment Miscellaneous AEE
10/25/84
12/07/84 12/11/84 11/24/84 02/27/85
75,000
45,000 65,000 36,000 75,000
9,297
42,933 54 0 0
10,265
42,500 4,265
33,060 0
0 0 10/85 12/85 22 Projects approved.
0 0 04/85 07/85 Construction in progress. 0 0 12/85 03/86 Engineering in progress. 0 0 04/85 07/85 Engineering in progress. 0 0 10/85 12/85 Projects under review.
VAB.0001184132
mum mm
PROCESS ENGINEERING - R. A. Frohreich
Reactor
With the assistance of PED and R&D personnel, samples of the reactor head space were taken. Additional sampling will be conducted In April.
Line I Modernization
Engineering is continuing to provide assistance to the Mechanical Engineering group on this project.
Compound Rate Improvements
Work is continuing on the compound
improvement project
blender charge sizes for several products were calculated and
instituted. Changes to the Line III FCM conveyor were made. Line I
cycle time was investigated and work is ongoing with the Mechanical
Group about cycle time revisions.
Plant Stormwater Revisions
The AFE for this project was submitted for approval.
PA Fluff Containment Operating Procedures The operating procedures for this project are being prepared.
I
Reactor Rinse Optimization
All reactors were checked for cleanliness and summaries of findings were issued.
Line III Pellet Coating System
The design to provide a permanent pellet coating system for Line III is being prepared.
%
VAB.0001184133
PERSONNEL - R. A. MILLER
EMPLOYMENT None
TRANSFER/PROMOTION Vemeta Blanchard, from General Helper to Compound Utility A.C. Pettus, from Lead Operator to "A" Operator William J. Davis, from General Helper to Compound Utility Norman Clay, from Compound Utility to General Helper Dave Gathings, from General Helper to Compound Utility Ralph D. Flippo, from General Helper to "A" Operator
RETIREMENT Aubrey Sanders
TERMINATIONS None
TO/FROM LEAVE OF ABSENCE None
CONOCO CHEMICALS Aberdeen, Mississippi
March 1985
MONTHLY PE
EL REPORT
Salaried Employees Hourly Employees Total Employees
67 154 **
221
Minority Employees # %
Salaried
8
12
J
Hourly
64
42
Total 72 33
New Employees
Terminations
0 0
Hourly Min. Hired % Min. Hired
Hourly Min. Term. % Min. Term.
0 b u 0
DEPARTMENTS
Warehouse Gen. Plant Maintenance Laboratory Compound
Vinyl
1
*
'
J, - *
*
Plasticizer
PAR * EMPLOYEES MIN. BMP. . % MIN.
16 14
7 50
11 11
6 55
53 39 22 21
7 18
+
5 24
41 33 26 79
36 32 12 38
44
1 25
NEW HIRES YTD
00
TERM. YTD TURNOVER
00
0
0 0 00 0
0 0 00 0
0 0 00 0
0 0 00 0
0 0 0 1 3%
0 0 0 JO 0
YTD
0 0 0 0'-- 0 3% 0
Number of Applicants:
Month
0 Year to Date
APPLICANT BREAKDOWN:
# Minority
0
% Minority
* Female 0 % Female
0
0 0
>
Hires (Hourly)
Month
0
Year to Date
Terminations (Hourly) :
Month
0
Year to Date
Overall Turnover
0
Projected Annual Turnover
0
2
5.2 &
* Includes one temporary part-time employee dr * One employee retired
VAB.0001184135
OVERTIME AND ABSENTEEISM
rtaient WAREHOUSE
maintenance
LAB COMPOUND VINYL PLASTICIZER UTILITY BOILER GENERAL PLANT
TOTAL
Stra.ght Time Hour) Worked
2256.00 4966.75 3227.50 5707.25 5618.00
564.50 659.00 592.00 23591.00
Overtliee Hours Worked Controllable(1) Non-Controllable(2)
327.75
0
609.25
0
326.75
0
229.00
0
619.50 31.25
48 0
13.25
0
1.00
0
2157.75
48
Overtime as a Z Of Straight Time
14.53 12.27 10.12 4.01 11.88 5.54 2.01
.20 9.35
Absence Hours' Lost 0
165 159 130
38 4
13 0 509
Absence as a X of Straieht Time Sickness Other Total Fiscal Y T*D
0
00
4.88
2.90
.42 3.32
3.13
4.83
.09 4.93
6.41
1.47
.81 2.28
3.60
.21
.46 .68
6.54
0
.71 .71
.86
0
1.97
1.97
1.92
0 0 0 .60
1.68
.48 2.16
4.47
(1) Controllable Overtime - all overtime excluding overtime due to working regular hours on a holiday and working the sixth day in operations. (2) Non-Controllable Overtime - that overtime due to working regular hours on a holiday and working regular hours on the sixth day in operations
*
4MI
l
*
VAB.0001184136
ENERGY CONSERVATION - S. C. Hillman I. Plant Operations Total energy consumption for March was 121.822 MMM BTUs. Energy consumption decreased to 2517 BTU/lb. from 2603 BTU/lb. in February. An adjusted CMA reduction of 53.8% was obtained for the month. The CMA values for fiscal 1985 are 53.8% adjusted and 39.5% unadjusted.
II. Plant Energy Conservation Program A. Maintenance There were sixty-one energy related items completed in March. Thirty-nine steam leaks were repaired and twenty-two stea trap repairs were made. B. Steam Trap Survey
\
The survey for the vinyl area identified one steam trap item for repair. The majority of the traps were not in service.
VAB.0001184137
ENERGY CONSERVATION DATA
Month Production, MM Lbs.
1985 March
1984 March
Resin Dry Blend Compound Plasticizer
Natural Gas
TOTAL
36.1 5.1 5.9 1.3
48.4
36.5 4.5 5.1 1.2
47.3
Consumption, MSCF Conversion, BTU/SCF Energy Consumption, MMM BTU Energy Consumption, BTU/lb.
Electricity
63993 1020
65.273 1349
69152 1020
70.536 1490
Consumption, MM KWH Conversion, BTU/KWH Energy Consumption, MMM BTU Energy Consumption, BTU/lb.
Propane
5.6549 1000
56.549 1168
5.4699 1000
54.699 1155
Consumption, M Gal. Conversion, BTU/Gal.ft Energy Consumption, MMM BTU Energy Consumption, BTU/lb.
Total
0 92000
0 0
0 92000
0 0
Energy Consumption, MMM BTU Energy Consumption, BTU/lb.
CMA Reduction (%)
121.822 2517
125.234 2645
Adjusted Unadjusted Fiscal 1985 Year-to-Date
Performance
53.8% Adjusted 39.5% Unadjusted
53.8 40.2
50.8 37,7
Boilers
Combustion Efficiency %
Mar .> 1985
Mar., 1984
No. 1 No. 2 No. 3
-- (1) 83.5
83.5
83.9 83.8 83.6
Note (1): Boiler no. 1 was not used during the month.
VAB.0001184138
ENVIRONMENTAL - V. E. Messick
Water
All wastewater parameters were within NPDES permit limitations during March
A State performance audit Inspection of permit sampling and analytical procedures was performed at our request as a check of our outside wastewater laboratory. No plant problems were noted. The State will Issue a report Including recommendations for improvement at the wastewater laboratory.
Consent Decree
Several draft responses to section 114 questions were Issued and reviewed
Hazardous Waste Management
The impact of the recent RCRA amendments on the plant was evaluated and documented.
City Water Backflow Prevention
The Mississippi State Board of Health reviewed the proposed design to Improve backflow prevention between the city water supply and the plant process water supply. They have requested that we supply them additional information.
*
ii& fr~* lir-i. . .
'j
....
VAB.0001184139
TABLE I -HATER COMPLIANCE WITH
*
A
Flow GPM
Jan. - Ave. 941 Max. 1189
Feb. - Ave. 878 Max. 1327
Mar. - Ave. 903
Max. 1016
NPDES PERMIT PARAMETERS
BOD PPM LB./DY.
13 158
22 298
14 157 20 228
COD PPM LB./DY.
30 352 36 474
29 328 39 444
Sus. Solids PPM LB./DY.
13 156 16 190
12 133 18 195
9 93 10 122
30 330 38 464
13 144 19 204
Diss. NH3
o2 LB./DY Ph
8.4 10.4
1.7 7.7 3.7 7.9
9.1 11.2
1.2 8.Q 1.4 8.2
8.9 9.5
1.1 8.0 1.2 8.2
Apr. - Ave. Max.
May - Ave.' Max.
June - Ave. Max.
*
July - Ave. Max.
t
h.
ig. - Ave. Max.
Sdpt. - Ave. Max.
Oct. Ave. Max.
Nov. - Ave. Max.
Dec. - Ave. Max.
NPDES Permit Li mi ts - December 1 through April 30
Ave.
Max.
NPDES Ave. Max.
-
-
Permit
-
32 43 Limits 25 40
431 800 - May 1 357 744
through -
1462 2713
November 30 1212 2523
-
674 7.0
1396
674 >7.0
1396
13 6.0-8.5 28
13 6.0-8.5 28
VAB.0001184140
LABORATORY - W. H. McNeese
i
RCAs Entered During March:
ACP-Donnelly AJP-022685-UTC
ACP-030885
Donnelly Corp. United Tech. Corp.
Master/Halco
48562 Blk. 5425
45541 Nat.
Mixed Material Wet Resin/Hard
Particles Streamers
Waivers Received
Customer
Product
Reason
No.
American Hoechst
5305
Particle Size
1 R/C 1 H/T
American Hoechst
5305
Bulk Density
1 H/T
Athol
5425
Static Flow
3 H/T
Carlon
5385-3
Particle Size
5 R/C
Charlotte Pipe
5265
Particle Size
1 R/C
Columbia Plastics
5385-3
Static Flow
1 H/T
Conductor Products
5425
Static Flow
2 H/T
DAS Terminal
5305
Bulk Density A Particle Size 1 R/C
DAS Terminal
5305
Particle Size
3 R/C
DAS Terminal
5305
Viscosity
1 R/C
Diversitech General 5385-1
Particle Size
1 R/C
Ecodyne
5385-3
Particle Size
1 H/T
Excel
5465
Static Flow
1 H/T
Genova Inmont Intex
5265 5305 5305
Particle Size & Viscosity Particle Size Particle Size
1 R/C 1 B/B 2 R/C
Macklinburg-Duncan
5425
Static Flow
1 H/T
Nib co 0*Leary Terminal Tenex Uniroyal
Vulcan
5305 5385-1 15041 CB50 5305
5385-3
Particle Size
3 H/T
Color
1 R/c
Hard Particles
1 R/c
Bulk Density & Particle Size Particle Size
1 R/C 1 B/B
2 R/C
LABORATORY - Continued
Quality Control Testing
Re 8 in
Regular Samples - 413 Total Batches Tested - 878 Bag Blends - 6 Bulk Shipments - 248 (Railcars - 163;
Trucks -85)
Dry Blend
Blenders Produced - 796 Blenders Tested - 531 Blenders Adjusted 1.8% Bulk Shipments - 45 (Railcars 22;
Trucks - 23)
Compound
Blenders Produced - 939 Blenders Adjusted - 1.0% Bulk Shipments - 21 (Railcars - 15;
Trucks - 6)
RVCM of In-Process Samples
The following is a summary of residual VCM results on in-process
samples. None of the reactor dally averages exceeded 400 ppm during the month of March.
Number of Samples Average RVCM, ppm
RVCM of Shipment Samples
Reactor
________ Drier
Slurries52655305
847 69
161
156 5.5 1.4
The following is a summary of the residual VCM analysis of shipment samples for the month of March.
Product
Number of Samples Average RVCM, ppm
5265
5305
5385
0.6 0.8
5425
5465
7 0.3
VAB.0001184142
Administrative Services - W. F. Higginbotham
Shipment by Product - M/lbs.
Resin Plasticizer
Dry Blend Compound
Total
28*739
666
5*061 6*179
40*645
of Shipments by Node
Resin - Bulk Plastic Dry BY Compou
0*T,
SO
O.T
Year-to Date
293*089
. 3,528
26,117 26*162 348*896
CPU CTR Total 6
Number of Shipment by*Month-Year-to Date
January February March
April May June July August Sept ember October November December
176 69 147 47 172 77
150 65 185 82 168 68
CPU CTR Total
62 10
18
48 7 20
59 15' 17
82 417 75 1 345 32 3 375
K
64 9 28 52 3^ 41 9 23 80 420 37 11 19 91 394
VAB.0001184143
Activity Report - Finished Goods David Whitaker
MARCH 31, 1985
MATERIAL. HANDLING REPORT
Packaged Resin from Production Packaged Compound, Dry Blend from Prod. Transferred From Main to Prairie Transferred from Prairie to Prairie Transferred from Prairie to Main Reverse Transfer Resin to Plant Reverse Transfer Cmpd. to Plant Shipment from Warehouses Special Packaging
OFF-GRAPE IN STORAGE
MATERIAL
Sifter Overflow Resin "BC" Resin "HM Mill Scraps Compound MBCN Compound NHN Vacuum,Dust Collector,Vent Dust Dry Blend "0. G.M
Volumes
- Month Y.T.D.
n.8
136.2
TOTAL
M/Lbs.
542 3,625 2,665
121 420 233
----
4,207
-- ----
11,813
13 90 67
3 11
6
105
*
295
M/Lbs.
289 23
62 535
12
77 93 1,091
T/L
7 1
*
2 13
2 2__ 27
LOCATION
TOTAL SO. FT.
*
MAIN
-p h
PRAIRIE 12-1
48 12
12-2 12-3 12-4 12-5
22 21 22 21
>
12-6
21
12-7 12-8
21 21
TOTAL
209
ABERDEEN WAREHOUSE
CONTENTS
CMPD A CMPD(BC) DRY BLEND CMPD CMPD DRY BLEND
P
CMPD
VACCUM DUST MILL SCRAP SIFTER OVERFLOW CMPD O.G. DRY DLEND O.G.
COMPOUND-HOLD
RESIN-HOLD
DRY BLEND-HOLD RAW MATERIAL
4
RESIN A
COMPOUND
COMPOUND
/
{
.1 .3
5 1. 4
.8 1.5
.1 .1 ,3 .2 .1
1
*
.3 .1 .3 3 1.7 .3
DATE MARCH 31.1985
4
%
ESTIMATED POUNDS ON FLOOR OPEN TOTAL
. 4 7a
7.S
.5 1.4
.8 1. 5
1 -0 2.1 2.7 2.0
1.5
3.5
{
3.5
3.5
.8 1.7 2.5
7
i
1-1 2*4 3.5 1 # / 1 *K 3.5
.3 3.2 3.5
8.5 24.0 32.5
* VAB.0001184145
j +
*
ABERDEEN CHEMICAL PLANT INJURY PERFORMANCE
f
Wl
I
o
a CN
CO
*0 *
4A
Si
tKfi uj,
X
T+
t
30
**
*
4
4*
%* '
4
* *
!
V
i I
+1
*-- 1 ----------- k ------ 1 >
+
................ <
*
;
i
44
t
VAB.0001184146
mhp-1.
-? -
HMf
rfc
1
5000 4500 4000 3500 3000 2500 2000 1500
ENERGY USAGE
II I I
! 'M 1
Monthly 12-Month Moving Avg
K\
* t
VAB.0001184147
MONTHLY HOURLY TURNOVER VAB.0001184148
MM POUNDS
10.0 8.0
2.0 1.0
0
VAB.OOOl 184149
%
OFF-GRADE
5.0 4.0 3.0
b
2.0 1.0
0
4.0 3.0
2.0 1.0
0
4.0 3.0
2.0
1.0
r*
0
10/1/84 10/1/85
VAB.0001184150
t *
MM POUNDS MONTHLY
40 35 30
25
20
15
6
5 4
3
2
1
6
5 4 3
2
1
2
1
0
Oct.
ABERDEEN PLANT PRODUCTION
A)
MM POUNDS CUMUUTNE
Dec. Jan.
60
: 50
40
3 30 20
10
70 60
50 40
30
20
10
20
15 10
5
Mar.
19 84/85
June July
Sent. Oct.
----------- Budget - - - - Actual
Cumulative
VAB.0001184152
t.
1.03
1.02 1.01
ABEROEEN PLANT EFFICIENCY POUNDS
1.06 1 1.05
1.04
1.03 1.02 1.01
1.020 1.010
1.000
3fSTTmmmmm
1 L
l Ls "?' i jmPMMH
*m i
mmumm
^j!l1 *..
mmmmmmtmmrnmmmm
mm
mm
mm*m
'rM#tll1'if"fM1I1
vpmm\nmrn
"+t *Ul!
mm
^ Mim
*********
rnmmrn^mm
****
mm(*4fr*^*pj***#^^
m Mf
*m+ mmmmm
mm
***** mmmmmrmmmrnmmmm
M*WW
****
*p
w ***
*f *11 ^*1
***** i*M*
mm fM*N
mmmmrnmmtum
NMh mm
rt*
JMM*
*****
mmmm mmrnmm
4w *
I w
** wMlfiapW -
ihM*
r h P1
*****
t
****#*<
*****
H**
rr
. .... ... ... . -
mm*** 4Wtt
n.
---------------------
i ii i
r 3____________
mm vfa U*H
1Awn
-- >-- -'-* " -- ---- --
.
Tr -
~ --i. ^ . '
1i
|
1.200
1.150
1.100
1.050
m+m
i -ir. .* _
ijlltl-.i. ._
i9 61/85
Monthly Cumulative
i
VAB.0001184153